12.2 Carrying Out the Practical: Inspection, Tests, Verification & Documentation
City & Guilds 2391-52 Combined Inspection & Testing of Electrical Installations Exam
Track your progress as you read
Finished sections get a check mark.
1 Introduction & Exam Overview
1.1 About the 2391-52 Exam 1.2 How to Use This Guide & Open-Book Exam Strategy
2 Chapter 2: Statutory & Non-Statutory Documents
2.1 Statutory Documents 2.2 Non-Statutory Documents 2.3 Roles, Responsibilities & the Statutory/Non-Statutory Relationship
3 Chapter 3: Certification & Documentation
3.1 The Electrical Installation Certificate (EIC) & Schedules 3.2 The Minor Electrical Installation Works Certificate (MEIWC) 3.3 The Electrical Installation Condition Report (EICR) & Schedules 3.4 Why the Documents Exist: Reasons, Information Needed, Recording & Retention
4 Chapter 4: Initial Verification & Safe Isolation
4.1 Safe Isolation & Safety Management 4.2 Visual Inspection Requirements 4.3 Initial Verification: Requirements & Process 4.4 Additions & Alterations to an Existing Installation 4.5 Inspection Methods: The Senses, Verifying Items & IP Classification
5 Chapter 5: Sequence of Tests & Test Instruments
5.1 The Correct Sequence of Tests 5.2 Test Instruments: Selection, Calibration & Accuracy 5.3 Factors That Affect Test Results & Tests That May Be Unnecessary at Periodic Inspection
6 Chapter 6: Continuity Testing
6.1 Continuity of Protective Conductors (R1+R2) 6.2 Continuity of Ring Final Circuits (r1, rn, r2) 6.3 Main & Supplementary Protective Bonding Continuity
7 Chapter 7: Insulation Resistance & Polarity
7.1 Insulation Resistance Testing 7.2 Polarity Verification 7.3 Verifying SELV, PELV & Electrical Separation
8 Chapter 8: Earth Fault Loop Impedance
8.1 Ze & Zs Measurement 8.2 Zs Limits, Disconnection Times & the 0.8 Rule 8.3 Prospective Fault Current (PFC/PSCC)
9 Chapter 9: RCD & Earth Electrode Testing
9.1 RCD Testing 9.2 Earth Electrode Resistance on TT Systems
10 Chapter 10: Periodic Inspection & EICR Reporting
10.1 Purpose, Scope & Limitations of Periodic Inspection 10.2 Sampling & Extent of Inspection 10.3 Observation Classification Codes C1/C2/C3/FI 10.4 Outcomes, Inspection Intervals & Completing the EICR
11 Chapter 11: Phase Sequence, Functional Testing & Voltage Drop
11.1 Check of Phase Sequence 11.2 Functional Testing 11.3 Verification of Voltage Drop
12 Chapter 12: The 2391-502 Practical Assignment
12.1 The Practical Assignment & Establishing a Safe System of Work 12.2 Carrying Out the Practical: Inspection, Tests, Verification & Documentation
12.2 Carrying Out the Practical: Inspection, Tests, Verification & Documentation
Key Takeaways Explain This Topic AI
AC5.3 to AC5.7 take you from inspection through testing and verification to completed certification - the paperwork is assessed, not just the readings
On the combined assignment you produce both initial-verification and periodic-inspection outputs, so you must switch between ticking a schedule of inspections and coding observations
Every recorded value must be a real measurement with its units and the right number of decimal places; ticks and blanks in a test-results column are marked as incomplete
Verifying results (AC5.6) means comparing each value against the correct limit for the actual protective device and stating the conclusion - a written Zs is worth nothing without the comparison
Leave time for the documentation: assessors routinely see candidates test well and then run out of time with the certificates half finished
Last updated: August 2026
AC5.3 and AC5.4 — Inspection and the Schedule of Inspections
The inspection comes first , before any instrument is connected, and it is carried out against the schedule of inspections in BS 7671 rather than from memory. Work through the schedule item by item and physically look at each one. The assessor will notice if you tick a line about the condition of conductor connections without having opened an accessory.
Typical items include the presence and adequacy of earthing and bonding conductors, the condition of conductor connections, correct cable selection and current-carrying capacity, methods of basic and fault protection, the presence of RCDs and their correct type, identification and labelling, the condition of enclosures and their IP integrity, and the suitability of accessories for the external influences of the location.
Marking the schedule
Remember which document you are producing — this is exactly the distinction from section 4.5:
- Document How items are marked
- Schedule of inspections for an EIC Acceptable (tick), or N/A — no observation codes on new work
- Schedule of inspections for an EICR Acceptable condition, or C1 / C2 / C3 / FI , plus N/A and LIM
On the combined 2391-52 assignment you produce both , so you have to switch modes deliberately. Carrying C-codes onto the EIC schedule is a common and avoidable error.
AC5.5 — Carrying Out the Tests
Work the sequence from Chapter 5 and do not improvise the order. For the initial-verification part of the assignment that means dead tests first, in the Regulation 643 order, then energise and complete the live tests.
Practical points the assessor is looking for:
Null the leads at the start of each set of continuity measurements, and be seen to do it.
Set the correct range and test voltage before each test — 500 V DC for a 230 V circuit, not 1000 V.
Disconnect or link out equipment that the insulation resistance test would damage, and say why.
Measure at the furthest point for R1+R2 and Zs, and record the highest value.
Test RCDs at both start points (0° and 180°) and record the longer operating time.
Restore every temporary link and disconnection as you go. A link left in the board at the end is a serious defect, not an oversight.
Work tidily. Loose conductors, an open board left unattended, or an instrument left connected while you write are all noted.
AC5.6 — Verifying the Results
This criterion is the one candidates most often treat as automatic. Recording a value is not verifying it. Verification is the comparison and the conclusion.
For each result, state:
What the limit is , for the actual device installed — a 32 A Type B circuit-breaker has a Table 41.3 maximum Zs of 1.37 Ω; the same rating in Type C is half that.
Whether the measured value satisfies it , applying the 0.8 rule for a cold measurement.
What follows — compliant for an EIC, or the appropriate classification code for an EICR.
Result Compare against Typical conclusion if it fails
Continuity R1+R2 Expected value for the conductor size and route length Investigate a high-resistance joint or a parallel path
- Insulation resistance Table 64 minimum: 1.0 MΩ at 500 V DC C2 on an EICR where the value is below the minimum
- Polarity Correct at every point C1 where a reversal makes exposed metalwork live
- Zs Table 41.2 / 41.3 maximum × 0.8 C2 — disconnection time may not be met
- RCD operating time at IΔn 300 ms general, 130–500 ms Type S C2 — protection not effective
- Earth electrode RA Reg 411.5.3 note: above 200 Ω may not be stable Record and recommend improvement
On a condition report the same logic drives the overall outcome : any C1 or C2 makes it unsatisfactory, and C3 or FI alone does not.