14.2 Minimum and Additional DC Tests

City & Guilds 2922-34 Level 3 Award in the Installation and Maintenance of Small Solar Photovoltaic Systems Exam

Track your progress as you read

Finished sections get a check mark.

1 Introduction & Exam Overview

1.1 Current Exam Facts 1.2 Eligibility, Currency and Industry Recognition 1.3 Assessment Format and Permitted Materials

2 Key Documentation and Legislation

2.1 Health, Safety and Continuity Law 2.2 Building Regulations and Planning Permission 2.3 Waste, Transport and Battery Fire Documents

3 Non-Statutory Standards and Industry Guidance

3.1 BS 7671, IET Codes of Practice and Guidance Notes 3.2 MCS Standards MIS 3002, MIS 3012 and MGD Guides 3.3 Fire Guidance, Grid Codes and Manufacturer Instructions

4 Working Safely with Solar PV Systems

4.1 PV Electrical Hazards 4.2 Risk Assessment, Method Statements, Height and PPE 4.3 Dual-Supply Isolation and Prove-Dead

5 PV Cells, Modules and I-V Behaviour

5.1 Silicon Cell Technologies 5.2 Module Types and Building Integration 5.3 The I-V Curve, Irradiance, Temperature and Shading

6 Inverters, Inverter Functions and Metering

6.1 Inverter Types 6.2 Inverter AC, DC and Energy-Management Functions 6.3 Utility and Generation Metering

7 Array Behaviour, Architectures and Nameplate Symbols

7.1 Reverse Currents, Bypass Diodes and PID 7.2 Array Architectures 7.3 STC and Manufacturer Symbols

8 Site Performance: Pitch, Shade and Yield

8.1 Pitch, Orientation and Location 8.2 Shading, Loss Stack and MGD 005 8.3 Estimating Annual Yield

9 Array Capacity, DNO Connection and Equipment Siting

9.1 Calculating Maximum Array Capacity 9.2 G98, G99, G100 and Combined Generation 9.3 Equipment Siting and Permissions

10 DC Voltage, Current and Overcurrent Protection

10.1 DC Voltage and Current Multipliers 10.2 String Overcurrent Protection Rule 10.3 DC Circuit-Breakers and gPV Fuses

11 DC Isolation, Combiners, Connectors and Cables

11.1 DC Isolation and Switching 11.2 Combiner Boxes and PV Connectors 11.3 DC Cables and Earth-Fault Causes

12 DC Fault Monitoring, Surge Protection and Inverter Sizing

12.1 Insulation Monitoring, RCM and Earth-Fault Alarms 12.2 Electromagnetic Interference and DC Surge Protection 12.3 Inverter Sizing and the MPP Window

13 Inverter Location, AC Side and Labelling

13.1 Inverter Specification and Location 13.2 AC Isolation and G99 Relays 13.3 AC Cables, Voltage Drop and RCDs 13.4 Labelling the PV System

14 Testing, Commissioning, Handover and Maintenance

14.1 Initial Verification and DC Inspection 14.2 Minimum and Additional DC Tests 14.3 Handover, Client Briefing and Maintenance

15 Prosumer Installations, EEMS and Storage

15.1 Prosumer Terms and Vehicle Storage 15.2 Integrated Energy Management and the Smart Grid 15.3 G100 Export Limitation and Why Add Storage

14.2 Minimum and Additional DC Tests

Key Takeaways Explain This Topic AI

Minimum DC tests are continuity of earthing and/or equipotential bonding, polarity, insulation resistance, combiner polarity and voltage, string Voc, string circuit current, and functional tests.

Additional tests include I-V curve tracing, infrared thermography, voltage to ground, wet insulation resistance, and shade evaluation.

Confirm polarity before measuring Voc so the meter and inverter are not reverse-fed.

Compare Voc and Isc with the design values after STC correction for irradiance and temperature; a string about 10% low on Voc is not a pass.

Insulation-resistance test voltage is the value specified in BS EN 62446-1 and the IET CoP; isolate the inverter and SPDs so the test does not damage them.

Last updated: September 2026

Quick Answer: Minimum DC tests are continuity of earthing and/or equipotential bonding, polarity, insulation resistance, combiner polarity and voltage, string open-circuit voltage (Voc), string circuit current, and functional tests. Additional tests include I-V curve tracing, infrared thermography, voltage to ground, wet insulation resistance, and shade evaluation. Polarity is confirmed before Voc so the meter and inverter are not reverse-fed.

Minimum tests versus additional tests

BS EN 62446-1 groups commissioning tests so that every grid-connected array gets a defined minimum set, with extra tests used where the contract, the IET CoP, a fault investigation, or a performance dispute requires more evidence. The 2922 handbook expects you to know which tests are the minimum set and which are additional — and to know that order matters .

Test Minimum or additional What it proves

Continuity of earthing and/or equipotential bonding conductors Minimum Protective and bonding conductors are connected and continuous

Polarity Minimum Positive and negative are not swapped before any voltage measurement

Insulation resistance of the DC circuit Minimum Insulation to earth meets the value specified for the chosen test voltage

Combiner box polarity and voltage Minimum (where a combiner is fitted) Strings are landed on the correct polarities and voltages match

String open-circuit voltage (Voc) Minimum String length and connections match design, corrected for conditions

String circuit current (Isc or operational current) Minimum Current capability matches design under measured irradiance

  • Functional tests Minimum Inverter starts, G98/G99 protection operates, isolators operate
  • I-V curve test Additional Curve shape shows mismatch, shading, or series resistance
  • Infrared (IR) thermography Additional Hot connectors, bypass diodes, or cells under load
  • Voltage to ground Additional Imbalance or leakage from one polarity to earth
  • Wet insulation resistance Additional Insulation faults that only appear when the array is wet
  • Shade evaluation Additional Predicted shading versus actual stringing and time of day
  • Order: polarity before Voc

After visual inspection, continuity of bonding is a dead test: you are proving conductors, not measuring generation. The next electrical check on a completed string is polarity . Only when polarity is proven do you measure open-circuit voltage .

If you measure Voc first on a reversed string, the meter sees reverse voltage. Many instruments are not designed to be reverse-fed at array voltage. If the DC isolator is closed onto the inverter, reverse polarity can damage the inverter input. Polarity testers, a DC voltmeter with clearly identified leads, and a physical check of connector gender at the combiner all come before you treat a Voc figure as a commissioning result.

Then work the rest of the minimum set:

Isolate the inverter and any SPD that the insulation-resistance test voltage could damage.

Insulation resistance at the test voltage specified in BS EN 62446-1 and the IET CoP for that system voltage — do not pick a megger range from habit. Those documents tabulate the test voltage and the minimum resistance against system Voc. Using 5 kV because higher feels safer can destroy SPDs and inverter input circuits. Leaving the inverter connected can make the reading meaningless and can damage the unit.

Combiner polarity and voltage: each string landed correctly, voltages consistent with one another.

String Voc compared with design.

String circuit current compared with design (short-circuit current with a correctly rated procedure, or operational current under generation, as the CoP method in use requires).

Functional tests once the AC side is complete: inverter starts and generates, G98 or G99 loss-of-mains and related protection behaves as required for that connection type, DC and AC isolators operate and isolate.

Functional tests are not a substitute for the dead DC set. An inverter that starts on a sunny day can still be fed by a reversed spare string sitting in a combiner, or by insulation that was never tested because someone skipped the isolation step.

Comparing Voc and Isc with design

Nameplate Voc and Isc are standard test conditions (STC) : 1000 W/m², 25 °C cell temperature, air mass 1.5. On a real roof the irradiance is rarely 1000 W/m² and the cells are rarely 25 °C.

Voc falls as cell temperature rises (negative temperature coefficient). A hot summer roof can show Voc several percent below the STC string total even when every module is present. Correct using the module temperature coefficient and a measured or estimated cell temperature, and note irradiance because very low light also depresses Voc.

Isc (or operational current) scales mainly with irradiance . Measure irradiance in the plane of the array at the same time as the current. A string at 600 W/m² should not be failed for delivering about 60% of STC Isc if the correction has been applied.

Record the design string Voc and Isc, the correction method, the meter readings, and the pass/fail decision. Looks-about-right is not a result. Do not compare an uncorrected cold-morning Voc on one string with an uncorrected hot-afternoon Voc on another and call the difference a fault without doing the arithmetic.

Additional tests in brief

I-V curve tracing plots current against voltage from Isc to Voc. A notch or shelf suggests shading or a failed bypass diode. A slope change suggests series resistance (connectors, fuses, underrated cable). It is additional evidence, not a replacement for polarity and Voc.

Infrared thermography under load finds hot connectors, hot bypass diodes, and hot cells. It needs sufficient irradiance and generation as specified in the thermography method you are using; a first-fix array with the inverter not live will not show load-related hot spots.

Voltage to ground looks at each polarity relative to earth. A large imbalance can indicate an insulation fault on one pole that a combined IR test might still need follow-up to locate.

Wet insulation resistance finds faults that only appear when moisture bridges a damaged backsheet, a poorly glanded combiner, or a nicked cable in a wet roof void. It is not a substitute for the dry minimum IR test.

Shade evaluation checks that stringing does not put a chimney shadow across every module in one string at the time of day the design claimed was clear. It explains a low Isc that irradiance correction cannot justify.

Scenario: Voc 10% below the adjacent string

Two nominally identical strings. String A Voc matches the temperature-corrected design. String B is about 10% low at the same time, same irradiance.

Do not energise the inverter to see if MPPT corrects it — MPPT cannot invent missing voltage. Do not pass it as meter error; 10% is far outside typical DC meter uncertainty on a string voltage measurement.

Work the sequence:

Reconfirm polarity on string B. A reversed measurement or a reversed jumper will not be cured by a better irradiance reading.

Count modules and check the string diagram. On a ten-module string, 10% low is about one module missing or not in circuit. A single reversed module subtracts rather than adds, so the drop is about two module voltages (larger than 10% on a long string, but the same diagnostic family).

Check combiner fuses, landed ferrules, and unterminated tails.

Look for shading, mixed orientations stuffed into one string, or a damaged module.

Only then consider additional tests: I-V curve, thermography under load, voltage to ground.

Record string B as a fail against design until the cause is found and corrected. Commissioning is not an average of the good strings.

Loading diagram... Minimum DC test sequence