5.2 Fire Extinguishers, Means of Escape, LPG Storage & Emergency Evacuation Plans

CITB Site Management Safety Training Scheme SMSTS

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Legal Framework, CDM 2015 & Health and Safety Management

1.1 How the SMSTS Course and Examination Actually Work 1.2 Health and Safety at Work etc. Act 1974 (HASAWA) & Statutory Duties 1.3 Management of Health and Safety at Work Regulations 1999 & HSG65 (Plan-Do-Check-Act) 1.4 CDM 2015 Overview & Five Duty Holders (Client, Principal Designer, Principal Contractor, Designer, Contractor) 1.5 CDM 2015 Project Documentation: PCI, Construction Phase Plan & Health and Safety File 1.6 Statutory Notifications (F10), Enforcement Notices (Improvement/Prohibition), and Fee for Intervention (FFI) 1.7 RIDDOR 2013: Reporting Over-7-Day Injuries, Specified Injuries, Occupational Diseases & Dangerous Occurrences

2 Chapter 2: Risk Management, RAMS & Site Safety Leadership

2.1 Principles of Risk Assessment & Five Steps to Risk Assessment 2.2 Hierarchy of Control Measures & Risk Matrices 2.3 Developing, Reviewing, and Implementing Risk Assessments & Method Statements (RAMS) 2.4 Permit to Work (PTW) Systems for High-Risk Activities 2.5 Worker Consultation, Toolbox Talks, and Safety Leadership Culture 2.6 Behavioural Safety, Human Factors, and Accident Investigation Techniques

3 Chapter 3: High-Risk Site Operations: Height, Excavations & Confined Spaces

3.1 Work at Height Regulations 2005 & Hierarchy of Control for Height Work 3.2 Scaffolding Standards (TG20, BS EN 12811) & Statutory 7-Day Inspection Regimes 3.3 Mobile Elevating Work Platforms (MEWPs), Ladders, Tower Scaffolds & Fragile Roof Safety 3.4 Excavation Safety: Preventing Ground Collapse, Shoring, Battering & Edge Protection 3.5 Underground Services Avoidance (HSG47): Cable Avoidance Tools (CAT) & Genny Operation 3.6 Confined Spaces Regulations 1997: Risk Assessment, Atmosphere Testing & Rescue Procedures 3.7 Temporary Works Management: BS 5975-1, Coordinator Roles & Permits to Load and Strike

4 Chapter 4: Occupational Health, Chemical Safety & Physical Hazards

4.1 Control of Substances Hazardous to Health (COSHH) Regulations & Exposure Limits 4.2 Respirable Crystalline Silica (RCS), Dust Control & Respiratory Protective Equipment (RPE) 4.3 Asbestos Management on Construction Sites: Control of Asbestos Regulations 2012 4.4 Noise at Work Regulations 2005 & Hand-Arm Vibration Syndrome (HAVS) Exposure Action Values 4.5 Manual Handling Operations Regulations 1992, Ergonomics & Musculoskeletal Health 4.6 Health Surveillance, Medical Fitness & Workplace Hygiene/Wellbeing 4.7 Lead in Buildings: Control of Lead at Work Regulations 2002 & Blood-Lead Surveillance 4.8 Drugs and Alcohol at Work: Legal Framework, Site Policy, Testing & Support

5 Chapter 5: Fire Safety, Electrical Protection & Plant Operations

5.1 Fire Prevention on Construction Sites (HSG168), Fire Triangle & Hot Work Permits 5.2 Fire Extinguishers, Means of Escape, LPG Storage & Emergency Evacuation Plans 5.3 Electricity at Work Regulations 1989 & Safe Isolation Procedures 5.4 110V Reduced Low Voltage Systems, RCDs & Overhead Power Lines Safety (GS6) 5.5 Provision and Use of Work Equipment Regulations 1998 (PUWER) & Equipment Inspections 5.6 Lifting Operations and Lifting Equipment Regulations 1998 (LOLER), Crane Safety & Rigging

6 Chapter 6: Site Setup, Logistics, Welfare & Environmental Protection

6.1 CDM 2015 Schedule 2 Welfare Facilities Standards & Site Setup Requirements 6.2 Site Traffic Management, Pedestrian-Vehicle Segregation & Delivery Logistics 6.3 Site Inductions, Security, Signage & Competence Verification (CSCS/CPCS) 6.4 First Aid at Work Regulations 1981: Needs Assessment, First Aiders & Equipment 6.5 Environmental Protection: Waste Management (Duty of Care), Pollution Prevention & Noise Control 6.6 Mobile Workforce, Lone Working & Driving for Work

5.2 Fire Extinguishers, Means of Escape, LPG Storage & Emergency Evacuation Plans

Key Takeaways Explain This Topic AI

Fire extinguishers must conform to BS EN 3 color coding (red body with signal color band): Water (Signal Red), Foam (Cream), Dry Powder (Blue), CO2 (Black), Wet Chemical (Yellow).

Liquefied Petroleum Gas (LPG) cylinders must be stored upright in well-ventilated, secure outdoor compounds located at least 3 metres from buildings, boundary fences, and ignition sources.

Emergency escape routes must be kept clear, unobstructed, well-lit (with emergency lighting where natural light is insufficient), and provide a maximum travel distance to a safe escape point (e.g., 18m single direction, 45m alternative directions).

Fire evacuation plans require site-wide audible alarms (interconnected wireless call points on multi-storey sites), weekly alarm testing, clear assembly points, and nominated Fire Marshals.

Flammable liquids (petrol, thinners) must be stored in lockable, ventilated, fire-resistant stores or bunded cabinets capable of holding 110% of the largest container capacity.

Last updated: August 2026

Fire Extinguishers, Means of Escape, LPG Storage & Emergency Evacuation Plans

Effective fire safety management requires robust suppression capability, strict control over high-hazard substances such as Liquefied Petroleum Gas (LPG), clear emergency evacuation routes, and comprehensive site alarm networks. Under the Regulatory Reform (Fire Safety) Order 2005 and DSEAR 2002 (Dangerous Substances and Explosive Atmospheres Regulations), Site Managers must ensure that appropriate firefighting equipment is readily accessible and that every worker can evacuate to a place of total safety quickly and unhindered.

1. Portable Fire Extinguisher Selection and BS EN 3 Color Coding

All portable fire extinguishers provided on UK construction sites must comply with BS EN 3 . Extinguishers feature a rich signal red body with a specific color coding band located above or around the operating instructions to identify the extinguishing agent.

Fire Classification and Extinguisher Selection Matrix

Fire Class Combustible Material / Risk Extinguisher Type BS EN 3 Signal Band Color Primary Extinguishing Action & Electrical Hazards

Class A Organic Solids (wood, paper, cardboard, textiles) Water / Water Spray Signal Red Cools fuel below ignition temperature. DO NOT use on live electrical equipment due to electrocution risk.

Class A & B Flammable Liquids (petrol, diesel, oils, paints, solvents) Foam (AFFF) Cream Forms a floating blanket that smothers flames and seals flammable vapors. Safe near electrical equipment up to 1000V if dielectrically tested.

Class A, B, C & Electrical Multi-purpose, Flammable Gases, Flammable Liquids Dry Powder (ABC) Blue Knocks down flames rapidly by interrupting chemical chain reactions. Causes severe visibility reduction indoors and leaves corrosive residue on delicate electrics.

Electrical & Class B Live Electrical Equipment, Switchgear, Transformers Carbon Dioxide (CO2) Black Displaces oxygen and cools surrounding air. Leaves no residue (non-damaging to electronics). Horn becomes freezing cold during discharge.

Class F Cooking Oils and Deep Fat Fryers (Canteen kitchens) Wet Chemical Yellow Saponification (creates a thick soapy layer over burning oil) and rapid cooling.

2. Operating Extinguishers: The PASS Protocol

Site personnel must receive instruction on the safe operation of portable fire extinguishers using the universally recognized PASS protocol:

P — Pull: Pull the safety pin to break the tamper seal.

A — Aim: Aim the nozzle or hose low at the base of the fire (not at the flames above).

S — Squeeze: Squeeze the operating handle to release the extinguishing agent.

S — Sweep: Sweep the nozzle from side to side across the base of the fire until extinguished.

Extinguisher Maintenance Statutory Requirement: Extinguishers must undergo visual monthly inspection by site staff and formal annual servicing by a competent technician accredited to BS 5306-3. Water and foam extinguishers require discharge testing every 5 years; CO2 extinguishers require 10-year hydraulic pressure testing.

3. Storage and Handling of Liquefied Petroleum Gas (LPG)

Liquefied Petroleum Gas (propane and butane) is widely used on construction sites for bitumen boilers, space heating, and pipe soldering. LPG poses extreme fire and explosion hazards under DSEAR 2002 and the Highly Flammable Liquids and Liquefied Petroleum Gases Regulations 1972 . +-----------------------------------------------------------------------------------+

  • | LPG SAFE STORAGE COMPOUND |
  • +-----------------------------------------------------------------------------------+
  • | [Well-Ventilated Mesh Cage] • Located OUTDOORS at least 3m from buildings, |
  • | | [Propane] [Propane] | drains, boundary fences, and ignition sources. |
  • | | (Upright & Chained) | • Solid, level concrete/compacted ground. |
  • | +-------------------------+ • Warning signs: "HIGHLY FLAMMABLE GAS - |
  • | [Separated Full & Empty] NO SMOKING - NO NAKED LIGHTS". |
  • +-----------------------------------------------------------------------------------+

Critical LPG Safety Rules:

Density Hazard: LPG vapor is heavier than air. Leaking gas sinks to ground level and accumulates in trenches, basements, and drainage gullies, creating explosive pockets.

Outdoor Storage Compounds: Cylinders must be stored outdoors in locked, well-ventilated wire-mesh cages located at least 3 metres away from any building openings, cellars, drains, boundary walls, or combustible storage areas.

Vertical Orientation: Cylinders must ALWAYS be stored and transported upright with valves closed and protective caps fitted to prevent liquid LPG escaping through pressure relief valves.

Indoor Quantity Limits: Indoor cylinder use must be strictly minimized. Max indoor storage is restricted to 1x 47kg or 2x 11kg cylinders connected to operational equipment only.

Separation of Full and Empty: Full cylinders must be physically segregated from empty cylinders within the compound using clear identification signage.

4. Storage of Flammable Liquids (Petrol, Solvents, Thinners)

Bunded Storage: Flammable liquids must be stored in secure metal cabinets or outdoor bunded stores capable of containing 110% of the volume of the largest container (or 25% of the total aggregate volume stored, whichever is greater).

Safety Cans: Small quantities of fuel carried on site must be transported in approved metal safety cans equipped with self-closing lids and integral flame arrestors.

5. Emergency Escape Routes and Means of Escape

In a fire emergency, workers must be able to escape to a place of safety without reliance on external rescue operations.

Maximum Permissible Travel Distances

Under HSG168, maximum travel distances from any point on site to the nearest final fire exit or protected stairwell are strictly regulated:

Risk Category / Route Type High Fire Risk (e.g., Timber Frame / Solvents) Normal Site Risk (Enclosed Fit-Out) Low Risk / Open Site

  • Single Direction / Dead End 12 metres 18 metres 25 metres
  • Alternative Routes Available 25 metres 45 metres 60 metres

Escape Route Requirements:

Unobstructed Access: Corridors, stairwells, and doorways must be kept completely clear of materials, plant, scaffolding tubes, and waste at all times.

Direction of Swing: Fire exit doors must open in the direction of escape and be fitted with panic hardware (push bars) that require no key to operate from the inside.

Emergency Lighting: Battery-backed emergency escape lighting (providing at least 1 lux illumination along escape routes) is mandatory in enclosed spaces, basements, and windowless structures.

6. Site Fire Evacuation Plans and Alarm Systems

Every site must maintain a documented Fire Emergency Plan displayed on site notice boards and communicated during worker inductions.

Fire Alarm Infrastructure:

Small Open Sites: Simple rotary gongs, hand-held air horns, or triangle bells located at designated fire points are acceptable only where audible across the entire footprint.

Multi-Storey / Enclosed Sites: Interconnected wireless electronic fire alarm systems featuring manual call points (break-glass units) and sounders on every floor level are mandatory to provide instant site-wide warnings.

Evacuation Management & Fire Marshals:

Weekly Testing: Fire alarms must be tested at a fixed time every week (e.g., Monday 08:00) and recorded in the site Fire Logbook.

Fire Marshals (Wardens): Trained Fire Marshals must sweep designated zones upon alarm activation, direct workers to the assembly point, and cross-check the site sign-in register.

Fire Brigade Liaison: The Site Manager or Lead Fire Marshal must meet arriving Fire and Rescue Service teams to hand over site plans detailing structural hazards, LPG compound locations, and high-voltage isolation points.

Loading diagram... BS EN 3 Fire Extinguisher Selection & Class Matrix