3.7 Temporary Works Management: BS 5975-1, Coordinator Roles & Permits to Load and Strike

CITB Site Management Safety Training Scheme SMSTS

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Legal Framework, CDM 2015 & Health and Safety Management

1.1 How the SMSTS Course and Examination Actually Work 1.2 Health and Safety at Work etc. Act 1974 (HASAWA) & Statutory Duties 1.3 Management of Health and Safety at Work Regulations 1999 & HSG65 (Plan-Do-Check-Act) 1.4 CDM 2015 Overview & Five Duty Holders (Client, Principal Designer, Principal Contractor, Designer, Contractor) 1.5 CDM 2015 Project Documentation: PCI, Construction Phase Plan & Health and Safety File 1.6 Statutory Notifications (F10), Enforcement Notices (Improvement/Prohibition), and Fee for Intervention (FFI) 1.7 RIDDOR 2013: Reporting Over-7-Day Injuries, Specified Injuries, Occupational Diseases & Dangerous Occurrences

2 Chapter 2: Risk Management, RAMS & Site Safety Leadership

2.1 Principles of Risk Assessment & Five Steps to Risk Assessment 2.2 Hierarchy of Control Measures & Risk Matrices 2.3 Developing, Reviewing, and Implementing Risk Assessments & Method Statements (RAMS) 2.4 Permit to Work (PTW) Systems for High-Risk Activities 2.5 Worker Consultation, Toolbox Talks, and Safety Leadership Culture 2.6 Behavioural Safety, Human Factors, and Accident Investigation Techniques

3 Chapter 3: High-Risk Site Operations: Height, Excavations & Confined Spaces

3.1 Work at Height Regulations 2005 & Hierarchy of Control for Height Work 3.2 Scaffolding Standards (TG20, BS EN 12811) & Statutory 7-Day Inspection Regimes 3.3 Mobile Elevating Work Platforms (MEWPs), Ladders, Tower Scaffolds & Fragile Roof Safety 3.4 Excavation Safety: Preventing Ground Collapse, Shoring, Battering & Edge Protection 3.5 Underground Services Avoidance (HSG47): Cable Avoidance Tools (CAT) & Genny Operation 3.6 Confined Spaces Regulations 1997: Risk Assessment, Atmosphere Testing & Rescue Procedures 3.7 Temporary Works Management: BS 5975-1, Coordinator Roles & Permits to Load and Strike

4 Chapter 4: Occupational Health, Chemical Safety & Physical Hazards

4.1 Control of Substances Hazardous to Health (COSHH) Regulations & Exposure Limits 4.2 Respirable Crystalline Silica (RCS), Dust Control & Respiratory Protective Equipment (RPE) 4.3 Asbestos Management on Construction Sites: Control of Asbestos Regulations 2012 4.4 Noise at Work Regulations 2005 & Hand-Arm Vibration Syndrome (HAVS) Exposure Action Values 4.5 Manual Handling Operations Regulations 1992, Ergonomics & Musculoskeletal Health 4.6 Health Surveillance, Medical Fitness & Workplace Hygiene/Wellbeing 4.7 Lead in Buildings: Control of Lead at Work Regulations 2002 & Blood-Lead Surveillance 4.8 Drugs and Alcohol at Work: Legal Framework, Site Policy, Testing & Support

5 Chapter 5: Fire Safety, Electrical Protection & Plant Operations

5.1 Fire Prevention on Construction Sites (HSG168), Fire Triangle & Hot Work Permits 5.2 Fire Extinguishers, Means of Escape, LPG Storage & Emergency Evacuation Plans 5.3 Electricity at Work Regulations 1989 & Safe Isolation Procedures 5.4 110V Reduced Low Voltage Systems, RCDs & Overhead Power Lines Safety (GS6) 5.5 Provision and Use of Work Equipment Regulations 1998 (PUWER) & Equipment Inspections 5.6 Lifting Operations and Lifting Equipment Regulations 1998 (LOLER), Crane Safety & Rigging

6 Chapter 6: Site Setup, Logistics, Welfare & Environmental Protection

6.1 CDM 2015 Schedule 2 Welfare Facilities Standards & Site Setup Requirements 6.2 Site Traffic Management, Pedestrian-Vehicle Segregation & Delivery Logistics 6.3 Site Inductions, Security, Signage & Competence Verification (CSCS/CPCS) 6.4 First Aid at Work Regulations 1981: Needs Assessment, First Aiders & Equipment 6.5 Environmental Protection: Waste Management (Duty of Care), Pollution Prevention & Noise Control 6.6 Mobile Workforce, Lone Working & Driving for Work

3.7 Temporary Works Management: BS 5975-1, Coordinator Roles & Permits to Load and Strike

Key Takeaways Explain This Topic AI

There are no bespoke temporary works regulations; the legal duties come from CDM 2015 Regulation 19 (stability of structures), PUWER, the Work at Height Regulations 2005 and HASAWA, with BS 5975-1:2024 supplying the industry-standard procedural control.

BS 5975:2019 was withdrawn and split in 2024 into BS 5975-1:2024 (management procedures) and BS 5975-2:2024 (falsework design and implementation).

The Temporary Works Coordinator is formally appointed by the principal contractor and must have the authority to stop work — a coordinator who cannot halt an unsafe pour has not been properly appointed.

Every temporary works item needs a design brief, a design, an independent design check proportionate to its check category, an entry in the temporary works register, and formal permits before it is loaded or struck.

The permit to load authorises the structure to take its design load; the permit to strike authorises dismantling — striking falsework early, before the permanent structure has gained strength, is a classic fatal failure.

Last updated: August 2026

Why Temporary Works Kill People

Temporary works are the engineered structures that make permanent construction possible and are then removed. They exist only for weeks or months, they are often assembled from reused components by operatives who did not design them, and they are frequently loaded to their limit on the day of a concrete pour. That combination makes them more dangerous than the permanent works they support . The Health and Safety Executive (HSE) has consistently identified temporary works as a high-risk area, and the classic incident pattern is depressingly repeatable: an inadequate design brief, an unauthorised change made on site to suit the plant that turned up, no independent check, and nobody formally accountable for saying "yes, you may load this".

CITB lists temporary works as a learning outcome in its own right within Module 3 of the SMSTS syllabus. As a site manager you are unlikely to design them, but you are very likely to be the person who receives a request to pour, prop or strike — and the person who has to say no.

What Counts as Temporary Works

HSE's definition is deliberately broad. Temporary works to provide structural support include:

  • Shoring and trench support for excavations (trench boxes, sheet piling, drag boxes, hydraulic props)
  • Propping of walls and floors during alteration and refurbishment
  • Falsework supporting above-ground concrete pours until the concrete gains design strength
  • Formwork giving wet concrete its shape and containing its pressure
  • Scaffolds used for access or as loading platforms
  • Haul roads, crane pads and working platforms for tracked and outrigger-mounted plant
  • Façade retention schemes and needling in refurbishment
  • Permanent works used temporarily — for example a partially cured slab used to support plant

Temporary works also cover items that people forget are engineered at all: site fencing and hoarding (which must resist wind loading), welfare and office units and their foundations, and earthworks including stockpiles that will later be removed. A hoarding blown flat across a footpath in a winter gale is a temporary works failure, not bad luck.

The Legal Framework

There is no specific set of "Temporary Works Regulations" . HSE states plainly that each organisation may choose how it arranges and manages temporary works safety. The legal duties come from general law:

Legal source What it requires

CDM 2015 Regulation 19 (Stability of structures) All practicable steps must be taken to prevent collapse of any new or existing structure that becomes unstable or temporarily weakened because of the construction work; any buttress or temporary support must be designed, installed and maintained to withstand foreseeable loads; and no structure may be overloaded so as to create danger

CDM 2015 Regulation 22 and Schedule 3 Excavations must be inspected by a competent person at the start of every shift, after any event likely to have affected stability, and after any accidental fall of material, with written reports where required by Regulation 24

PUWER 1998 Temporary works equipment (props, trench boxes, falsework components) is work equipment: suitable, maintained, inspected and used only by trained people

Work at Height Regulations 2005 Working platforms, including scaffolds used as temporary works, must be of sufficient strength and stability

HASAWA 1974 sections 2, 3 and 6 General duties to employees, non-employees affected by the work, and duties on those supplying equipment

BS 5975-1:2024 is a British Standard, not law. It is nonetheless the recognised industry consensus on good practice, and following it is the most straightforward way to demonstrate compliance with the duties above. A contractor departing from it must be able to explain what it does instead.

The 2024 Standard Split — Know the Current Reference

BS 5975:2019 has been withdrawn and divided into two parts , published by BSI in February 2025:

BS 5975-1:2024 — Temporary works. Management procedures for the control of temporary works. Code of practice (the procedural control, roles, register and permits)

BS 5975-2:2024 — Temporary works. Falsework: design and implementation. Code of practice (permissible stress and limit state design of falsework, wind force calculation)

Citing "BS 5975:2008" or "BS 5975:2019" in a method statement dates the document. Both are withdrawn.

The BS 5975-1 Role Structure

Role Appointed by Core responsibilities

Designated Individual (DI) The contracting organisation, at senior level Owns the company temporary works procedure; appoints the TWC in writing and confirms their competence

Temporary Works Coordinator (TWC) The principal contractor / DI, formally and in writing Maintains the temporary works register; ensures every item has a design and a proportionate design check; issues permits to load and permits to strike; coordinates the temporary and permanent works interface; has authority to stop the work

Temporary Works Supervisor (TWS) The TWC, where the scale of the job justifies it Supervises erection, use, inspection and dismantling on site; reports to the TWC; does not issue permits

Temporary Works Designer (TWD) The contractor or a specialist consultancy Produces the design, calculations and drawings from the design brief; specifies materials, loading limits and erection/dismantling sequence; responds to site queries and changes

Design checker Independently of the designer Verifies the design to the appropriate check category before it is issued for construction

HSE's guidance is emphatic on one point: the TWC must be formally appointed and have adequate authority to carry out the role, including stopping the work if it is not satisfactory . On a complex project this is typically a chartered civil or structural engineer based on site; on a simple job the main contractor may hold the role and buy in engineering advice. On smaller projects one person may hold more than one role, but each role must be explicitly assigned and documented — and a designer should not be the sole checker of their own design.

CITB runs the Temporary Works Coordinator Training Course (TWCTC) and Temporary Works Supervisor Training Course (TWSTC) within the same Site Safety Plus suite as SMSTS, and holding SMSTS is recognised as useful prior knowledge for both.

The Procedural Cycle a Site Manager Must Police

Design brief. A written statement of what the temporary works must do: geometry, loads (including plant, wind and construction traffic), ground conditions, constraints and the permanent works interface. A vague brief guarantees an inadequate design.

Design. Produced by a competent designer to a recognised standard, with calculations, drawings, materials, load limits and the erection and dismantling sequence.

Independent design check. BS 5975 grades the required independence by check category , escalating with complexity and consequence — from standard, restricted solutions at the lowest category through simple and then complex or comprehensive designs, up to genuinely innovative designs which require a checker from a separate organisation entirely. A design check certificate records the outcome.

Temporary works register. A live project document listing every temporary works item, its designer, check category, check status, permit dates, inspection regime and removal authorisation. It is the audit trail if anything fails.

Pre-erection inspection. Components checked for damage, correct type and correct quantity before assembly — reused props with bent pins and missing pins are endemic.

Erection to the design and method statement. No site improvisation. Any proposed change goes back to the designer.

Permit to load. Issued by the TWC once erection is verified as complete and compliant. It authorises the structure to accept its design load — for example before a concrete pour into formwork, or before fill is placed against a retaining structure. No permit, no pour.

In-service inspection and monitoring for the life of the temporary works, with excavations inspected at the start of every shift under CDM 2015.

Permit to strike / dismantle. Issued by the TWC only when it is confirmed that the permanent works can safely carry the load — for falsework, typically on the basis of concrete strength results, not the calendar. Premature striking is a recurring cause of multi-fatality collapses.

Where Site Managers Get Caught

The commercial pressure to pour on schedule is the mechanism by which nearly every temporary works failure occurs. Three practical rules protect you. First, treat the permit to load and the permit to strike as non-negotiable hold points — they are the only two moments where the whole procedural chain is verified before something can go wrong irreversibly. Second, treat any on-site modification as a new design : swapping prop types, changing centres, adding a plant load or altering the ground bearing conditions all invalidate the original calculations. Third, remember the interface risk — the most dangerous temporary works questions are usually about the permanent structure, such as whether a slab has cured enough to be back-propped or whether a wall being needled is carrying more than the drawings suggest. Those questions go to a designer, not to a gang foreman.