3.1 Work at Height Regulations 2005 & Hierarchy of Control for Height Work

CITB Site Management Safety Training Scheme SMSTS

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Legal Framework, CDM 2015 & Health and Safety Management

1.1 How the SMSTS Course and Examination Actually Work 1.2 Health and Safety at Work etc. Act 1974 (HASAWA) & Statutory Duties 1.3 Management of Health and Safety at Work Regulations 1999 & HSG65 (Plan-Do-Check-Act) 1.4 CDM 2015 Overview & Five Duty Holders (Client, Principal Designer, Principal Contractor, Designer, Contractor) 1.5 CDM 2015 Project Documentation: PCI, Construction Phase Plan & Health and Safety File 1.6 Statutory Notifications (F10), Enforcement Notices (Improvement/Prohibition), and Fee for Intervention (FFI) 1.7 RIDDOR 2013: Reporting Over-7-Day Injuries, Specified Injuries, Occupational Diseases & Dangerous Occurrences

2 Chapter 2: Risk Management, RAMS & Site Safety Leadership

2.1 Principles of Risk Assessment & Five Steps to Risk Assessment 2.2 Hierarchy of Control Measures & Risk Matrices 2.3 Developing, Reviewing, and Implementing Risk Assessments & Method Statements (RAMS) 2.4 Permit to Work (PTW) Systems for High-Risk Activities 2.5 Worker Consultation, Toolbox Talks, and Safety Leadership Culture 2.6 Behavioural Safety, Human Factors, and Accident Investigation Techniques

3 Chapter 3: High-Risk Site Operations: Height, Excavations & Confined Spaces

3.1 Work at Height Regulations 2005 & Hierarchy of Control for Height Work 3.2 Scaffolding Standards (TG20, BS EN 12811) & Statutory 7-Day Inspection Regimes 3.3 Mobile Elevating Work Platforms (MEWPs), Ladders, Tower Scaffolds & Fragile Roof Safety 3.4 Excavation Safety: Preventing Ground Collapse, Shoring, Battering & Edge Protection 3.5 Underground Services Avoidance (HSG47): Cable Avoidance Tools (CAT) & Genny Operation 3.6 Confined Spaces Regulations 1997: Risk Assessment, Atmosphere Testing & Rescue Procedures 3.7 Temporary Works Management: BS 5975-1, Coordinator Roles & Permits to Load and Strike

4 Chapter 4: Occupational Health, Chemical Safety & Physical Hazards

4.1 Control of Substances Hazardous to Health (COSHH) Regulations & Exposure Limits 4.2 Respirable Crystalline Silica (RCS), Dust Control & Respiratory Protective Equipment (RPE) 4.3 Asbestos Management on Construction Sites: Control of Asbestos Regulations 2012 4.4 Noise at Work Regulations 2005 & Hand-Arm Vibration Syndrome (HAVS) Exposure Action Values 4.5 Manual Handling Operations Regulations 1992, Ergonomics & Musculoskeletal Health 4.6 Health Surveillance, Medical Fitness & Workplace Hygiene/Wellbeing 4.7 Lead in Buildings: Control of Lead at Work Regulations 2002 & Blood-Lead Surveillance 4.8 Drugs and Alcohol at Work: Legal Framework, Site Policy, Testing & Support

5 Chapter 5: Fire Safety, Electrical Protection & Plant Operations

5.1 Fire Prevention on Construction Sites (HSG168), Fire Triangle & Hot Work Permits 5.2 Fire Extinguishers, Means of Escape, LPG Storage & Emergency Evacuation Plans 5.3 Electricity at Work Regulations 1989 & Safe Isolation Procedures 5.4 110V Reduced Low Voltage Systems, RCDs & Overhead Power Lines Safety (GS6) 5.5 Provision and Use of Work Equipment Regulations 1998 (PUWER) & Equipment Inspections 5.6 Lifting Operations and Lifting Equipment Regulations 1998 (LOLER), Crane Safety & Rigging

6 Chapter 6: Site Setup, Logistics, Welfare & Environmental Protection

6.1 CDM 2015 Schedule 2 Welfare Facilities Standards & Site Setup Requirements 6.2 Site Traffic Management, Pedestrian-Vehicle Segregation & Delivery Logistics 6.3 Site Inductions, Security, Signage & Competence Verification (CSCS/CPCS) 6.4 First Aid at Work Regulations 1981: Needs Assessment, First Aiders & Equipment 6.5 Environmental Protection: Waste Management (Duty of Care), Pollution Prevention & Noise Control 6.6 Mobile Workforce, Lone Working & Driving for Work

3.1 Work at Height Regulations 2005 & Hierarchy of Control for Height Work

Key Takeaways Explain This Topic AI

Work at height is defined legally under the Work at Height Regulations 2005 (WAHR) as any place where, if no precautions were in place, a person could fall a distance liable to cause personal injury, with no minimum height threshold.

The statutory hierarchy of control under Regulation 6 mandates four sequential tiers: AVOID work at height, PREVENT falls using collective measures, MITIGATE fall distance and consequences, and utilize PERSONAL protection as a last resort.

Collective fall protection measures (such as permanent guardrails, scaffold working platforms, and safety nets) must always take legal precedence over personal fall protection systems (such as harnesses and lanyards).

Personal fall arrest systems require a minimum clearance height of approximately 5.5 to 6.0 meters below the anchorage point to accommodate lanyard length, energy absorber deployment, harness stretch, and safety margins.

Statutory equipment inspections under WAHR Regulation 12 require pre-use checks by operators, detailed 6-monthly inspections for textile harnesses and lanyards, and 7-day formal inspection reports for working platforms.

Last updated: August 2026

Loading diagram... Work at Height Statutory Hierarchy of Control

Work at height remains the single biggest cause of workplace fatalities and major injuries in the UK construction industry. The Work at Height Regulations 2005 (WAHR 2005) set out clear legal requirements for duty holders—including Principal Contractors, Site Managers, and subcontractors—to plan, manage, and supervise all work at height to prevent falls.

Legal Definition and Scope of Work at Height

Under Regulation 2 of WAHR 2005, work at height is legally defined as work in any place where, if there were no precautions in place, a person could fall a distance liable to cause personal injury.

Crucially, there is no minimum height threshold under UK law. The historic '2-meter rule' was abolished when WAHR 2005 came into force. Work at height includes:

Working on a scaffold platform, tower scaffold, or mobile elevating work platform (MEWP).

Working on a flat or pitched roof, edge, or fragile surface.

Working near open floor edges, stairwells, lift shafts, or un-boarded joists.

Working at ground level adjacent to an open excavation, trench, pit, or water body where a person could fall into the opening.

Working on ladders or stepladders.

Note: Work at height does not include permanent staircases in a finished building or slipping/tripping on a flat, level surface at ground grade.

Statutory Duties of Site Managers (Regulation 4 & 5)

Site Managers are responsible for ensuring that all work at height is:

Properly Planned: Prepared in advance with detailed risk assessments and Method Statements (RAMS), taking into account emergency rescue procedures.

Appropriately Supervised: Overseen by a competent supervisor who ensures work strictly follows agreed safety controls.

Carried Out by Competent Persons: Undertaken only by operatives possessing the necessary skills, knowledge, training, and experience (e.g., CISRS for scaffolding, IPAF for MEWPs, PASMA for tower scaffolds).

Weather Monitored: Suspended if severe weather conditions (high winds, ice, heavy rain, or lightning) endanger worker safety.

Equipped with Inspected Gear: Performed using work equipment that has undergone statutory inspections and pre-use checks.

The Statutory Hierarchy of Control (Regulation 6)

Regulation 6 of WAHR 2005 establishes a strict legal hierarchy of control that Site Managers must apply sequentially when planning height operations: +-------------------------------------------------------------------------+

  • | Tier 1: AVOID Work at Height |
  • | (Pre-fabricate assemblies on ground, use long-reach maintenance tools) |
  • +-------------------------------------------------------------------------+
  • | (If Avoidance is Unfeasible)
  • v
  • +-------------------------------------------------------------------------+
  • | Tier 2: PREVENT Falls Using Collective Equipment |
  • | (Permanent guardrails, TG20 scaffolds, MEWPs, podium steps) |
  • +-------------------------------------------------------------------------+
  • | (If Prevention Equipment is Unfeasible)
  • v
  • +-------------------------------------------------------------------------+
  • | Tier 3: MITIGATE Distance & Consequences Using Collective Arrest |
  • | (Safety nets, soft landing bags, catch platforms) |
  • +-------------------------------------------------------------------------+
  • | (If Collective Protection is Unfeasible)
  • v
  • +-------------------------------------------------------------------------+
  • | Tier 4: PERSONAL PROTECTION (Individual Fall Protection Systems) |
  • | (Work Restraint lines, Fall Arrest harnesses and shock lanyards) |
  • +-------------------------------------------------------------------------+

Breakdown of Hierarchy Tiers:

Tier 1: Avoid Work at Height Altogether

Re-design construction processes so work is executed at ground level. Examples include assembling roof trusses or steel modular units on the ground before crane lifting, using ground-based telescopic cameras for inspections, or employing extendable window cleaning poles.

Tier 2: Prevent Falls Using Existing Safe Places or Collective Equipment

Where work at height cannot be avoided, select equipment that physically prevents workers from falling. Priority must be given to collective protection (guardrails, toe boards, scaffolding, MEWPs) over personal protection.

Tier 3: Mitigate Distance and Consequences of a Fall (Collective Arrest)

If fall prevention measures are unfeasible, install collective equipment that limits the distance and mitigates the impact of any potential fall. Examples include tensioned safety nets rigged close below the working deck or soft landing airbags.

Tier 4: Personal Fall Protection Systems (Individual Protection)

As a last resort, issue individual Personal Protection Equipment (PPE) to workers. Personal systems protect only the individual wearing them and rely entirely on correct user training and compliance.

Collective Protection vs. Personal Protection

UK health and safety law strictly mandates that collective protection must always take priority over personal protection .

Feature Collective Protection Personal Protection

Examples Guardrails, toe boards, scaffolds, MEWPs, safety nets Fall arrest harnesses, lanyards, work restraint lines

Protection Scope Protects everyone in the vicinity simultaneously Protects only the individual wearing the equipment

User Intervention Passive—requires no active user action or adjustment Active—requires continuous user hook-up, clipping, and vigilance

Training Burden Low—general site induction and visual inspection High—specialized user training, harness fitting, and anchor selection

Failure Risk Low operational failure risk once engineered Higher risk from misuse, improper tie-off, or damaged webbing

Personal Fall Protection Systems (PFPS)

When personal equipment must be used, Site Managers must understand the three operational categories under BS EN 363 :

Work Restraint Systems:

A system designed to physically prevent the worker from reaching an exposed edge or fall hazard. It comprises a full-body harness or restraint belt attached to a fixed-length lanyard secured to a rated anchor point. Because the lanyard length prevents the worker from reaching the edge, a fall cannot occur.

Work Positioning Systems:

A system that supports the worker in tension or suspension at height (e.g., rope access or pole straps) so they can work hands-free. A back-up fall arrest line is legally required in conjunction with work positioning.

Fall Arrest Systems:

A system that allows a worker to reach a fall hazard and fall through space, but safely arrests the fall before the worker collides with the ground or structure below. It consists of a full-body harness, an energy-absorbing (shock-absorbing) lanyard or personal fall arrester (inertia reel), and a structural anchor point rated to at least 12 kN (or EN 795 compliant).

Calculating Minimum Fall Clearance Distance

Before authorizing fall arrest equipment, Site Managers must calculate the Minimum Required Fall Clearance (MRFC) below the anchorage point to ensure an arresting fall will not result in collision with obstacles or ground: Total Clearance Required = L + E + H + H user + S \text{Total Clearance Required} = L + E + H + H_{\text{user}} + S Total Clearance Required = L + E + H + H user ​ + S

Where:

L L L = Original length of energy-absorbing lanyard (typically 2.0m ).

E E E = Maximum extension of energy absorber tear-webbing during deployment (up to 1.75m ).

H H H = Harness stretch and D-ring displacement (typically 0.5m ).

H user H_{\text{user}} H user ​ = Distance from worker's D-ring to feet (typically 1.5m ).

S S S = Safety clearance margin below feet (minimum 1.0m ). Total Required Clearance = 2.0 m + 1.75 m + 0.5 m + 1.5 m + 1.0 m = 6.75 m \text{Total Required Clearance} = 2.0\text{m} + 1.75\text{m} + 0.5\text{m} + 1.5\text{m} + 1.0\text{m} = 6.75\text{m} Total Required Clearance = 2.0 m + 1.75 m + 0.5 m + 1.5 m + 1.0 m = 6.75 m

If the available height below the anchor point is less than 5.5 to 6.0 meters , standard 2m fall arrest lanyards cannot be safely used; work restraint lines, self-retracting lifelines (inertia reels), or collective platforms must be substituted.

Equipment Inspection and Maintenance Regimes (Regulation 12)

Under WAHR Regulation 12 and HSE guidance INDG367 , all equipment used for work at height must undergo strict inspection regimes:

Pre-Use Checks: Conducted by the operative prior to every work shift (visual check for cuts, fraying, chemical contamination, deformed D-rings, or faulty carabiner gates).

Statutory Detailed Inspection: Conducted by a competent, independent inspector at intervals not exceeding 6 months for textile harnesses, lanyards, and lifelines (or 3 months in harsh marine/chemical environments). Written records must be retained.

Working Platform Inspections: Scaffolds, tower scaffolds, and MEWPs must be inspected prior to initial use and at intervals not exceeding 7 days , with formal entry into the site inspection register.