Study guide

1.5 CDM 2015 Project Documentation: PCI, Construction Phase Plan & Health and Safety File

CITB Site Management Safety Training Scheme SMSTS

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Legal Framework, CDM 2015 & Health and Safety Management

1.1 How the SMSTS Course and Examination Actually Work 1.2 Health and Safety at Work etc. Act 1974 (HASAWA) & Statutory Duties 1.3 Management of Health and Safety at Work Regulations 1999 & HSG65 (Plan-Do-Check-Act) 1.4 CDM 2015 Overview & Five Duty Holders (Client, Principal Designer, Principal Contractor, Designer, Contractor) 1.5 CDM 2015 Project Documentation: PCI, Construction Phase Plan & Health and Safety File 1.6 Statutory Notifications (F10), Enforcement Notices (Improvement/Prohibition), and Fee for Intervention (FFI) 1.7 RIDDOR 2013: Reporting Over-7-Day Injuries, Specified Injuries, Occupational Diseases & Dangerous Occurrences

2 Chapter 2: Risk Management, RAMS & Site Safety Leadership

2.1 Principles of Risk Assessment & Five Steps to Risk Assessment 2.2 Hierarchy of Control Measures & Risk Matrices 2.3 Developing, Reviewing, and Implementing Risk Assessments & Method Statements (RAMS) 2.4 Permit to Work (PTW) Systems for High-Risk Activities 2.5 Worker Consultation, Toolbox Talks, and Safety Leadership Culture 2.6 Behavioural Safety, Human Factors, and Accident Investigation Techniques

3 Chapter 3: High-Risk Site Operations: Height, Excavations & Confined Spaces

3.1 Work at Height Regulations 2005 & Hierarchy of Control for Height Work 3.2 Scaffolding Standards (TG20, BS EN 12811) & Statutory 7-Day Inspection Regimes 3.3 Mobile Elevating Work Platforms (MEWPs), Ladders, Tower Scaffolds & Fragile Roof Safety 3.4 Excavation Safety: Preventing Ground Collapse, Shoring, Battering & Edge Protection 3.5 Underground Services Avoidance (HSG47): Cable Avoidance Tools (CAT) & Genny Operation 3.6 Confined Spaces Regulations 1997: Risk Assessment, Atmosphere Testing & Rescue Procedures 3.7 Temporary Works Management: BS 5975-1, Coordinator Roles & Permits to Load and Strike

4 Chapter 4: Occupational Health, Chemical Safety & Physical Hazards

4.1 Control of Substances Hazardous to Health (COSHH) Regulations & Exposure Limits 4.2 Respirable Crystalline Silica (RCS), Dust Control & Respiratory Protective Equipment (RPE) 4.3 Asbestos Management on Construction Sites: Control of Asbestos Regulations 2012 4.4 Noise at Work Regulations 2005 & Hand-Arm Vibration Syndrome (HAVS) Exposure Action Values 4.5 Manual Handling Operations Regulations 1992, Ergonomics & Musculoskeletal Health 4.6 Health Surveillance, Medical Fitness & Workplace Hygiene/Wellbeing 4.7 Lead in Buildings: Control of Lead at Work Regulations 2002 & Blood-Lead Surveillance 4.8 Drugs and Alcohol at Work: Legal Framework, Site Policy, Testing & Support

5 Chapter 5: Fire Safety, Electrical Protection & Plant Operations

5.1 Fire Prevention on Construction Sites (HSG168), Fire Triangle & Hot Work Permits 5.2 Fire Extinguishers, Means of Escape, LPG Storage & Emergency Evacuation Plans 5.3 Electricity at Work Regulations 1989 & Safe Isolation Procedures 5.4 110V Reduced Low Voltage Systems, RCDs & Overhead Power Lines Safety (GS6) 5.5 Provision and Use of Work Equipment Regulations 1998 (PUWER) & Equipment Inspections 5.6 Lifting Operations and Lifting Equipment Regulations 1998 (LOLER), Crane Safety & Rigging

6 Chapter 6: Site Setup, Logistics, Welfare & Environmental Protection

6.1 CDM 2015 Schedule 2 Welfare Facilities Standards & Site Setup Requirements 6.2 Site Traffic Management, Pedestrian-Vehicle Segregation & Delivery Logistics 6.3 Site Inductions, Security, Signage & Competence Verification (CSCS/CPCS) 6.4 First Aid at Work Regulations 1981: Needs Assessment, First Aiders & Equipment 6.5 Environmental Protection: Waste Management (Duty of Care), Pollution Prevention & Noise Control 6.6 Mobile Workforce, Lone Working & Driving for Work

1.5 CDM 2015 Project Documentation: PCI, Construction Phase Plan & Health and Safety File

Key Takeaways Explain This Topic AI

Pre-Construction Information (PCI) is compiled by the Client/PD to inform tendering designers and contractors of existing site hazards

The Construction Phase Plan (CPP) must be prepared by the PC before site work starts and must be site-specific and dynamic

Schedule 3 of CDM 2015 details specific high-risk construction activities that mandate detailed risk controls within the CPP

The Health and Safety File (HSF) is compiled by the PD, updated during construction, and handed to the Client upon project completion

The Client must retain the HSF and make it available to any person carrying out future design, construction, or demolition work

Last updated: August 2026

Statutory Documentation under CDM 2015

CDM 2015 establishes a structured documentation chain across the pre-construction, construction, and post-completion phases of a project. The three main statutory documents are:

  • Pre-Construction Information (PCI)
  • Construction Phase Plan (CPP)
  • Health and Safety File (HSF)

Understanding the exact purpose, author, statutory responsibility, and timing of each document is critical for site managers and SMSTS candidates.

  • 1. Pre-Construction Information (PCI)
  • Purpose & Legal Duty

Pre-Construction Information (PCI) is the core hazard and information document prepared during the design and planning stage. The Client has primary legal responsibility for ensuring PCI is provided, while the Principal Designer (PD) assists in gathering, structuring, and distributing it.

PCI must be provided to every designer and contractor tendering for or appointed to the project as early as possible. Its purpose is to ensure that contractors can price for necessary safety measures and designers can design out known site hazards.

Key Components of PCI:

Project Description: Scope of work, key dates, project team structure, and client constraints.

Environmental & Site Restrictions: Surrounding land use, adjacent schools/hospitals, noise/vibration limits, traffic management restrictions.

Existing Site Hazards:

Asbestos location reports and Refurbishment/Demolition Asbestos Surveys (R&D surveys).

Buried utilities (electric cables, gas mains, fiber optic lines) and overhead powerlines.

Contaminated land, ground instability, or high water table levels.

Structural stability of existing buildings, load-bearing capacities, fragile roofs.

Design Risks & Residual Hazards: Hazards identified by designers that could not be designed out.

Client Site Rules: Specific site rules mandated by the Client (e.g., security clearances, drug/alcohol testing protocols).

  • 2. Construction Phase Plan (CPP)
  • Purpose & Legal Duty

The Construction Phase Plan (CPP) is the master health and safety document setting out how health, safety, and welfare will be managed on site during actual construction operations. The Principal Contractor (PC) (or sole Contractor on single-contractor projects) must prepare the CPP before site setup or construction work commences .

The Client is legally prohibited from allowing site construction work to start until they are satisfied that a suitable site-specific CPP has been prepared by the PC.

Critical SMSTS Rule: Site-Specific vs. Generic Plans

Generic, off-the-shelf binders fail to meet statutory requirements. The CPP must be tailored to the specific site , reflecting actual ground conditions, sequence of work, site layout, and identified risks. It is a living document that must be continuously updated by the PC as work progresses.

Key Components of the CPP:

Project Overview & Management Structure: Site manager details, contact numbers, emergency procedures, first aid arrangements.

Site Rules & Inductions: Mandatory site PPE rules, working hours, delivery arrangements, alcohol/drug policy.

Welfare Facilities: Location and specification of Schedule 2 welfare provisions.

Worker Consultation & Cooperation: Daily briefings, Toolbox Talks, safety committee meetings.

Control of Specific Site Risks: High-risk activities detailing Safe Systems of Work (SSoW), Risk Assessments, and Method Statements (RAMS).

Schedule 3 High-Risk Construction Works

Under CDM 2015 Schedule 3 , the CPP must contain detailed management controls for work involving specific high-risk hazards:

Work involving risk of fall from height or burial under earthwork / fall into excavation .

Work exposing workers to chemical or biological substances (COSHH hazards, lead, silica, asbestos).

Work exposing workers to ionizing radiation .

Work in the vicinity of high-voltage overhead electric lines or buried services.

Work presenting a risk of drowning .

Work in caissons, wells, underground shafts, or tunnels .

Work involving the use of explosives .

Work involving the assembly or disassembly of heavy prefabricated components .

  • 3. Health and Safety File (HSF)
  • Purpose & Legal Duty

The Health and Safety File (HSF) is an essential asset management safety record compiled for the Client. Its purpose is to ensure that anyone carrying out future construction, maintenance, refurbishment, cleaning, or demolition work on the structure can do so safely.

The Principal Designer is responsible for compiling, updating, and revising the HSF throughout the pre-construction and construction phases (incorporating information provided by the PC and designers). Upon completion of the project, the PD formally hands over the HSF to the Client .

The Client must retain the HSF and make it available to any future designers or contractors working on the building or structure.

Key Content of the Health and Safety File:

Brief description of the work carried out.

Residual hazards that could not be eliminated during design (e.g., location of lead paint, hazardous materials, fragile roof sheets).

Key structural principles, safe floor loadings, and post-tensioned cable locations.

Hazardous materials used in construction (e.g., insulation types, fireproofing coatings).

Location of concealed services (underground drains, buried cables, embedded pipes).

Information and 'as-built' drawings showing structural layout and access points.

Maintenance guidelines and equipment manuals for built-in cleaning/maintenance plant (e.g., cradles, fall arrest anchor points).

Statutory Documentation Lifecycle Matrix

Document Primary Compiler / Author Recipient / Key Users Lifecycle Phase Statutory Purpose

Pre-Construction Information (PCI) Client / Principal Designer Tendering Contractors & Designers Pre-Construction Phase Inform designers and contractors of existing site hazards prior to bidding

Construction Phase Plan (CPP) Principal Contractor Site Management, Workers, Subcontractors Construction Phase Operational blueprint for site safety management, RAMS, and Schedule 3 risks

Health and Safety File (HSF) Principal Designer (handed to Client) Client / Future Contractors & Designers Post-Completion / Asset Lifecycle Provide essential safety details for future maintenance, alteration, or demolition