1.4 CDM 2015 Overview & Five Duty Holders (Client, Principal Designer, Principal Contractor, Designer, Contractor)
CITB Site Management Safety Training Scheme SMSTS
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Legal Framework, CDM 2015 & Health and Safety Management
1.1 How the SMSTS Course and Examination Actually Work 1.2 Health and Safety at Work etc. Act 1974 (HASAWA) & Statutory Duties 1.3 Management of Health and Safety at Work Regulations 1999 & HSG65 (Plan-Do-Check-Act) 1.4 CDM 2015 Overview & Five Duty Holders (Client, Principal Designer, Principal Contractor, Designer, Contractor) 1.5 CDM 2015 Project Documentation: PCI, Construction Phase Plan & Health and Safety File 1.6 Statutory Notifications (F10), Enforcement Notices (Improvement/Prohibition), and Fee for Intervention (FFI) 1.7 RIDDOR 2013: Reporting Over-7-Day Injuries, Specified Injuries, Occupational Diseases & Dangerous Occurrences
2 Chapter 2: Risk Management, RAMS & Site Safety Leadership
2.1 Principles of Risk Assessment & Five Steps to Risk Assessment 2.2 Hierarchy of Control Measures & Risk Matrices 2.3 Developing, Reviewing, and Implementing Risk Assessments & Method Statements (RAMS) 2.4 Permit to Work (PTW) Systems for High-Risk Activities 2.5 Worker Consultation, Toolbox Talks, and Safety Leadership Culture 2.6 Behavioural Safety, Human Factors, and Accident Investigation Techniques
3 Chapter 3: High-Risk Site Operations: Height, Excavations & Confined Spaces
3.1 Work at Height Regulations 2005 & Hierarchy of Control for Height Work 3.2 Scaffolding Standards (TG20, BS EN 12811) & Statutory 7-Day Inspection Regimes 3.3 Mobile Elevating Work Platforms (MEWPs), Ladders, Tower Scaffolds & Fragile Roof Safety 3.4 Excavation Safety: Preventing Ground Collapse, Shoring, Battering & Edge Protection 3.5 Underground Services Avoidance (HSG47): Cable Avoidance Tools (CAT) & Genny Operation 3.6 Confined Spaces Regulations 1997: Risk Assessment, Atmosphere Testing & Rescue Procedures 3.7 Temporary Works Management: BS 5975-1, Coordinator Roles & Permits to Load and Strike
4 Chapter 4: Occupational Health, Chemical Safety & Physical Hazards
4.1 Control of Substances Hazardous to Health (COSHH) Regulations & Exposure Limits 4.2 Respirable Crystalline Silica (RCS), Dust Control & Respiratory Protective Equipment (RPE) 4.3 Asbestos Management on Construction Sites: Control of Asbestos Regulations 2012 4.4 Noise at Work Regulations 2005 & Hand-Arm Vibration Syndrome (HAVS) Exposure Action Values 4.5 Manual Handling Operations Regulations 1992, Ergonomics & Musculoskeletal Health 4.6 Health Surveillance, Medical Fitness & Workplace Hygiene/Wellbeing 4.7 Lead in Buildings: Control of Lead at Work Regulations 2002 & Blood-Lead Surveillance 4.8 Drugs and Alcohol at Work: Legal Framework, Site Policy, Testing & Support
5 Chapter 5: Fire Safety, Electrical Protection & Plant Operations
5.1 Fire Prevention on Construction Sites (HSG168), Fire Triangle & Hot Work Permits 5.2 Fire Extinguishers, Means of Escape, LPG Storage & Emergency Evacuation Plans 5.3 Electricity at Work Regulations 1989 & Safe Isolation Procedures 5.4 110V Reduced Low Voltage Systems, RCDs & Overhead Power Lines Safety (GS6) 5.5 Provision and Use of Work Equipment Regulations 1998 (PUWER) & Equipment Inspections 5.6 Lifting Operations and Lifting Equipment Regulations 1998 (LOLER), Crane Safety & Rigging
6 Chapter 6: Site Setup, Logistics, Welfare & Environmental Protection
6.1 CDM 2015 Schedule 2 Welfare Facilities Standards & Site Setup Requirements 6.2 Site Traffic Management, Pedestrian-Vehicle Segregation & Delivery Logistics 6.3 Site Inductions, Security, Signage & Competence Verification (CSCS/CPCS) 6.4 First Aid at Work Regulations 1981: Needs Assessment, First Aiders & Equipment 6.5 Environmental Protection: Waste Management (Duty of Care), Pollution Prevention & Noise Control 6.6 Mobile Workforce, Lone Working & Driving for Work
1.4 CDM 2015 Overview & Five Duty Holders (Client, Principal Designer, Principal Contractor, Designer, Contractor)
Key Takeaways Explain This Topic AI
CDM 2015 applies to all construction work in Great Britain, establishing 5 main duty holders across commercial and domestic projects
The Client must appoint a Principal Designer and Principal Contractor in writing whenever a project involves more than one contractor
The Principal Designer manages health and safety during the pre-construction phase, eliminating design risks and preparing the PCI
The Principal Contractor manages health and safety during the construction phase, preparing the CPP and ensuring Schedule 2 welfare facilities
Domestic client duties automatically transfer to the Contractor or Principal Contractor unless assigned to the Principal Designer by written agreement
Last updated: August 2026
Introduction to CDM 2015
The Construction (Design and Management) Regulations 2015 (CDM 2015) are the primary statutory regulations governing health, safety, and welfare on construction projects in Great Britain. CDM 2015 replaced the previous 2007 regulations, simplifying the regulatory structure, replacing the former 'CDM Coordinator' role with the Principal Designer (PD) , and extending statutory duties to domestic clients.
CDM 2015 applies to all construction projects , regardless of scale, contract value, or duration. Construction work is defined broadly under Regulation 2 to include building, alteration, conversion, fitting out, commissioning, renovation, repair, maintenance, high-pressure cleaning, dismantling, and demolition.
The Five CDM 2015 Duty Holders
CDM 2015 establishes five primary duty holders, each holding specific legal duties across project lifecycle phases. +------------------------+
- | THE CLIENT |
- | (Commercial / Domestic)|
- +-----------+------------+
- |
- Appoints in Writing (>1 Contractor)
- |
- +--------------------+--------------------+
- | |
- v v
- +-------+----------------+ +---------------+--------+
- | PRINCIPAL DESIGNER | | PRINCIPAL CONTRACTOR |
- | (Pre-Construction Phase| | (Construction Phase |
- | H&S Coordination) | | Site Management) |
- +-------+----------------+ +---------------+--------+
- | |
- v v
- +-------+----------------+ +---------------+--------+
- | DESIGNERS | | CONTRACTORS |
- | (Architects, Engineers)| | (Subcontractors, Trades|
- +------------------------+ +------------------------+
- 1. The Client
The Client is any organization or individual for whom a construction project is carried out. Clients have overall legal responsibility for ensuring that construction projects are structured and managed safely.
Key Client Duties:
Make Suitable Management Arrangements: Ensure suitable arrangements are made for managing the project so that health, safety, and welfare are maintained throughout.
Appoint Duty Holders in Writing: Where a project involves more than one contractor (or is reasonably foreseeable to involve more than one contractor), the Client must appoint in writing a Principal Designer (PD) and a Principal Contractor (PC) as early as possible.
Allocate Resources and Time: Ensure sufficient time and resources are allocated for all phases of the project.
Ensure Competence: Take reasonable steps to ensure that appointed duty holders possess the necessary skills, knowledge, experience, and organizational capability (SKEO).
Provide Pre-Construction Information (PCI): Ensure that PCI is compiled and promptly provided to every designer and contractor tendering for or appointed to the project.
Ensure Construction Phase Plan (CPP) Execution: Ensure that the PC prepares a suitable, site-specific CPP before construction work commences on site.
Ensure Welfare Provisions: Ensure that suitable welfare facilities complying with Schedule 2 are provided by the PC from the start of site setup.
Maintain the Health and Safety File: Ensure the PD prepares, updates, and passes over the Health and Safety File upon completion, retaining it for future works.
2. The Principal Designer (PD)
The Principal Designer is an organization or individual appointed by the Client in writing on multi-contractor projects to take control of health and safety during the pre-construction phase .
Key Principal Designer Duties:
Plan, Manage, and Monitor Pre-Construction: Coordinate health and safety during design, planning, and preparation.
Eliminate and Control Design Risks: Assist designers to identify, eliminate foreseeable hazards, and reduce remaining risks using the General Principles of Prevention.
Compile and Distribute PCI: Gather, organize, and provide Pre-Construction Information to designers, the Client, and the PC.
Liaise with Principal Contractor: Share relevant design information and coordinate ongoing design changes during the construction phase.
Prepare the Health and Safety File: Compile, update, and review the Health and Safety File during the project and hand it to the Client upon completion.
3. The Principal Contractor (PC)
The Principal Contractor is the contractor appointed by the Client in writing on multi-contractor projects to take overall control of health and safety during the construction phase .
Key Principal Contractor Duties:
Plan, Manage, and Monitor Construction: Coordinate all site work to ensure construction is executed without risks to health and safety.
Prepare the Construction Phase Plan (CPP): Prepare, implement, update, and enforce a site-specific CPP before site setup or construction work begins.
Organize Cooperation: Coordinate the activities of all contractors on site to ensure compliance with health and safety legal duties.
Provide Site Inductions & Training: Ensure suitable site-specific inductions are delivered to every worker prior to starting work on site.
Enforce Welfare Facilities (Schedule 2): Ensure adequate, operational welfare facilities (sanitary conveniences, washing facilities, drinking water, changing rooms, rest facilities) are available from day one.
Secure Site Perimeter: Prevent unauthorized access to the site using suitable boundary fencing, hoardings, and access controls.
Worker Consultation: Consult and engage with workers on site health, safety, and welfare matters.
4. Designers
A Designer is anyone who prepares or modifies designs for a building, structure, or product used in construction (including architects, structural engineers, quantity surveyors specifying materials, or sub-contractors performing design detailing).
Key Designer Duties:
Eliminate Hazards: When preparing designs, eliminate foreseeable health and safety risks to persons constructing, maintaining, or demolishing the structure.
Reduce Residual Risks: Apply the General Principles of Prevention to reduce remaining risks.
Provide Information: Include information about residual hazards in design drawings and notes provided to the PD and PC.
5. Contractors
A Contractor is any business or self-employed individual who carries out, manages, or controls construction work.
Key Contractor Duties:
Plan, Manage, and Monitor Own Work: Ensure work under their control is executed safely.
Comply with Directions: Follow site rules set out in the CPP and obey directions issued by the PC.
Provide Worker Training: Ensure their workers have received site inductions and possess required skills and qualifications.
Report Hazards: Promptly report dangerous conditions or incidents to the PC.
Special Rules for Domestic Clients
A Domestic Client is an individual who has construction work carried out on their own home (or the home of a family member) that is not in connection with a business.
Under Regulation 7 of CDM 2015:
Domestic client duties are automatically transferred to the Contractor (on single-contractor projects) or the Principal Contractor (on multi-contractor projects).
Alternatively, a domestic client may sign a written agreement transferring client duties to the Principal Designer .
CDM 2015 Duty Holders Summary Table
Duty Holder Mandatory Written Appointment Primary Lifecycle Phase Statutory Key Deliverable
Client Retains primary responsibility Whole Project Lifecycle Suitable arrangements, appointing PD/PC, allocating budget/time
Principal Designer (PD) Required when >1 contractor Pre-Construction Phase Pre-Construction Information (PCI) & Health and Safety File
Principal Contractor (PC) Required when >1 contractor Construction Phase Construction Phase Plan (CPP) & Site Welfare (Schedule 2)
- Designer By appointment / engagement Design & Planning Phase Risk elimination in drawings, hazard notes to PD
- Contractor By contract / appointment Construction Phase RAMS, safe execution of work, compliance with CPP