1.3 Management of Health and Safety at Work Regulations 1999 & HSG65 (Plan-Do-Check-Act)
CITB Site Management Safety Training Scheme SMSTS
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Legal Framework, CDM 2015 & Health and Safety Management
1.1 How the SMSTS Course and Examination Actually Work 1.2 Health and Safety at Work etc. Act 1974 (HASAWA) & Statutory Duties 1.3 Management of Health and Safety at Work Regulations 1999 & HSG65 (Plan-Do-Check-Act) 1.4 CDM 2015 Overview & Five Duty Holders (Client, Principal Designer, Principal Contractor, Designer, Contractor) 1.5 CDM 2015 Project Documentation: PCI, Construction Phase Plan & Health and Safety File 1.6 Statutory Notifications (F10), Enforcement Notices (Improvement/Prohibition), and Fee for Intervention (FFI) 1.7 RIDDOR 2013: Reporting Over-7-Day Injuries, Specified Injuries, Occupational Diseases & Dangerous Occurrences
2 Chapter 2: Risk Management, RAMS & Site Safety Leadership
2.1 Principles of Risk Assessment & Five Steps to Risk Assessment 2.2 Hierarchy of Control Measures & Risk Matrices 2.3 Developing, Reviewing, and Implementing Risk Assessments & Method Statements (RAMS) 2.4 Permit to Work (PTW) Systems for High-Risk Activities 2.5 Worker Consultation, Toolbox Talks, and Safety Leadership Culture 2.6 Behavioural Safety, Human Factors, and Accident Investigation Techniques
3 Chapter 3: High-Risk Site Operations: Height, Excavations & Confined Spaces
3.1 Work at Height Regulations 2005 & Hierarchy of Control for Height Work 3.2 Scaffolding Standards (TG20, BS EN 12811) & Statutory 7-Day Inspection Regimes 3.3 Mobile Elevating Work Platforms (MEWPs), Ladders, Tower Scaffolds & Fragile Roof Safety 3.4 Excavation Safety: Preventing Ground Collapse, Shoring, Battering & Edge Protection 3.5 Underground Services Avoidance (HSG47): Cable Avoidance Tools (CAT) & Genny Operation 3.6 Confined Spaces Regulations 1997: Risk Assessment, Atmosphere Testing & Rescue Procedures 3.7 Temporary Works Management: BS 5975-1, Coordinator Roles & Permits to Load and Strike
4 Chapter 4: Occupational Health, Chemical Safety & Physical Hazards
4.1 Control of Substances Hazardous to Health (COSHH) Regulations & Exposure Limits 4.2 Respirable Crystalline Silica (RCS), Dust Control & Respiratory Protective Equipment (RPE) 4.3 Asbestos Management on Construction Sites: Control of Asbestos Regulations 2012 4.4 Noise at Work Regulations 2005 & Hand-Arm Vibration Syndrome (HAVS) Exposure Action Values 4.5 Manual Handling Operations Regulations 1992, Ergonomics & Musculoskeletal Health 4.6 Health Surveillance, Medical Fitness & Workplace Hygiene/Wellbeing 4.7 Lead in Buildings: Control of Lead at Work Regulations 2002 & Blood-Lead Surveillance 4.8 Drugs and Alcohol at Work: Legal Framework, Site Policy, Testing & Support
5 Chapter 5: Fire Safety, Electrical Protection & Plant Operations
5.1 Fire Prevention on Construction Sites (HSG168), Fire Triangle & Hot Work Permits 5.2 Fire Extinguishers, Means of Escape, LPG Storage & Emergency Evacuation Plans 5.3 Electricity at Work Regulations 1989 & Safe Isolation Procedures 5.4 110V Reduced Low Voltage Systems, RCDs & Overhead Power Lines Safety (GS6) 5.5 Provision and Use of Work Equipment Regulations 1998 (PUWER) & Equipment Inspections 5.6 Lifting Operations and Lifting Equipment Regulations 1998 (LOLER), Crane Safety & Rigging
6 Chapter 6: Site Setup, Logistics, Welfare & Environmental Protection
6.1 CDM 2015 Schedule 2 Welfare Facilities Standards & Site Setup Requirements 6.2 Site Traffic Management, Pedestrian-Vehicle Segregation & Delivery Logistics 6.3 Site Inductions, Security, Signage & Competence Verification (CSCS/CPCS) 6.4 First Aid at Work Regulations 1981: Needs Assessment, First Aiders & Equipment 6.5 Environmental Protection: Waste Management (Duty of Care), Pollution Prevention & Noise Control 6.6 Mobile Workforce, Lone Working & Driving for Work
1.3 Management of Health and Safety at Work Regulations 1999 & HSG65 (Plan-Do-Check-Act)
Key Takeaways Explain This Topic AI
MHSWR 1999 Regulation 3 mandates suitable and sufficient risk assessments, which must be recorded in writing if employing 5 or more people
Regulation 4 establishes the statutory Principles of Prevention, placing collective protection above individual protection
Regulation 7 requires employers to appoint one or more competent persons possessing sufficient training, knowledge, and experience (TKE)
HSG65 provides the HSE framework for health and safety management structured around Plan-Do-Check-Act (PDCA)
Active monitoring measures performance proactively before incidents, whereas reactive monitoring investigates accidents and near-misses after they occur
Last updated: August 2026
Management of Health and Safety at Work Regulations 1999 (MHSWR)
While HASAWA 1974 sets out broad legal responsibilities, the Management of Health and Safety at Work Regulations 1999 (MHSWR) explicitates how employers must manage health and safety day-to-day. MHSWR mandates a proactive, systematic risk management approach across all construction projects.
Regulation 3: Statutory Risk Assessment
Regulation 3 requires every employer and self-employed person to carry out a suitable and sufficient assessment of the risks to the health and safety of their employees and non-employees (subcontractors, site visitors, members of the public) arising out of or in connection with their work.
Key statutory requirements under Regulation 3 include:
If an employer employs 5 or more employees , the significant findings of the risk assessment must be recorded in writing .
Assessments must identify hazards, evaluate risks, determine appropriate control measures, and identify groups of workers specifically at risk.
Assessments must be reviewed and revised if there is reason to suspect they are no longer valid, or if significant changes occur in work procedures, plant, or site conditions.
Regulation 4 & Schedule 1: General Principles of Prevention
Regulation 4 mandates that where an employer implements preventive and protective measures, they must do so on the basis of the General Principles of Prevention specified in Schedule 1 (derived from European Council Directive 89/391/EEC):
Avoid risks (e.g., design out hazardous work at height or pre-fabricate components off-site).
Evaluate risks which cannot be avoided (e.g., conduct formal risk assessments).
Combat risks at source (e.g., control silica dust using local exhaust ventilation or water suppression directly on cut-off saws).
Adapt work to the individual (e.g., design workstations, choose ergonomic tools, and adjust working speeds).
Adapt to technical progress (e.g., substitute manual lifting with modern telehandlers or vacuum lifters).
Replace the dangerous by the non-dangerous or less dangerous (e.g., replace solvent-based paints with water-based coatings).
Develop a coherent overall prevention policy (e.g., integrate technology, work organization, working conditions, and social relationships).
Give collective protective measures priority over individual protective measures (e.g., install scaffold guardrails or safety netting rather than relying solely on personal fall arrest harnesses).
Give appropriate instructions to employees (e.g., deliver site inductions, clear method statements, and daily tooltalks).
The Hierarchy of Risk Controls (ERIC PD Mnemonic)
In construction management, the Principles of Prevention are practically applied through the Hierarchy of Risk Controls:
E liminate the hazard.
R educe / Substitute the hazard.
I solate the hazard (enclosures, barrier fencing).
C ontrol engineering measures (LEV, guards).
P rotect individuals (Personal Protective Equipment - PPE as last resort).
D iscipline / Administration (signage, permits to work, training).
Key Operational Regulations under MHSWR 1999
Regulation 5 (Health and Safety Arrangements): Employers must make arrangements for the effective planning, organization, control, monitoring, and review of preventive and protective measures. Written arrangements are mandatory for employers with 5+ staff.
Regulation 7 (Competent Persons): Employers must appoint one or more competent persons to assist them in undertaking measures to comply with statutory health and safety duties. Competence is legally defined as a combination of training, knowledge, experience (TKE) and other qualities.
Regulation 10 (Information for Employees): Employers must provide employees with comprehensible and relevant information on workplace risks, preventative measures, emergency procedures, and identities of appointed competent persons.
Regulation 13 (Capabilities and Training): Employers must take into account employees' capabilities regarding health and safety when allocating tasks. Training must be provided on recruitment, on exposure to new/increased risks, or when work equipment/technology changes.
Regulation 19 (Young Persons & Expectant Mothers): Employers must carry out specific risk assessments for young persons (under 18 years of age) taking into account their lack of experience, absence of awareness of existing or potential risks, and developmental immaturity. Specific assessments are also required for new and expectant mothers.
The HSG65 Framework: Managing for Health and Safety
HSG65 is the Health and Safety Executive's core guidance document outlining a practical business management approach to safety. Structured around the Plan-Do-Check-Act (PDCA) methodology, HSG65 integrates safety management directly into core operational construction management. +-------------------------------------------------------------+
- | PLAN |
- | - Set H&S Policy & Intent |
- | - Plan for Implementation & Resources |
- +------------------------------+------------------------------+
- |
- v
- +------------------------------+------------------------------+
- | DO |
- | - Risk Profiling & Control Measures |
- | - Organize, Train & Communicate (Competence) |
- | - Implement Safe Systems of Work |
- +------------------------------+------------------------------+
- |
- v
- +------------------------------+------------------------------+
- | CHECK |
- | - Active Monitoring (Inspections, Plant Audits) |
- | - Reactive Monitoring (Accident/Near-Miss Investigations) |
- +------------------------------+------------------------------+
- |
- v
- +------------------------------+------------------------------+
- | ACT |
- | - Management Review & Auditing |
- | - Learn Lessons & Revise Procedures |
- +-------------------------------------------------------------+
- 1. PLAN
Establish an effective health and safety policy.
Plan for implementation by setting measurable targets and allocating necessary resources.
Identify legal requirements and design safe systems of work before site operations commence.
2. DO
Risk Profiling: Identify hazards, assess risks, and decide on appropriate control measures using the hierarchy of controls.
Organizing: Communicate effectively, promote worker involvement, ensure competence, and provide adequate supervision.
Implementing: Deliver site-specific inductions, enforce safety rules, and implement Safe Systems of Work (SSoW) and Method Statements (RAMS).
3. CHECK
Active (Proactive) Monitoring: Checking that safety standards, risk controls, and site rules are being correctly implemented before an accident occurs. Examples include routine site safety inspections, scaffold inspections every 7 days, daily plant checks, health surveillance, and safety audits.
Reactive Monitoring: Measuring performance by investigating incidents after they occur. Examples include accident investigations, dangerous occurrence reviews, near-miss logging, and analyzing ill-health data.
4. ACT
Review performance against targets through comprehensive management reviews and formal safety audits.
Investigate root causes of non-compliance or incidents and implement corrective action plans.
Revise risk assessments, policies, and operational arrangements to achieve continuous improvement.
Active vs. Reactive Performance Monitoring
Monitoring Type Operational Definition Construction Examples SMSTS Manager Action
Active Monitoring Proactive checks conducted prior to incidents to verify compliance Weekly scaffold inspections, daily crane pre-use checks, site H&S walks, air monitoring Correct non-compliances immediately; reward safe behavior
Reactive Monitoring Retrospective analysis carried out after an accident, near-miss, or ill-health event RIDDOR reports, accident book analysis, damage investigations, HSE notice reviews Identify root causes; update RAMS; retrain site personnel