Study guide
2.3 Developing, Reviewing, and Implementing Risk Assessments & Method Statements (RAMS)
CITB Site Management Safety Training Scheme SMSTS
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Legal Framework, CDM 2015 & Health and Safety Management
1.1 How the SMSTS Course and Examination Actually Work 1.2 Health and Safety at Work etc. Act 1974 (HASAWA) & Statutory Duties 1.3 Management of Health and Safety at Work Regulations 1999 & HSG65 (Plan-Do-Check-Act) 1.4 CDM 2015 Overview & Five Duty Holders (Client, Principal Designer, Principal Contractor, Designer, Contractor) 1.5 CDM 2015 Project Documentation: PCI, Construction Phase Plan & Health and Safety File 1.6 Statutory Notifications (F10), Enforcement Notices (Improvement/Prohibition), and Fee for Intervention (FFI) 1.7 RIDDOR 2013: Reporting Over-7-Day Injuries, Specified Injuries, Occupational Diseases & Dangerous Occurrences
2 Chapter 2: Risk Management, RAMS & Site Safety Leadership
2.1 Principles of Risk Assessment & Five Steps to Risk Assessment 2.2 Hierarchy of Control Measures & Risk Matrices 2.3 Developing, Reviewing, and Implementing Risk Assessments & Method Statements (RAMS) 2.4 Permit to Work (PTW) Systems for High-Risk Activities 2.5 Worker Consultation, Toolbox Talks, and Safety Leadership Culture 2.6 Behavioural Safety, Human Factors, and Accident Investigation Techniques
3 Chapter 3: High-Risk Site Operations: Height, Excavations & Confined Spaces
3.1 Work at Height Regulations 2005 & Hierarchy of Control for Height Work 3.2 Scaffolding Standards (TG20, BS EN 12811) & Statutory 7-Day Inspection Regimes 3.3 Mobile Elevating Work Platforms (MEWPs), Ladders, Tower Scaffolds & Fragile Roof Safety 3.4 Excavation Safety: Preventing Ground Collapse, Shoring, Battering & Edge Protection 3.5 Underground Services Avoidance (HSG47): Cable Avoidance Tools (CAT) & Genny Operation 3.6 Confined Spaces Regulations 1997: Risk Assessment, Atmosphere Testing & Rescue Procedures 3.7 Temporary Works Management: BS 5975-1, Coordinator Roles & Permits to Load and Strike
4 Chapter 4: Occupational Health, Chemical Safety & Physical Hazards
4.1 Control of Substances Hazardous to Health (COSHH) Regulations & Exposure Limits 4.2 Respirable Crystalline Silica (RCS), Dust Control & Respiratory Protective Equipment (RPE) 4.3 Asbestos Management on Construction Sites: Control of Asbestos Regulations 2012 4.4 Noise at Work Regulations 2005 & Hand-Arm Vibration Syndrome (HAVS) Exposure Action Values 4.5 Manual Handling Operations Regulations 1992, Ergonomics & Musculoskeletal Health 4.6 Health Surveillance, Medical Fitness & Workplace Hygiene/Wellbeing 4.7 Lead in Buildings: Control of Lead at Work Regulations 2002 & Blood-Lead Surveillance 4.8 Drugs and Alcohol at Work: Legal Framework, Site Policy, Testing & Support
5 Chapter 5: Fire Safety, Electrical Protection & Plant Operations
5.1 Fire Prevention on Construction Sites (HSG168), Fire Triangle & Hot Work Permits 5.2 Fire Extinguishers, Means of Escape, LPG Storage & Emergency Evacuation Plans 5.3 Electricity at Work Regulations 1989 & Safe Isolation Procedures 5.4 110V Reduced Low Voltage Systems, RCDs & Overhead Power Lines Safety (GS6) 5.5 Provision and Use of Work Equipment Regulations 1998 (PUWER) & Equipment Inspections 5.6 Lifting Operations and Lifting Equipment Regulations 1998 (LOLER), Crane Safety & Rigging
6 Chapter 6: Site Setup, Logistics, Welfare & Environmental Protection
6.1 CDM 2015 Schedule 2 Welfare Facilities Standards & Site Setup Requirements 6.2 Site Traffic Management, Pedestrian-Vehicle Segregation & Delivery Logistics 6.3 Site Inductions, Security, Signage & Competence Verification (CSCS/CPCS) 6.4 First Aid at Work Regulations 1981: Needs Assessment, First Aiders & Equipment 6.5 Environmental Protection: Waste Management (Duty of Care), Pollution Prevention & Noise Control 6.6 Mobile Workforce, Lone Working & Driving for Work
2.3 Developing, Reviewing, and Implementing Risk Assessments & Method Statements (RAMS)
Key Takeaways Explain This Topic AI
RAMS combine formal statutory risk assessments with a step-by-step safe method of work into a unified operational safety document.
A compliant Method Statement details the logical sequence of operations, supervisory roles, plant requirements, environmental controls, and emergency rescue plans.
Site managers have a legal responsibility under CDM 2015 to vet subcontractor RAMS before work commences, ensuring documents are site-specific rather than generic.
All operatives must undergo a formal RAMS briefing prior to starting work, with written records of attendance maintained on site.
Significant changes in site conditions, scope, or equipment mandate immediate work stoppage and formal re-assessment under Management of Change (MOC) procedures.
Last updated: August 2026
Developing, Reviewing, and Implementing RAMS
In UK construction management, RAMS stands for Risk Assessments and Method Statements . While a risk assessment identifies site hazards and evaluates control measures, a Method Statement provides a detailed, step-by-step written instruction on how to execute a specific task safely.
Together, RAMS form the core operational sub-system of the project's Construction Phase Plan (CPP) mandated by Regulation 12 of the Construction (Design and Management) Regulations 2015 (CDM 2015) . For site managers and supervisors, ensuring RAMS are robust, site-specific, properly vetted, and strictly followed at the workface is a primary duty.
Structure and Essential Components of a Method Statement
A comprehensive Method Statement must clearly outline the safe system of work so that site supervisors and operatives can follow it without ambiguity. Key sections include:
Document Header & Scope of Works: Title, document revision number, date, project location, contractor details, and exact task boundaries.
Management Structure & Supervision: Named site managers, supervisors, appointed competent persons (e.g., Crane Appointed Person, Scaffolding Inspector), emergency contacts, and qualified first aiders.
Detailed Step-by-Step Task Sequence: The logical operational sequence of the work from initial site setup to demobilization.
Site Access, Egress, & Logistics: Material delivery routes, crane setup zones, ground bearing capacities, loading limits, and traffic management rules.
Resource Requirements:
Plant, machinery, tools, and access equipment (e.g., MEWPs, towers).
Hazardous substances (COSHH assessments, Safety Data Sheets).
Lifting tackle, slings, and LOLER certification requirements.
Environmental & Public Protection Controls: Noise and vibration limits, dust suppression measures, waste management, and public boundary exclusion zones.
Specific Risk Controls & Permits: References to key risk assessments, mandatory Permits to Work (e.g., Hot Work, Confined Space, Excavation), and PPE requirements.
Emergency & Rescue Plans: Task-specific rescue procedures (e.g., MEWP emergency lowering, work-at-height harness recovery plan, confined space extraction).
The Dangers of Generic RAMS
One of the most widespread compliance failures in construction management is the reliance on generic, "cut-and-paste" RAMS .
Why Generic RAMS Fail: Off-the-shelf templates fail to account for unique site constraints such as adjacent live services, unstable ground, restricted overhead clearances, live public traffic, or simultaneous operations by other trade contractors.
Legal & Operational Risk: In an HSE prosecution or incident investigation, submitting unedited generic RAMS is viewed as evidence of management negligence. Site managers must reject generic submissions from subcontractors immediately.
Site Manager Responsibilities: Vetting Subcontractor RAMS
Before any subcontractor or specialist trade is permitted to begin work on site, the Principal Contractor's site manager must formally vet and approve their RAMS. Subcontractor Drafts RAMS
- └── Site Manager Vets RAMS (Technical & Site-Specific Check)
- ├── REJECTED: Return for revision (unclear sequence / generic / missing controls)
- └── APPROVED: Authorize Pre-Start Briefing
- └── Operatives Briefed & Sign Register --> Work Commences
- RAMS Vetting Checklist for Site Managers
Is it site-specific? Does it mention exact site locations, gridlines, drawings, and local hazards?
Is the sequence complete? Does it cover delivery, unloading, assembly, main works, and dismantling?
Are competency checks verified? Are operative qualifications attached (e.g., CSCS, CPCS, IPAF, PASMA, GAS SAFE)?
Are equipment certificates current? Are valid LOLER, PUWER, and calibration certificates provided?
Are emergency plans credible? Does the rescue plan rely on the emergency services (unacceptable) or provide internal site recovery equipment?
Operational Implementation and Worker Briefings
Creating a compliant RAMS document is worthless if it remains locked in the site office. Effective implementation requires:
Pre-Work RAMS Briefing: Before task commencement, the site supervisor must brief all operatives involved in the task directly at the workface or in the site briefing room.
Language & Accessibility: Briefings must be delivered in plain language. Where operatives have English as a second language, pictorial guides or translated summaries must be utilized.
Signed Acknowledgement Register: Every operative must sign a formal RAMS attendance register confirming they have understood the sequence and controls.
Workface Supervision: Supervisors must actively monitor work to verify that operatives adhere strictly to the agreed method statement.
Management of Change (MOC) Protocols
Site conditions on construction projects are dynamic. Unforeseen circumstances often arise mid-task—such as discovering unmapped underground utilities, experiencing sudden adverse weather, or encountering unpredicted structural timber rot.
The 4-Step MOC Procedure
When site conditions deviate significantly from the approved RAMS:
STOP WORK: Instruct operatives to pause the activity and secure the area safely.
RE-ASSESS: The site manager and trade supervisor must re-evaluate the new hazard at the workface.
REVISE RAMS: Amend the written risk assessment and method statement to incorporate revised controls (e.g., switching from machine excavation to hand digging).
RE-BRIEF: Re-brief all operatives on the revised RAMS, update the signed register, and only then authorize work to resume.