Study guide
6.4 First Aid at Work Regulations 1981: Needs Assessment, First Aiders & Equipment
CITB Site Management Safety Training Scheme SMSTS
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Legal Framework, CDM 2015 & Health and Safety Management
1.1 How the SMSTS Course and Examination Actually Work 1.2 Health and Safety at Work etc. Act 1974 (HASAWA) & Statutory Duties 1.3 Management of Health and Safety at Work Regulations 1999 & HSG65 (Plan-Do-Check-Act) 1.4 CDM 2015 Overview & Five Duty Holders (Client, Principal Designer, Principal Contractor, Designer, Contractor) 1.5 CDM 2015 Project Documentation: PCI, Construction Phase Plan & Health and Safety File 1.6 Statutory Notifications (F10), Enforcement Notices (Improvement/Prohibition), and Fee for Intervention (FFI) 1.7 RIDDOR 2013: Reporting Over-7-Day Injuries, Specified Injuries, Occupational Diseases & Dangerous Occurrences
2 Chapter 2: Risk Management, RAMS & Site Safety Leadership
2.1 Principles of Risk Assessment & Five Steps to Risk Assessment 2.2 Hierarchy of Control Measures & Risk Matrices 2.3 Developing, Reviewing, and Implementing Risk Assessments & Method Statements (RAMS) 2.4 Permit to Work (PTW) Systems for High-Risk Activities 2.5 Worker Consultation, Toolbox Talks, and Safety Leadership Culture 2.6 Behavioural Safety, Human Factors, and Accident Investigation Techniques
3 Chapter 3: High-Risk Site Operations: Height, Excavations & Confined Spaces
3.1 Work at Height Regulations 2005 & Hierarchy of Control for Height Work 3.2 Scaffolding Standards (TG20, BS EN 12811) & Statutory 7-Day Inspection Regimes 3.3 Mobile Elevating Work Platforms (MEWPs), Ladders, Tower Scaffolds & Fragile Roof Safety 3.4 Excavation Safety: Preventing Ground Collapse, Shoring, Battering & Edge Protection 3.5 Underground Services Avoidance (HSG47): Cable Avoidance Tools (CAT) & Genny Operation 3.6 Confined Spaces Regulations 1997: Risk Assessment, Atmosphere Testing & Rescue Procedures 3.7 Temporary Works Management: BS 5975-1, Coordinator Roles & Permits to Load and Strike
4 Chapter 4: Occupational Health, Chemical Safety & Physical Hazards
4.1 Control of Substances Hazardous to Health (COSHH) Regulations & Exposure Limits 4.2 Respirable Crystalline Silica (RCS), Dust Control & Respiratory Protective Equipment (RPE) 4.3 Asbestos Management on Construction Sites: Control of Asbestos Regulations 2012 4.4 Noise at Work Regulations 2005 & Hand-Arm Vibration Syndrome (HAVS) Exposure Action Values 4.5 Manual Handling Operations Regulations 1992, Ergonomics & Musculoskeletal Health 4.6 Health Surveillance, Medical Fitness & Workplace Hygiene/Wellbeing 4.7 Lead in Buildings: Control of Lead at Work Regulations 2002 & Blood-Lead Surveillance 4.8 Drugs and Alcohol at Work: Legal Framework, Site Policy, Testing & Support
5 Chapter 5: Fire Safety, Electrical Protection & Plant Operations
5.1 Fire Prevention on Construction Sites (HSG168), Fire Triangle & Hot Work Permits 5.2 Fire Extinguishers, Means of Escape, LPG Storage & Emergency Evacuation Plans 5.3 Electricity at Work Regulations 1989 & Safe Isolation Procedures 5.4 110V Reduced Low Voltage Systems, RCDs & Overhead Power Lines Safety (GS6) 5.5 Provision and Use of Work Equipment Regulations 1998 (PUWER) & Equipment Inspections 5.6 Lifting Operations and Lifting Equipment Regulations 1998 (LOLER), Crane Safety & Rigging
6 Chapter 6: Site Setup, Logistics, Welfare & Environmental Protection
6.1 CDM 2015 Schedule 2 Welfare Facilities Standards & Site Setup Requirements 6.2 Site Traffic Management, Pedestrian-Vehicle Segregation & Delivery Logistics 6.3 Site Inductions, Security, Signage & Competence Verification (CSCS/CPCS) 6.4 First Aid at Work Regulations 1981: Needs Assessment, First Aiders & Equipment 6.5 Environmental Protection: Waste Management (Duty of Care), Pollution Prevention & Noise Control 6.6 Mobile Workforce, Lone Working & Driving for Work
6.4 First Aid at Work Regulations 1981: Needs Assessment, First Aiders & Equipment
Key Takeaways Explain This Topic AI
The Health and Safety (First-Aid) Regulations 1981 require employers to provide adequate equipment, facilities, and trained personnel to give immediate first aid to injured workers.
First Aid Needs Assessments must evaluate site hazard levels, workforce numbers, multi-occupancy sub-contractors, site geography, shift patterns, and distance to emergency hospitals.
First aid personnel qualifications comprise First Aider at Work (FAW - 3-day course), Emergency First Aider at Work (EFAW - 1-day course), and Appointed Persons (equipment/call management).
First aid containers complying with BS 8599-1 must be marked with a white cross on a green background, regularly inspected, and must NEVER contain oral medications or painkillers.
Dedicated First Aid Treatment Rooms are mandatory on larger high-risk construction sites (250+ workers, or remote high-risk civils/tunneling operations).
Last updated: August 2026
Statutory Basis of Construction First Aid
First aid provision on construction sites is governed by the Health and Safety (First-Aid) Regulations 1981 (as amended) , supported by HSE Approved Code of Practice L74 ( First aid at work ) . The regulations place a strict duty on all employers to provide adequate and appropriate equipment, facilities, and personnel to ensure their employees receive immediate attention if they are injured or taken ill at work.
While the 1981 Regulations primarily address direct employees, in construction project environments managed under CDM 2015 , the Principal Contractor must coordinate first aid arrangements across all sub-contractors and self-employed operatives on site to ensure seamless emergency medical cover across the entire workforce.
The First Aid Needs Assessment
Employers cannot rely on arbitrary first aid ratios. First aid provision must be determined by conducting a thorough, documented First Aid Needs Assessment . In construction, which is legally classified as a high-hazard environment , the assessment must evaluate six core risk factors:
Nature of Workplace Hazards: Construction involves major trauma risks (falls from height, heavy plant crush injuries, electrocution, structural collapse, hazardous chemicals, power tool lacerations). Higher hazard levels mandate higher numbers of fully qualified First Aiders at Work.
Workforce Size and Composition: Total peak headcount including sub-contractors, agency staff, and part-time workers. Ratios must accommodate fluctuations as site trades increase.
Site Layout and Geography: Multi-story buildings, sprawling civil engineering projects, or subterranean works require multiple distributed first aid stations rather than a single central kit.
Shift Patterns and Out-of-Hours Work: First aid cover must be continuous during all working hours, including night shifts, weekend overtime, and early morning deliveries.
Distance to Emergency Medical Services: Proximity and travel time to the nearest NHS Accident & Emergency (A&E) hospital. Remote sites require advanced first aid equipment and higher trained personnel.
Accident History: Analysis of historical accident logs (BI 510) and near-miss records to identify recurring injury hot-spots on site.
Tiers of First Aid Personnel & Qualification Standards
The regulations establish three distinct levels of first aid personnel based on formal training and qualification standards.
1. First Aider at Work (FAW)
Qualification: Holds a valid 3-year FAW certificate issued by an approved training provider following completion of a 18-to-24 hour (3-day) training course.
Competence: Qualified to administer CPR, operate Automated External Defibrillators (AEDs), handle severe arterial bleeding, manage spinal injuries, treat burns, eye injuries, fractures, anaphylaxis, and shock.
Construction Ratio Guidance: In high-hazard construction, HSE guidance recommends a minimum of 1 FAW per 50 workers (or part thereof).
2. Emergency First Aider at Work (EFAW)
Qualification: Holds a valid 3-year EFAW certificate following a 6-hour (1-day) training course.
Competence: Trained in basic emergency first aid, CPR, AED usage, minor bleeding control, and managing an unconscious breathing casualty.
Application: Suitable for lower-risk office environments, small low-hazard sub-contractor packages, or as secondary support to FAW personnel.
3. Appointed Person
Role: Designated individual responsible for taking charge of first aid equipment, restocking supplies, and dialing 999/112 to call emergency medical services.
Critical Limitation: An Appointed Person is NOT a qualified first aider . They must NOT administer clinical first aid treatment unless they hold a valid FAW or EFAW certificate. Appointed persons are permitted only on small, low-hazard setups where a needs assessment demonstrates a full first aider is unnecessary.
First Aid Equipment & BS 8599-1 Standards
First aid equipment must be housed in suitable containers and kept easily accessible across the site.
Container Specifications
Design: Rigid, dust-proof, moisture-resistant green containers marked prominently with a white cross on a green background (complying with Safety Signs Regulations 1996).
Location: Positioned near high-risk work areas, site offices, welfare rest rooms, and inside mobile plant/site vehicles.
Mandatory Contents under BS 8599-1 (Workplace First Aid Kits)
Kits must be stocked in accordance with BS 8599-1 standards (Small, Medium, Large, or Travel kits based on worker numbers):
- Kit Component Purpose & Standard Specification
- Sterile Adhesive Plasters Assorted waterproof plasters for minor cuts/abrasions
- Sterile Eye Pads Protect injured eyes from contamination
- Triangular Bandages Support fractured limbs or secure large wound dressings
- Sterile Wound Dressings Medium & large unmedicated sterile pads with attached bandages
- Nitrile Gloves & Face Shields Medical grade protective gloves and CPR resuscitation face shields
- Burn Gel Dressings Sterile hydrogel dressings for thermal or chemical burns
Sterile Eyewash Saline 500ml bottles of 0.9% sterile saline solution (mandatory where mains water is unavailable)
Strict Prohibition of Medications
First aid containers must NEVER contain oral medications, painkillers (paracetamol, aspirin, ibuprofen), antiseptic creams, or prescription drugs. First aiders are not legally permitted to administer drugs, as doing so carries severe risks of triggering life-threatening allergic reactions (anaphylaxis) or masking underlying clinical symptoms.
First Aid Treatment Rooms & Emergency Coordination
On large construction sites employing 250 or more personnel , or on high-risk projects located distant from hospital facilities (e.g. tunneling, marine works), a dedicated First Aid Treatment Room must be provided.
Mandatory Standards for First Aid Rooms
Clean, adequately heated, ventilated, well-lit, and dedicated exclusively to medical treatment.
Equipped with a hand-wash basin with hot and cold running water, soap, disposable paper towels, examination couch, refuse bin for clinical waste, stretcher, and an Automated External Defibrillator (AED) .
Positioned near ground level with wide access doors allowing easy stretcher and paramedic entry.
Emergency Response Notices
Noticeboards displaying clear, legible first aid signs must be posted in all welfare units and work areas, stating:
Names and site contact telephone numbers of all qualified First Aiders on duty.
Exact location of first aid kits, AEDs, and the first aid room.
Emergency procedure details: Site postcode, Ordnance Survey grid reference, and entrance rendezvous point where a designated marshal will meet arriving emergency ambulances.