6.2 Site Traffic Management, Pedestrian-Vehicle Segregation & Delivery Logistics
CITB Site Management Safety Training Scheme SMSTS
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Legal Framework, CDM 2015 & Health and Safety Management
1.1 How the SMSTS Course and Examination Actually Work 1.2 Health and Safety at Work etc. Act 1974 (HASAWA) & Statutory Duties 1.3 Management of Health and Safety at Work Regulations 1999 & HSG65 (Plan-Do-Check-Act) 1.4 CDM 2015 Overview & Five Duty Holders (Client, Principal Designer, Principal Contractor, Designer, Contractor) 1.5 CDM 2015 Project Documentation: PCI, Construction Phase Plan & Health and Safety File 1.6 Statutory Notifications (F10), Enforcement Notices (Improvement/Prohibition), and Fee for Intervention (FFI) 1.7 RIDDOR 2013: Reporting Over-7-Day Injuries, Specified Injuries, Occupational Diseases & Dangerous Occurrences
2 Chapter 2: Risk Management, RAMS & Site Safety Leadership
2.1 Principles of Risk Assessment & Five Steps to Risk Assessment 2.2 Hierarchy of Control Measures & Risk Matrices 2.3 Developing, Reviewing, and Implementing Risk Assessments & Method Statements (RAMS) 2.4 Permit to Work (PTW) Systems for High-Risk Activities 2.5 Worker Consultation, Toolbox Talks, and Safety Leadership Culture 2.6 Behavioural Safety, Human Factors, and Accident Investigation Techniques
3 Chapter 3: High-Risk Site Operations: Height, Excavations & Confined Spaces
3.1 Work at Height Regulations 2005 & Hierarchy of Control for Height Work 3.2 Scaffolding Standards (TG20, BS EN 12811) & Statutory 7-Day Inspection Regimes 3.3 Mobile Elevating Work Platforms (MEWPs), Ladders, Tower Scaffolds & Fragile Roof Safety 3.4 Excavation Safety: Preventing Ground Collapse, Shoring, Battering & Edge Protection 3.5 Underground Services Avoidance (HSG47): Cable Avoidance Tools (CAT) & Genny Operation 3.6 Confined Spaces Regulations 1997: Risk Assessment, Atmosphere Testing & Rescue Procedures 3.7 Temporary Works Management: BS 5975-1, Coordinator Roles & Permits to Load and Strike
4 Chapter 4: Occupational Health, Chemical Safety & Physical Hazards
4.1 Control of Substances Hazardous to Health (COSHH) Regulations & Exposure Limits 4.2 Respirable Crystalline Silica (RCS), Dust Control & Respiratory Protective Equipment (RPE) 4.3 Asbestos Management on Construction Sites: Control of Asbestos Regulations 2012 4.4 Noise at Work Regulations 2005 & Hand-Arm Vibration Syndrome (HAVS) Exposure Action Values 4.5 Manual Handling Operations Regulations 1992, Ergonomics & Musculoskeletal Health 4.6 Health Surveillance, Medical Fitness & Workplace Hygiene/Wellbeing 4.7 Lead in Buildings: Control of Lead at Work Regulations 2002 & Blood-Lead Surveillance 4.8 Drugs and Alcohol at Work: Legal Framework, Site Policy, Testing & Support
5 Chapter 5: Fire Safety, Electrical Protection & Plant Operations
5.1 Fire Prevention on Construction Sites (HSG168), Fire Triangle & Hot Work Permits 5.2 Fire Extinguishers, Means of Escape, LPG Storage & Emergency Evacuation Plans 5.3 Electricity at Work Regulations 1989 & Safe Isolation Procedures 5.4 110V Reduced Low Voltage Systems, RCDs & Overhead Power Lines Safety (GS6) 5.5 Provision and Use of Work Equipment Regulations 1998 (PUWER) & Equipment Inspections 5.6 Lifting Operations and Lifting Equipment Regulations 1998 (LOLER), Crane Safety & Rigging
6 Chapter 6: Site Setup, Logistics, Welfare & Environmental Protection
6.1 CDM 2015 Schedule 2 Welfare Facilities Standards & Site Setup Requirements 6.2 Site Traffic Management, Pedestrian-Vehicle Segregation & Delivery Logistics 6.3 Site Inductions, Security, Signage & Competence Verification (CSCS/CPCS) 6.4 First Aid at Work Regulations 1981: Needs Assessment, First Aiders & Equipment 6.5 Environmental Protection: Waste Management (Duty of Care), Pollution Prevention & Noise Control 6.6 Mobile Workforce, Lone Working & Driving for Work
6.2 Site Traffic Management, Pedestrian-Vehicle Segregation & Delivery Logistics
Key Takeaways Explain This Topic AI
Complete physical segregation of pedestrians and vehicles is the single most effective control measure to eliminate workplace transport fatalities and serious injuries.
Construction traffic routes must follow strict design principles: one-way circulation systems, elimination of reversing, defined speed limits (5–10 mph), and rigid pedestrian barriers.
Reversing operations represent the highest-risk vehicle maneuver and must be controlled using Trained Vehicle Marshals (Banksmen), 360-degree visibility aids, and physical exclusion zones.
Delivery logistics require pre-booking schedules, off-site holding areas, flat firm unloading bays, and vehicle fall protection (edge protection, soft landing bags).
Traffic Management Plans (TMP) must be established prior to work commencing, reviewed regularly as site layout evolves, and communicated during site inductions.
Last updated: August 2026
Workplace Transport Hazards in Construction
Workplace transport accidents remain one of the leading causes of fatalities, major amputations, and catastrophic injuries on UK construction sites. According to HSE statistics, incidents involving moving vehicles—such as excavators, forward-tipping dumpers, telehandlers, and heavy goods vehicles (HGVs)—account for approximately 20% of all site fatalities annually. Common incident mechanisms include workers being struck or run over by reversing plant, operatives crushed between vehicles and fixed structures, vehicles overturning on embankment slopes, and falls from vehicle loading beds during unstrapping operations.
Statutory requirements for managing transport safety are established under CDM 2015 Regulation 27 and Schedule 3 (Workplace Transport Safety) , alongside Regulation 17 of the Workplace (Health, Safety and Welfare) Regulations 1992 . These regulations place a strict duty on site managers and Principal Contractors to organize construction sites so that vehicles and pedestrians can move safely without risk to health.
Principles of Pedestrian-Vehicle Segregation
The primary principle of site traffic management is complete physical segregation of pedestrians and vehicles . Relying on administrative rules or high-visibility clothing alone is insufficient. Site management must establish robust physical controls:
1. Physical Separation Barriers
Rigid Barrier Systems: Pedestrian routes alongside vehicle roads must be protected by heavy-duty rigid barriers—such as interlocking steel fencing, concrete Jersey barriers, or Armco crash barriers. Plastic water-filled barriers or flexible barrier tape are unsuitable along heavy vehicle routes as they offer zero physical impact protection.
Clear Footpaths & Surfaces: Walkways must be well-drained, firm, free from tripping hazards or debris, and adequately lit during darkness or winter working hours.
2. Pedestrian Access & Crossing Points
Dedicated Pedestrian Entrances: Pedestrians must enter the site via dedicated turnstiles or pedestrian gates separated by physical hoarding from vehicle access gates.
Controlled Crossing Points: Where footpaths cross vehicle routes, crossing points must be clearly designated with drop-bars, high-visibility signage, non-slip rubber matting or zebra markings, and clear sightlines. Pedestrians must be given clear right-of-way priority.
3. Personal Protective Equipment (PPE)
All personnel entering active traffic zones must wear High-Visibility Clothing complying with BS EN ISO 20471 (Class 2 waistcoats or Class 3 long-sleeved jacket/trouser combinations in retro-reflective orange or yellow). High-visibility PPE serves as a final line of defense to enhance conspicuity but never substitutes for physical segregation.
Designing Safe Site Traffic Routes
Traffic management must be designed during the pre-construction planning stage and detailed within the Site Traffic Management Plan (TMP) .
Key Route Layout Standards
One-Way Circulation Systems: Sites should establish one-way traffic circuits wherever space permits. One-way systems eliminate head-on vehicle conflicts and drastically reduce the need for reversing.
Speed Management: Site speed limits must be set low—typically 5 mph or 10 mph depending on site conditions. Speed limits must be enforced using speed humps, clear signage, and radar speed displays.
Gradient and Surface Conditions: Haul roads must be constructed on stable foundations, regularly graded to remove ruts and potholes, and dampened with water suppression tankers during dry periods to control dust emissions.
Overhead Hazard Protection ("Goalposts"): Where traffic routes pass beneath overhead electric power lines or low overhead structures, rigid non-conducting warning structures ( "Goalposts" ) equipped with bunting and high-visibility danger signs must be erected at defined warning distances to prevent boom or tipper body strikes.
Vehicle Reversing & Vehicle Marshal (Banksman) Controls
Vehicle reversing is the single highest-risk transport maneuver on construction sites. The control of reversing must follow a strict statutory risk hierarchy: Hierarchy of Reversing Control Measures:
- 1. ELIMINATE reversing entirely (One-way systems / drive-through loading bays)
- 2. MINIMIZE reversing distances and frequency (Turning circles / drive-in bays)
- 3. PROVIDE visibility aids & engineering controls (360° cameras, white-noise alarms, radar sensors)
- 4. UTILIZE trained Vehicle Marshals / Traffic Marshals in designated safe zones
- Vehicle Marshals (Traffic Banksmen)
Where reversing cannot be eliminated, it must be directed by a qualified Vehicle Marshal (Traffic Banksman) holding a valid CPCS or CSCS Traffic Marshal card:
Position of Safety: The marshal must remain in constant clear sight of the driver at all times while positioned in a safe location outside vehicle blind spots and turning radiuses.
Stopping Movement: If the driver loses sight of the marshal, the driver must immediately STOP the vehicle.
Standardized Hand Signals: Marshals must use official BS 6736 hand signals or two-way radio communication.
Delivery Logistics & Loading/Unloading Safety
Unmanaged HGV deliveries cause off-site traffic congestion, public hazards, and severe on-site loading accidents.
Delivery Stage Safety & Logistics Control Measure
Pre-Booking Implement delivery booking system (e.g. Voyage Control) to stagger arrivals and avoid school pick-up hours
Off-Site Holding Establish off-site vehicle holding areas to prevent HGVs queuing on public highways
Unloading Bays Designated flat, firm, level unloading bays isolated from pedestrian footpaths and overhead power lines
Fall Protection Vehicle bed edge protection rails, overhead fall-arrest wire lines, or inflatable soft-landing bags for unstrapping
Plant Safety Telehandlers/cranes loading vehicles must establish exclusion zones using cones and barriers during lifting
Workplace Transport Control Measures Matrix
Transport Hazard Statutory Reference Mandatory Control Measure Secondary Safety Equipment
Pedestrian Collision CDM 2015 Schedule 3 Rigid physical barrier segregation & dedicated turnstiles Class 2/3 High-visibility PPE
Vehicle Reversing Workplace Regs 1992 R17 Drive-through one-way routes / CPCS Vehicle Marshal 360° cameras & white-noise reversing alarms
Overhead Line Strike GS6 (HSE Guidance) Non-conducting timber/fiberglass goalposts & bunting Height restriction barrier signs
Falls from Vehicle Bed Work at Height Regs 2005 Ground-based unstrapping / trailer edge protection rails Inflatable air bags / fall-arrest harnesses
Overturning Plant PUWER 1998 Reg 25 Rollover Protective Structures (ROPS) & seatbelt enforcement Slopes engineered < 1:4 gradient