Study guide

15.5 Completion, Post-Completion and Delay Remedies

Solicitors Qualifying Examination Part 1 SQE1

Track your progress as you read

Finished sections get a check mark.

1 Introduction and Exam Overview

1.1 Current SQE1 Exam Facts 1.2 Single Best Answer Technique and Assessment Day 1.3 Qualifying as a Solicitor After SQE1

2 Ethics and Professional Conduct

2.1 The SRA Principles 2.2 Code of Conduct: Clients, Confidentiality and Disclosure 2.3 Conflicts, Undertakings and Duties to the Court 2.4 Firms, Managers and Compliance Officers 2.5 SRA Warning Notices: NDAs and SLAPPs

3 Business Organisations and Finance

3.1 Business Organisations, Personality and Limited Liability 3.2 Incorporation, Constitutions and Companies House 3.3 Financing: Debt, Equity, Security and Distributions 3.4 Partnership Decision-Making and Authority

4 Business Governance, Insolvency and Tax

4.1 Directors' Duties and Powers 4.2 Shareholders, Meetings, Filings and Minority Protection 4.3 Insolvency: Options and Procedures 4.4 Claw-Back of Assets and Order of Priority 4.5 Income Tax for Businesses 4.6 Capital Gains Tax for Businesses 4.7 Corporation Tax 4.8 VAT and Business Property Relief

5 Starting and Pleading a Civil Claim

5.1 Choosing Arbitration, Mediation or Litigation 5.2 Limitation, Pre-Action Conduct and Applicable Law 5.3 Where to Start, Issue and Service 5.4 Responding to a Claim and Statements of Case

6 Case Management, Trial, Costs and Enforcement

6.1 Interim Applications 6.2 Case Management, Sanctions and CCMCs 6.3 Evidence, Disclosure and Privilege 6.4 Trial and Costs Management 6.5 Part 36, Security for Costs and Assessed Costs 6.6 Appeals and Enforcement of Money Judgments

7 Contract Formation, Parties and Terms

7.1 Formation of Contract 7.2 Parties, Privity and Third-Party Rights 7.3 Express Terms, Incorporation, Implication and Variation 7.4 Exemption Clauses, Unfair Terms, Classification and Interpretation

8 Vitiating Factors, Termination and Remedies

8.1 Vitiating Factors 8.2 Termination of Contract 8.3 Remedies, Causation and Remoteness

9 Negligence, Defences and Vicarious Liability

9.1 Duty of Care and Breach 9.2 Causation, Remoteness and Personal Injury Remedies 9.3 Economic Loss, Psychiatric Harm and Employers' Primary Liability 9.4 Defences and Vicarious Liability

10 Occupiers, Products, Nuisance and Rylands

10.1 Occupiers' Liability 10.2 Product Liability 10.3 Nuisance and Rylands v Fletcher

11 Courts, Precedent and Legislation

11.1 Courts, Judicial Function and Rights of Audience 11.2 Precedent and Case Law 11.3 Primary Legislation in England and in Wales 11.4 Statutory Interpretation

12 Constitution, Judicial Review, Human Rights and EU Law

12.1 Constitutional Institutions, Devolution and the Rule of Law 12.2 Judicial Review and Public Order 12.3 Human Rights Act 1998 and EU Law in the UK Constitution

13 Legal Services Regulation, Equality and AML

13.1 SRA Regulation, Reserved Activities and PII 13.2 Equality Act 2010 in Legal Services 13.3 Money Laundering: Purpose, Scope and Reporting 13.4 POCA Offences, Defences and Due Diligence

14 Financial Services and Funding Legal Services

14.1 The FSMA Perimeter and Authorisation 14.2 Section 327, Scope Rules and Insurance Distribution 14.3 Retainers, Fixed Fees, CFAs and DBAs 14.4 Civil Legal Aid, Third-Party Funding and Insurance

15 Freehold Conveyancing Practice

15.1 Investigating Freehold Title 15.2 Pre-Contract Searches and Enquiries 15.3 Finance and Acting for a Lender 15.4 Drafting the Contract and Exchange 15.5 Completion, Post-Completion and Delay Remedies

16 Leasehold Practice, Security of Tenure, Planning and Property Tax

16.1 Lease Structure and Granting a Lease 16.2 Assignment, Covenants and Remedies 16.3 Business Security of Tenure (Landlord and Tenant Act 1954 Part II) 16.4 Planning Law and Property Taxation

17 Land: Estates, Title and Co-ownership

17.1 The Nature of Land, Estates and Interests 17.2 Acquiring, Transferring and Protecting Interests in Land 17.3 Registered and Unregistered Title 17.4 Co-ownership and Trusts of Land

18 Easements, Covenants, Mortgages and Leases

18.1 Easements 18.2 Freehold Covenants 18.3 Mortgages 18.4 Leases and Licences 18.5 Passing and Enforcing Leasehold Covenants

19 Wills, Revocation and Intestacy

19.1 Validity of Wills and Codicils 19.2 Executors, Alterations, Revocation and Interpretation 19.3 Intestacy and Property Passing Outside the Estate

20 Grants, Administration of Estates and Inheritance Tax

20.1 Grants of Representation and Order of Priority 20.2 Valuation, Excepted Estates and the Burden of IHT 20.3 Administration of Estates 20.4 Family Provision Claims under the 1975 Act 20.5 Inheritance Tax: Lifetime Transfers, Death and Reliefs 20.6 Income Tax and CGT During Administration

21 Express Trusts, Resulting Trusts and the Family Home

21.1 Express Trusts: Certainties, Formalities and Constitution 21.2 Beneficial Entitlement and Purpose Trusts 21.3 Resulting Trusts and Trusts of the Family Home

22 Fiduciaries, Trustees and Breach of Trust

22.1 Fiduciary Obligations and Liability of Strangers 22.2 Trustees: Appointment, Retirement and Removal 22.3 Trustees' Duties: Care, Investment and Advancement 22.4 Breach of Trust, Tracing and Equitable Remedies

23 Solicitors' Accounts

23.1 Client Money and the Client Account 23.2 Interest, Breaches and Corrections 23.3 Ledgers, Bills, Third-Party Accounts and Reports

24 Criminal Liability: Offences Against the Person and Defences

24.1 Actus Reus, Mens Rea, Parties and Attempts 24.2 Non-Fatal Offences Against the Person 24.3 Homicide and Partial Defences 24.4 General Defences

25 Theft, Criminal Damage and Fraud

25.1 Theft, Robbery and Burglary 25.2 Criminal Damage 25.3 Fraud

26 Police Station, Bail and Allocation

26.1 Advising at the Police Station 26.2 Bail and First Hearings 26.3 Plea Before Venue, Allocation, Case Management and Disclosure

27 Evidence, Trial, Sentencing, Appeals and Youth Court

27.1 Burden of Proof, Identification and Silence 27.2 Hearsay, Confessions, Bad Character and Exclusion 27.3 Trial Procedure in the Magistrates' Court and Crown Court 27.4 Sentencing 27.5 Appeals in Criminal Practice 27.6 Youth Court Procedure and the Welsh Language

15.5 Completion, Post-Completion and Delay Remedies

Key Takeaways Explain This Topic AI

If completion is late, time is not automatically of the essence: contractual compensation can run at the contract rate, a notice to complete can give 10 working days, and common law damages, rescission, and deposit remedies then follow the facts.

A notice to complete makes time of the essence and gives the standard period for completion, after which the innocent party's contractual remedies, including the deposit consequences, become available.

Registration is not a formality: a registrable disposition does not operate at law until it is completed by registration, so post-completion delay can cost the client priority.

Last updated: September 2026

Transfer deed, pre-completion, apportionments, completion, and after

The usual transfer of a whole registered freehold is TR1 (TP1 for part). Unregistered land being sold will generally be transferred by a deed that is then used for first registration . Execution formalities are not optional:

an individual executes a deed by signing in the presence of a witness who attests ( Law of Property (Miscellaneous Provisions) Act 1989, s.1 );

a company executes under the Companies Act 2006 rules (two authorised signatories, or a director in the presence of a witness, or the seal if used);

attorneys need a power that authorises the disposition;

the transfer is usually executed before completion and dated on completion , when it is delivered.

Prescribed clauses, consideration, title guarantee, a declaration of trust if co-buyers are tenants in common, an indemnity covenant if required, and any restriction must be right before you send the document for signature. A TR1 that names the wrong proprietor, or that omits the lender's restriction, will come back from Land Registry after the priority period has started to run.

Pre-completion searches and steps

OS1 (whole) or OS2 (part) against the title, giving a priority period of 30 working days for the buyer's application;

K15 Land Charges if the title is still unregistered, and K16 bankruptcy searches against individual borrowers (and as the Handbook requires);

a company search if a corporate party might be in insolvency;

TA13 completion information and undertakings on Protocol files: vacant possession arrangements, keys, undertakings to discharge, and the seller's solicitor's bank details;

a redemption statement for the seller's charge, with per diem interest;

the completion statement : price, less deposit, plus or minus apportionments , plus any contractual additions, less the mortgage advance on a purchase, leaving the balance to send by same-day transfer.

Apportionments are the financial consideration the specification names expressly. Under the SCS, income and outgoings of the property are apportioned as at completion. On a freehold that may mean an estate service charge, a rentcharge, or insurance. Council tax and utility bills are often dealt with outside the strict contractual apportionment, but they still affect what you tell the client to pay on the day. On SCPC files, rent and service charge apportionments can be large; getting the completion date wrong by one day moves real money. Do not mix up apportionments with SDLT or LTT: those are taxes on the transaction, taught in the later chapter, with a 14-day SDLT filing window in England and a 30-day LTT window in Wales. You still need the cleared funds and the diary entries on this file.

Methods and effect of completion. Residential files almost always complete under the Law Society Code for Completion by Post . The seller's solicitor receives the money, and on completion undertakes to date and release the transfer, to hold the documents to the buyer's order, and to redeem and evidence discharge of the seller's charge. Keys are then released through the agent. Personal completion (all parties in one room) is rare. The effect of completion is that the buyer becomes entitled to possession and to the seller's interest in the land. On registered land, the legal estate moves on registration ; the OS1 priority period exists so that the buyer and lender are not overtaken while the AP1 is processed. If you complete and then miss the priority window, you have completed into a risk you were paid to avoid.

Post-completion: date the transfer if not already dated; submit the SDLT or LTT return and obtain the certificate needed for registration; apply to register the transfer and the new charge (AP1) within the OS1 period; register a company charge at Companies House within 21 days where the borrower is a company; send the discharge evidence (electronic discharge or DS1) through; report to client and lender; pay the estate agent if so instructed; close the file only when the new official copies show what you certified they would show.

Delayed completion remedies

Time is not of the essence of a completion date merely because a date appears in the contract ( Raineri v Miles is the common-law backdrop; the standard conditions then overlay a scheme). If someone is late, you still have a contract. The remedies are cumulative in the sense the exam cares about: know which one needs a notice, which one needs proof of loss, and which one can kill the contract.

Remedy When it bites What it gives you What it does not do by itself

Common law damages Breach (late completion, or failure to complete) Compensation for loss caused by the breach, subject to remoteness ( Hadley v Baxendale ) and mitigation: extra bridging, extra rent, wasted storage, loss of bargain if the contract later goes Does not make time of the essence; does not automatically forfeit the deposit

Contractual compensation Standard conditions (SCS 7.2 and the SCPC equivalent) once completion is delayed A daily sum at the contract rate on the unpaid balance (price less deposit paid), without proving that this was the actual cost of money Does not, without more, rescind the contract; you cannot double-recover the same interest-like loss as damages and compensation

Notice to complete After the completion date, served by a party who is ready, able and willing Makes time of the essence and requires completion within 10 working days (standard conditions) A party who is not themselves able to complete cannot validly serve

Rescission Typically after unremedied failure to comply with a notice to complete, or for a contractual right to rescind Contract ends; deposit is forfeited or repaid according to who is in default; damages may still be available You must follow the contractual machinery; walking away on day one of delay is not rescission

Ready, able and willing is the trap. A seller who has not procured a redemption figure or an executed TR1 is not ready. A buyer who has not got the balance of funds is not ready. Serving a notice you were not entitled to serve wastes time and can rebound.

If the buyer fails to complete after a valid notice, the seller may rescind, forfeit the deposit , and claim damages. If the deposit paid was less than 10%, the standard conditions commonly let the seller recover the unpaid balance of that 10% as well. If the seller fails, the buyer may rescind, recover the deposit, and claim damages. Specific performance remains a possible additional path where damages are not an adequate remedy and the court will compel a sale of unique land.

Worked rhythm for the exam: completion date missed → check who is in default and whether you are ready → claim contractual compensation while the contract is alive → if you need to force the issue, serve a notice to complete → if the notice expires unused, rescind and then sort deposit and common law damages . Do not jump straight from a missed 2pm completion to rescission without the notice machinery the standard conditions require.

That is the freehold practice loop. Title and searches tell you whether to exchange. Finance and the certificate of title tell you whether the money will be there. The contract, the formulae, the TR1, the OS1, and the delay remedies tell you how the file starts, how it finishes, and what you do when it does not finish on time.