5.1 Progress Billing, Schedule of Values & AIA G702/G703
Florida Construction Business and Finance Exam Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Business Organization & Corporate Governance
1.1 Business Organizational Structures & Personal Liability 1.2 Fiduciary Duties, Officers & Qualifying Agent Responsibilities 1.3 Licensing Scope, Name Registration & Business Setup
2 Chapter 2: Business Planning, Capitalization & Commercial Insurance
2.1 Contractor Business Planning, Capitalization & Working Capital 2.2 Professional Advisory Relationships & Fixed Asset Acquisition 2.3 Commercial Insurance Coverage for Contractors
3 Chapter 3: Estimating, Overhead Allocation & Bid Preparation
3.1 Estimating Principles, Direct Costs & Quantity Takeoffs 3.2 Business Overhead Determination & Allocation Methods 3.3 Bid Preparation, Markup vs. Margin Calculations & Submission
4 Chapter 4: Construction Contracts & AIA Standard Agreements
4.1 Construction Contract Types & Essential Clauses 4.2 AIA Document A201 General Conditions of the Contract 4.3 AIA Document A401 Subcontract Agreements & Flow-Down Provisions
5 Chapter 5: Project Billing, Invoicing & Jobsite Safety Management
5.1 Progress Billing, Schedule of Values & AIA G702/G703 5.2 Change Orders, Construction Change Directives & Claims Management 5.3 Developing Written Safety Programs & Hazard Communication
6 Chapter 6: Project Scheduling, Critical Path Method & Trade Coordination
6.1 Critical Path Method (CPM) Scheduling Fundamentals 6.2 Total Float, Free Float & Critical Path Identification 6.3 Trade Sequencing, Submittal Logs & Requests for Information
7 Chapter 7: Logistics, Inventory Management & Jobsite Safety Recordkeeping
7.1 Material Procurement, Inventory Management & Fleet Operations 7.2 OSHA Recordkeeping, Injury Logs & Reporting Mandates
8 Chapter 8: Construction Accounting Fundamentals & Financial Statements
8.1 Construction Accounting Methods & Revenue Recognition 8.2 The Construction Balance Sheet & Working Capital Management 8.3 The Income Statement, Direct Costs & Gross Profit Analysis
9 Chapter 9: Financial Ratio Analysis, Job Costing & Work-in-Progress (WIP)
9.1 Construction Financial Ratio Analysis & Benchmarks 9.2 Job Cost Accounting, CSI Cost Codes & Variance Reporting 9.3 Work-in-Progress (WIP) Schedule & Over/Under-Billing
10 Chapter 10: Cash Management, Receivables, Payroll Burden & Tax Compliance
10.1 Cash Flow Projections, Receivables Management & Collections 10.2 Accounts Payable, Vendor Terms & 2/10 Net 30 Mathematics 10.3 Comprehensive Payroll Burden & Direct Labor Costing 10.4 Federal and Florida Tax Compliance & Statutory Filings
11 Chapter 11: Human Resources, Labor Regulations & Prevailing Wage
11.1 Employment Discrimination, Labor Relations & Hiring Regulations 11.2 Worker Classification (W-2 vs. 1099), I-9 & Florida E-Verify 11.3 Fair Labor Standards Act (FLSA) & Davis-Bacon Prevailing Wage
12 Chapter 12: Florida Construction Licensing Law & Business Governance
12.1 DBPR, CILB & Florida Contractor Licensing Structure 12.2 Qualifying Agents, Business Entities & Fiduciary Duties 12.3 CILB Disciplinary Grounds, Fines & Unlicensed Contracting
13 Chapter 13: Florida Construction Lien Law & Public Payment Bonds
13.1 Florida Lien Law (F.S. Chapter 713) Foundations & Notice to Owner (NTO) 13.2 Claim of Lien Perfection, 90-Day Deadlines & Foreclosure 13.3 Florida Public Payment Bonds & Florida Little Miller Act
14 Chapter 14: Workers' Compensation, Environmental Compliance & Safety Regulations
14.1 Florida Workers' Compensation Law (F.S. Chapter 440) 14.2 Environmental Protection, NPDES Stormwater & Asbestos / Lead
5.1 Progress Billing, Schedule of Values & AIA G702/G703
Key Takeaways Explain This Topic AI
The Schedule of Values (SOV) provides the structural foundation for progress payments, allocating the total contract sum across discrete project work packages and CSI divisions.
Unbalanced front-loading of the SOV—inflating early milestone values to finance ongoing operations—violates contract terms, compromises surety bonding, and exposes contractors to civil liability.
AIA Document G702 (Application and Certificate for Payment) summarizes contract status, tracking original contract sum, net change orders, completed work, stored materials, and retainage.
AIA Document G703 (Continuation Sheet) breaks down individual line items, calculating work completed from previous applications, work completed this period, and stored materials.
Under AIA A201 Section 9.3.2, off-site stored-material payment requires advance owner approval, a storage location agreed to in writing, and owner-satisfactory procedures that establish title or otherwise protect the owner's interest, including applicable insurance, storage, and transportation costs. The standard text does not itself require a “bonded warehouse.”
Last updated: October 2026
Progress Billing, Schedule of Values & AIA G702/G703
Progress billing is the primary mechanism through which cash flows from project owners to prime contractors and downstream subcontractors. In commercial construction, invoicing is not a matter of submitting arbitrary periodic estimates; it is governed by standardized contractual frameworks designed to verify that work billed matches work installed. Under Florida contracting practice and standard American Institute of Architects (AIA) contract administration, progress billing requires two indispensable companion documents: AIA Document G702 (Application and Certificate for Payment) and AIA Document G703 (Continuation Sheet) , both anchored to a pre-approved Schedule of Values (SOV) .
The Schedule of Values (SOV)
Under AIA Document A201 (General Conditions of the Contract for Construction, Section 9.2), the contractor must submit a comprehensive Schedule of Values to the architect before submitting the initial application for payment. The SOV allocates the entire contract sum across individual work packages, categorized by Construction Specifications Institute (CSI) MasterFormat divisions (e.g., Division 03 Concrete, Division 04 Masonry, Division 26 Electrical).
Requirements for an Acceptable Schedule of Values
Substantiating Data: The contractor must support each line item with verified subcontractor agreements, material purchase orders, and internal cost breakdowns.
Direct Cost Alignment: Values assigned to line items must reflect true anticipated direct costs plus a proportionate share of project general conditions, overhead, and profit.
Owner/Architect Approval: Once approved, the SOV serves as the sole basis for reviewing and auditing subsequent monthly pay applications.
The Legal and Financial Risks of "Front-Loading"
Front-loading is the practice of artificially inflating the allocated monetary values of early project activities (e.g., site clearing, mobilization, earthwork, foundations) while artificially depressing the values of later project phases (e.g., painting, flooring, mechanical trim-out, commissioning).
While contractors often attempt front-loading to generate early working capital and offset mobilization deficits, the practice carries severe consequences:
Breach of Contract: Architects are contractually mandated to reject front-loaded schedules of values as fraudulent or unrepresentative.
Surety and Lender Vulnerability: If a contractor becomes insolvent mid-project after receiving front-loaded disbursements, the remaining contract balance will be insufficient to complete the remaining work, triggering surety takeover litigation.
Florida Construction Lien & Licensing Violations: Deliberately submitting inflated billing values can be construed as misapplication of construction funds under Florida Statutes § 713.345, subjecting the contractor to criminal penalties and CILB license discipline.
Anatomy and Mathematics of AIA Document G702
AIA Document G702 represents the summary page of the pay application, signed by the contractor and notarized, certifying that work has progressed as indicated and that all previous payments have been applied to satisfy trade obligations.
Line-by-Line Mathematical Mechanics Line 1: Original Contract Sum ................................... \$1,000,000.00
- Line 2: Net Change by Change Orders ............................. +\$50,000.00
- Line 3: Contract Sum to Date (Line 1 ± Line 2) .................. \$1,050,000.00
- Line 4: Total Completed & Stored to Date (from G703 Col. G) ..... \$420,000.00
Line 5: Retainage:
- a. 10% of Completed Work (Col. D + E) ..... \$38,000.00
- b. 10% of Stored Material (Col. F) ........ \$4,000.00
- Total Retainage (Line 5a + 5b) .......................... -\$42,000.00
- Line 6: Total Earned Less Retainage (Line 4 minus Line 5) ....... \$378,000.00
- Line 7: Less Previous Certificates for Payment (Prior Line 6) ... -\$225,000.00
- Line 8: Current Payment Due (Line 6 minus Line 7) ............... \$153,000.00
- Line 9: Balance to Finish, Including Retainage (Line 3 - Line 6) . \$672,000.00
G702 Line Line Description Governing Formula Key Operational Rule
Line 1 Original Contract Sum Fixed Base Value Initial executed contract price.
Line 2 Net Change by Change Orders ∑ Additions − ∑ Deductions \sum \text{Additions} - \sum \text{Deductions} ∑ Additions − ∑ Deductions Only executed, signed Change Orders (AIA G701) may be included. Unapproved claims cannot be billed.
Line 3 Contract Sum to Date Line 1 + Line 2 \text{Line 1} + \text{Line 2} Line 1 + Line 2 The active total contract price.
Line 4 Total Completed & Stored to Date Column G Total from AIA G703 Sum of all work completed to date plus materials currently stored.
Line 5 Total Retainage Line 5a + Line 5b \text{Line 5a} + \text{Line 5b} Line 5a + Line 5b Contractually withheld percentage (e.g., 5% to 10%) to secure completion.
Line 6 Total Earned Less Retainage Line 4 − Line 5 \text{Line 4} - \text{Line 5} Line 4 − Line 5 Cumulative net revenue earned by contractor to date.
Line 7 Less Previous Certificates Line 6 from Previous Month Total net funds previously certified for payment by the architect.
Line 8 Current Payment Due Line 6 − Line 7 \text{Line 6} - \text{Line 7} Line 6 − Line 7 The net cash amount payable for the current billing cycle.
Line 9 Balance to Finish, Including Retainage Line 3 − Line 6 \text{Line 3} - \text{Line 6} Line 3 − Line 6 Remaining unpaid contract funds, representing total future cash flow.
AIA Document G703 (Continuation Sheet)
AIA Document G703 provides the line-item substantiation for Line 4 of Document G702. Every item on the approved SOV appears as a discrete row with nine distinct columns:
Column A (Item No.): Numerical tracking sequence (e.g., 03-100, 03-200).
Column B (Description of Work): Exact trade scope activity.
Column C (Scheduled Value): Approved dollar value from the SOV.
Column D (Work Completed from Previous Applications): Cumulative dollar value of work billed in prior months (excluding materials stored).
Column E (Work Completed this Period): Dollar value of work installed during the current billing cycle.
Column F (Materials Presently Stored): Value of uninstalled materials currently stored on-site or in an approved off-site warehouse.
Column G (Total Completed and Stored to Date): Sum of Columns D, E, and F ( Col. D + Col. E + Col. F \text{Col. D} + \text{Col. E} + \text{Col. F} Col. D + Col. E + Col. F ).
Column H (% Completed / Stored): Column G Column C × 100 \frac{\text{Column G}}{\text{Column C}} \times 100 Column C Column G × 100 .
Column I (Balance to Finish): Column C − Column G \text{Column C} - \text{Column G} Column C − Column G .
Billing for Stored Materials
Contractors frequently purchase long-lead materials (e.g., structural steel, chillers, electrical switchgear) months before installation. Including these materials in Column F of Document G703 is subject to strict contractual safeguards:
1. On-Site Stored Materials
Materials must be delivered to the project site, inventoried, inspected for damage, and stored in a secure, weatherproof area.
The contractor must provide invoices proving acquisition cost, minus delivery or labor charges.
2. Off-Site Stored Materials
Under AIA A201 Section 9.3.2, payment for suitably stored off-site materials requires advance owner approval and a storage location agreed upon in writing. Payment is also conditioned on owner-satisfactory procedures to establish the owner's title or otherwise protect the owner's interest, including applicable insurance, storage, and transportation costs. Project procedures may call for segregation, tagging, bills of sale, certificates of insurance, photographs, or warehouse acknowledgments, but those details come from the contract and the owner's approved procedure—not a universal A201 “bonded warehouse” rule.