13.2 Claim of Lien Perfection, 90-Day Deadlines & Foreclosure
Florida Construction Business and Finance Exam Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Business Organization & Corporate Governance
1.1 Business Organizational Structures & Personal Liability 1.2 Fiduciary Duties, Officers & Qualifying Agent Responsibilities 1.3 Licensing Scope, Name Registration & Business Setup
2 Chapter 2: Business Planning, Capitalization & Commercial Insurance
2.1 Contractor Business Planning, Capitalization & Working Capital 2.2 Professional Advisory Relationships & Fixed Asset Acquisition 2.3 Commercial Insurance Coverage for Contractors
3 Chapter 3: Estimating, Overhead Allocation & Bid Preparation
3.1 Estimating Principles, Direct Costs & Quantity Takeoffs 3.2 Business Overhead Determination & Allocation Methods 3.3 Bid Preparation, Markup vs. Margin Calculations & Submission
4 Chapter 4: Construction Contracts & AIA Standard Agreements
4.1 Construction Contract Types & Essential Clauses 4.2 AIA Document A201 General Conditions of the Contract 4.3 AIA Document A401 Subcontract Agreements & Flow-Down Provisions
5 Chapter 5: Project Billing, Invoicing & Jobsite Safety Management
5.1 Progress Billing, Schedule of Values & AIA G702/G703 5.2 Change Orders, Construction Change Directives & Claims Management 5.3 Developing Written Safety Programs & Hazard Communication
6 Chapter 6: Project Scheduling, Critical Path Method & Trade Coordination
6.1 Critical Path Method (CPM) Scheduling Fundamentals 6.2 Total Float, Free Float & Critical Path Identification 6.3 Trade Sequencing, Submittal Logs & Requests for Information
7 Chapter 7: Logistics, Inventory Management & Jobsite Safety Recordkeeping
7.1 Material Procurement, Inventory Management & Fleet Operations 7.2 OSHA Recordkeeping, Injury Logs & Reporting Mandates
8 Chapter 8: Construction Accounting Fundamentals & Financial Statements
8.1 Construction Accounting Methods & Revenue Recognition 8.2 The Construction Balance Sheet & Working Capital Management 8.3 The Income Statement, Direct Costs & Gross Profit Analysis
9 Chapter 9: Financial Ratio Analysis, Job Costing & Work-in-Progress (WIP)
9.1 Construction Financial Ratio Analysis & Benchmarks 9.2 Job Cost Accounting, CSI Cost Codes & Variance Reporting 9.3 Work-in-Progress (WIP) Schedule & Over/Under-Billing
10 Chapter 10: Cash Management, Receivables, Payroll Burden & Tax Compliance
10.1 Cash Flow Projections, Receivables Management & Collections 10.2 Accounts Payable, Vendor Terms & 2/10 Net 30 Mathematics 10.3 Comprehensive Payroll Burden & Direct Labor Costing 10.4 Federal and Florida Tax Compliance & Statutory Filings
11 Chapter 11: Human Resources, Labor Regulations & Prevailing Wage
11.1 Employment Discrimination, Labor Relations & Hiring Regulations 11.2 Worker Classification (W-2 vs. 1099), I-9 & Florida E-Verify 11.3 Fair Labor Standards Act (FLSA) & Davis-Bacon Prevailing Wage
12 Chapter 12: Florida Construction Licensing Law & Business Governance
12.1 DBPR, CILB & Florida Contractor Licensing Structure 12.2 Qualifying Agents, Business Entities & Fiduciary Duties 12.3 CILB Disciplinary Grounds, Fines & Unlicensed Contracting
13 Chapter 13: Florida Construction Lien Law & Public Payment Bonds
13.1 Florida Lien Law (F.S. Chapter 713) Foundations & Notice to Owner (NTO) 13.2 Claim of Lien Perfection, 90-Day Deadlines & Foreclosure 13.3 Florida Public Payment Bonds & Florida Little Miller Act
14 Chapter 14: Workers' Compensation, Environmental Compliance & Safety Regulations
14.1 Florida Workers' Compensation Law (F.S. Chapter 440) 14.2 Environmental Protection, NPDES Stormwater & Asbestos / Lead
13.2 Claim of Lien Perfection, 90-Day Deadlines & Foreclosure
Key Takeaways Explain This Topic AI
A Claim of Lien must be recorded in the county public records strictly within 90 calendar days from the lienor's final furnishing of labor, services, or materials under F.S. § 713.08.
Warranty repairs, correcting defective work, and incidental punch-list items do not extend or reset the 90-day final furnishing statutory deadline.
A copy of the recorded Claim of Lien must be served on the owner within 15 calendar days of recording pursuant to F.S. § 713.08(4)(c).
Prime contractors in direct privity with the owner must deliver a Contractor's Final Payment Affidavit at least 5 days prior to filing a lien foreclosure lawsuit under F.S. § 713.06(3)(d)1.
The baseline one-year foreclosure statute of limitations under F.S. § 713.22 can be shortened to 60 days via a Notice of Contest of Lien or to 20 days via a Summons to Show Cause.
Last updated: October 2026
13.2 Claim of Lien Perfection, 90-Day Deadlines & Foreclosure
Core Principle: Recording a Claim of Lien under Florida Statutes § 713.08 creates a formal encumbrance on real property title. To enforce this encumbrance, the lienor must strictly adhere to statutory recording deadlines, mandatory service requirements, conditions precedent to litigation, and procedural statutes of limitation.
Perfection of a construction lien converts an unrecorded equitable right into an enforceable, recorded property encumbrance. Failure to meet any statutory deadline in this process results in immediate loss of the lien.
1. Perfecting the Claim of Lien (F.S. § 713.08)
To perfect a construction lien against private real estate, the lienor must record a formal Claim of Lien in the public records of the county where the real property is located.
The Strict 90-Day Recording Deadline
Under Florida Statutes § 713.08(5), the Claim of Lien must be recorded:
Strictly within 90 calendar days after the final furnishing of the labor, services, or materials by the lienor.
This 90-day statutory window is an absolute deadline. Florida courts have no equitable power to extend the 90-day period. If the 90th day falls on a Saturday, Sunday, or legal holiday, the deadline extends to the next business day under Florida Rule of Judicial Administration 2.514, but recording on day 91 under ordinary circumstances renders the lien completely void.
What Constitutes "Final Furnishing"?
Determining the exact date of final furnishing is one of the most frequently litigated issues on the Florida Construction Business and Finance Exam. Florida appellate courts (such as Aronson v. Keating and Home Electric of Dade County, Inc. v. G盖ron ) have established clear legal standards:
Qualifying Final Furnishing: Work performed in good faith, within a reasonable time, pursuant to the original contract requirements or approved change orders, that is substantial and necessary to complete the contractual scope.
Non-Qualifying Work (Does NOT Extend the 90 Days):
Punch-list work of a minor or corrective nature.
Warranty repairs or service calls.
Remedying defective or non-compliant work.
Work performed after long unexplained project abandonment merely to resurrect expired lien rights.
If a roofing contractor finishes the roof installation on August 1 and returns on October 15 under a warranty callback to replace a cracked tile, the final furnishing date remains August 1. The October 15 warranty visit does not reset the 90-day clock.
Mandatory Form & Content of the Claim of Lien
Under F.S. § 713.08(1), the Claim of Lien must be executed under oath before a notary public and state:
Name and address of the lienor.
Name of the person or entity with whom the lienor contracted.
The total labor, services, or materials furnished, and the agreed contract price or value.
Description of the real property sufficient for legal identification.
Name of the property owner.
Date of first furnishing and date of final furnishing.
Total amount remaining unpaid (principal balance only; interest and attorney's fees are excluded from the face of the lien).
2. Serving Copy of Claim of Lien (F.S. § 713.08(4)(c))
Recording the lien in the clerk of court's public records is only the first step. Under Florida Statutes § 713.08(4)(c):
The lienor must serve a copy of the recorded Claim of Lien on the property owner within 15 calendar days after recording.
Service must be accomplished using the authorized methods in F.S. § 713.18 (certified mail, hand delivery, or commercial overnight courier). While failure to serve the copy within 15 days does not automatically void the lien, Florida statute provides that failure to serve is a complete defense to enforcement if the owner demonstrates prejudice or detrimental reliance (e.g., the owner disbursed remaining funds to the general contractor after day 15 without notice of the recorded lien).
3. Contractor's Final Payment Affidavit (F.S. § 713.06(3)(d)1)
A prime contractor (contractor in direct privity with the owner) cannot file a lawsuit to enforce a construction lien without first delivering a formal Contractor's Final Payment Affidavit .
Statutory Timing and Content
Timing: Must be physically delivered to the owner at least 5 days prior to filing any lawsuit to foreclose the lien or enforce the underlying construction contract.
Content: A sworn statement listing the legal names of all lienors contracting under the prime contractor who remain unpaid, specifying the exact amounts due or to become due to each. If all downstream lienors have been paid in full, the affidavit must explicitly swear that all lienors have been paid in full.
Legal Impact: Delivery of the affidavit is a mandatory statutory condition precedent. If a general contractor files a foreclosure lawsuit without serving the affidavit at least 5 days prior, the action is subject to dismissal. If the one-year statute of limitations expires before the affidavit is delivered, the contractor permanently forfeits its lien rights.
4. Foreclosure Actions & Acceleration Mechanisms
A recorded Claim of Lien does not remain valid indefinitely. Florida provides a strict baseline limitation period, as well as two statutory mechanisms that permit property owners to shorten the litigation window.
The Baseline One-Year Statute of Limitations (F.S. § 713.22(1))
Under F.S. § 713.22(1), a construction lien remains valid for a maximum period of 1 year from the date the Claim of Lien was recorded in the county public records. The lienor must file a formal foreclosure lawsuit in the circuit court within that one-year period. If no lawsuit is filed within one year, the lien automatically expires and becomes void by operation of law.
Shortening Mechanism 1: Notice of Contest of Lien (F.S. § 713.22(2))
An owner or owner's attorney seeking to resolve an encumbrance quickly may execute and record a Notice of Contest of Lien in the county public records:
The clerk of the circuit court serves a copy of the recorded Notice of Contest on the lienor at the address listed on the Claim of Lien via certified mail.
Upon service by the clerk, the lienor's deadline to file a foreclosure lawsuit is accelerated from the remainder of the one-year period down to exactly 60 calendar days from the date the clerk serves the notice.
If the lienor fails to file a foreclosure action in circuit court within 60 days, the lien is extinguished by operation of law, and clerk records a discharge.
Shortening Mechanism 2: 20-Day Summons to Show Cause (F.S. § 713.21(4))
An owner can accelerate the deadline even further by filing a civil complaint against the lienor in the circuit court:
The clerk issues a formal Summons to Show Cause pursuant to F.S. § 713.21(4).
The summons is formally served on the lienor, giving the lienor exactly 20 calendar days to file an action enforcing the lien or show cause why the lien should not be cancelled.
If the lienor fails to commence a foreclosure action within 20 days of service, the court enters an immediate order discharging and vacating the Claim of Lien from public records.
5. Fraudulent Liens (F.S. § 713.31)
Florida strictly penalizes contractors or lienors who abuse the lien law process by filing exaggerated or bad-faith claims. Under F.S. § 713.31, a lien is deemed a fraudulent lien if:
- The lienor willfully exaggerates the amount claimed;
- The lienor willfully includes a claim for work not performed or materials not delivered; or
The lienor compiles the claim with such willful and gross negligence as to amount to a willful exaggeration.
Severe Statutory Penalties for Fraudulent Liens
Complete Forfeiture: The lien is completely void, unenforceable, and discharged of record.
Civil Liability: The lienor is liable to the owner for actual damages suffered, court costs, reasonable attorney's fees incurred in invalidating the lien, and punitive damages equal to the difference between the claimed amount and the legitimate amount owed.
Criminal Sanctions: Filing a fraudulent lien is a third-degree felony under Florida law, punishable by up to 5 years imprisonment and disciplinary revocation of construction licenses.
6. Transfer of Lien to Security / "Bonding Off" (F.S. § 713.24)
When a lien clouds title during a pending sale or refinance, the owner is not forced to wait for litigation to conclude. Under F.S. § 713.24, an owner, developer, or contractor can transfer the lien from the real property to alternative security:
Methods of Transfer: Depositing cash with the clerk of the circuit court or filing a surety bond issued by a surety authorized to do business in Florida.
Calculation of Required Security Deposit:
- The face amount of the Claim of Lien; plus
- Statutory interest at the legal rate for 3 years; plus
$1,000 or 25% of the face amount of the lien , whichever is greater, to apply toward court costs and attorney's fees.
Upon recording the certificate of transfer, the real property is instantly released from the lien encumbrance, restoring clear and marketable title to the owner while securing the lienor's recovery against the cash or bond deposit.
Statutory Procedure Action Required Statutory Deadline Statutory Basis
Record Claim of Lien Clerk recording in county of project Within 90 calendar days of final furnishing F.S. § 713.08(5)
Serve Copy of Lien Certified mail or hand delivery to owner Within 15 calendar days of recording F.S. § 713.08(4)(c)
Contractor Final Affidavit Delivery to owner before lawsuit At least 5 days prior to filing suit F.S. § 713.06(3)(d)1
- Baseline Foreclosure File circuit court lawsuit Within 1 year from recording date F.S. § 713.22(1)
- Notice of Contest of Lien File foreclosure lawsuit Within 60 calendar days of clerk service F.S. § 713.22(2)
Summons to Show Cause File foreclosure or show cause Within 20 calendar days of formal service F.S. § 713.21(4)