6.7 Budgeting, Procurement, Inventory & Capital Planning

Virginia Water/Wastewater Operator Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Virginia Licensing, Regulations & Administrative Standards

1.1 Virginia DPOR Board Structure, License Categories & Scope of Practice 1.2 Experience, Education, Substitutions & Examination Approval 1.3 Renewal, Reinstatement, CPE Requirements & Discipline 1.4 Virginia Drinking Water & Wastewater Environmental Governance 1.5 Facility Classification & Minimum Operator Attendance 1.6 The ABC/WPI Exam Blueprint, References & Test-Day Rules 1.7 License Maintenance, Reporting Duties & Professional Conduct

2 Chapter 2: Source Water & Drinking Water Treatment Unit Processes

2.1 Source Water Hydrology, Groundwater Protection & Raw Water Quality 2.2 Coagulation, Flocculation & Sedimentation Processes 2.3 Filtration Technologies & Media Management 2.4 Disinfection Chemistry, CT Calculations & Disinfection Byproducts 2.5 Corrosion Control, Softening & Fluoridation Chemistry 2.6 Pretreatment: Screening, Presedimentation, Aeration & Preoxidation 2.7 Filter Backwash, Surface Wash, Air Scour & Filter Surveillance 2.8 Membrane Systems: MF, UF, NF and RO Operation & Integrity Testing 2.9 Water Treatment Residuals: Handling, Thickening & Disposal 2.10 Chemical Feed Systems: Metering Pumps, Dry Feeders & Calibration 2.11 Process Monitoring, Trend Interpretation & Plant Optimization 2.12 Iron and Manganese, Taste-and-Odor Control, GAC & PFAS

3 Chapter 3: Wastewater Treatment, Biological Processes & Biosolids

3.1 Preliminary Treatment & Primary Clarification 3.2 Activated Sludge Dynamics & Secondary Process Control 3.3 Attached Growth Systems & Advanced Biological Processes 3.4 Biological & Chemical Nutrient Removal (BNR/ENR) 3.5 Solids Thickening, Digestion & Biosolids Management 3.6 Wastewater Characteristics, Influent Loading & Industrial Pretreatment 3.7 Secondary Clarifier Operation & Sludge Blanket Control 3.8 Lagoons, Stabilization Ponds & Natural Treatment Systems 3.9 Tertiary Filtration, Effluent Polishing & Water Reuse 3.10 Wastewater Disinfection & Dechlorination Systems 3.11 Aeration Systems, Blowers, Diffusers & Dissolved Oxygen Control 3.12 Digester Gas Handling, Cogeneration & Gas System Safety 3.13 Biosolids Land Application, Part 503 & Virginia Permitting

4 Chapter 4: Distribution Networks, Collection Systems & Hydraulic Systems

4.1 Water Distribution Networks, Storage & Pressure Management 4.2 Cross-Connection Control & Backflow Prevention Assemblies 4.3 Wastewater Collection Systems, Lift Stations & Inflow/Infiltration 4.4 Centrifugal & Positive Displacement Pumps 4.5 Motors, Drives, Control Systems & SCADA 4.6 Storage Tank Inspection, Meters, Services & Distribution Appurtenances 4.7 Main Disinfection, Flushing & Distribution Water Quality Management 4.8 Sewer Cleaning, CCTV Inspection & Collection System Rehabilitation 4.9 Maintenance Programs, Asset Management & Pump Efficiency Testing 4.10 Odor Control, Standby Power & Ancillary Plant Equipment

5 Chapter 5: Laboratory Analysis, Environmental Safety & Applied Math

5.1 Water & Wastewater Laboratory Analysis & QA/QC Protocols 5.2 Confined Space Entry, Chemical Safety & OSHA/VOSH Compliance 5.3 Hydraulic, Dosage & Pounds Formula Math 5.4 Wastewater Process & Loading Rate Mathematics 5.5 Drinking Water Microbiology & the Revised Total Coliform Rule 5.6 Wastewater Laboratory Analysis: Nutrients, Metals, WET & Regulatory Testing 5.7 Instrument Calibration, Online Analyzers & Data Validation 5.8 Process Control Testing: Jar Tests, Settleometer & Microscopic Examination 5.9 Chemical Receiving, Storage, Spill Response & Hazardous Waste 5.10 Electrical Safety, Fall Protection, Excavation & Traffic Control 5.11 PPE, Respiratory Protection & Biological Hazards 5.12 Advanced Applied Math: Mass Balance, Blending & Efficiency

6 Chapter 6: Regulatory Compliance, Reporting & Plant Administration

6.1 Safe Drinking Water Act Compliance: MCLs, Monitoring & Violations 6.2 Public Notification, Consumer Confidence Reports & Customer Complaints 6.3 VPDES Permit Compliance, DMRs & Overflow Reporting 6.4 Operating Records, Logbooks, Reports & Data Integrity 6.5 Emergency Response Planning & AWIA Risk and Resilience 6.6 Facility Security, SCADA Cybersecurity & Vulnerability Assessment 6.7 Budgeting, Procurement, Inventory & Capital Planning 6.8 Supervision, Training, SOP Development & Resource Optimization

6.7 Budgeting, Procurement, Inventory & Capital Planning

Key Takeaways Explain This Topic AI

An operating budget funds recurring annual costs such as labor, chemicals, power, and supplies, while a capital budget funds long-lived assets and is normally financed rather than paid from annual revenue.

Chemical cost per million gallons equals dose in milligrams per liter times 8.34 times the unit price per pound, which is the calculation that converts a dose optimization into a budget number.

The Virginia Public Procurement Act requires competitive sealed bidding or competitive negotiation for most purchases above locally set thresholds, with sole source and emergency purchases documented in writing and posted.

A reorder point equals average usage during the lead time plus a safety stock, and critical spares are stocked on consequence of failure rather than on usage rate.

Full cost pricing sets rates to recover operations, maintenance, debt service, and a renewal and replacement reserve, so that the utility is not deferring asset renewal into an unfunded future.

Last updated: August 2026

Budgeting, Procurement, Inventory & Capital Planning

The ABC Water Treatment criteria list "prepare budgets," "determine costs and follow procurement procedures needed for maintenance, operation, and repairs," "track and maintain inventory (e.g., equipment, chemical, and general supplies)," and "operational and capital project implementation: project management, contract management, capital improvement planning." Virginia's regulations reinforce this by requiring at least four of the 18 CPE contact hours to be in utility management for Class 1 and Class 2 operators (18VAC160-30-200 B and 18VAC160-30-210 B).

1. Operating Budget Versus Capital Budget

  • Operating budget Capital budget
  • Funds Recurring annual costs Long-lived assets and major projects
  • Horizon One fiscal year 5 to 20 years (the CIP)
  • Paid from Annual rate revenue Bonds, loans, grants, reserves, capital recovery fees

Examples Salaries, chemicals, power, supplies, laboratory services, routine maintenance A new clarifier, a filter rehabilitation, a main replacement program, a SCADA upgrade

The line between them is set by a capitalization threshold (commonly $5,000 to $25,000) and a useful life criterion (typically more than one year). A pump rebuild is usually operating; a pump replacement is usually capital.

Where the money goes at a typical treatment plant

  • Category Typical share of operating budget
  • Personnel (wages, benefits, training) 40 to 60 percent
  • Energy (electricity, natural gas, fuel) 10 to 30 percent - higher at wastewater plants that nitrify
  • Chemicals 5 to 20 percent
  • Maintenance and repair (parts, contracts) 10 to 20 percent
  • Residuals and biosolids disposal 5 to 15 percent at a wastewater plant
  • Laboratory services 2 to 5 percent
  • Administration, insurance, regulatory fees 5 to 10 percent

The two categories an operator directly controls day to day are chemicals and energy , which is precisely why the ABC criteria pair "prepare budgets" with "optimize the use of energy and chemicals."

  • 2. Cost Arithmetic
  • Chemical cost per million gallons
  • $/MG = Dose (mg/L) x 8.34 x Unit price ($/lb)

At 32 mg/L of alum at $0.26/lb: 32 x 8.34 x 0.26 = $69.39 per MG . At 4.5 MGD that is $312/day, $114,000 per year . A jar-test-verified reduction to 27 mg/L saves 5 x 8.34 x 0.26 x 4.5 x 365 = $17,800 per year - a real, defensible number to put in a budget narrative.

  • Annual chemical quantity for budgeting
  • lb/yr = Dose (mg/L) x 8.34 x Average flow (MGD) x 365

At 32 mg/L and 4.5 MGD: 32 x 8.34 x 4.5 x 365 = 438,000 lb/yr , or 219 tons. That figure drives both the budget line and the bid quantity.

  • Energy unit cost
  • kWh per MG treated = Total kWh / MG produced

Benchmarks worth knowing: conventional surface water treatment typically runs 1,500 to 2,500 kWh per MG including high-service pumping, and conventional activated sludge wastewater treatment runs 1,500 to 3,000 kWh per MG , higher with nitrification. Tracking this ratio monthly - rather than tracking the bill - separates a rate increase from a real efficiency loss.

Demand charges are often 30 to 50 percent of an electric bill and are billed on the highest 15- or 30-minute peak in the month . Staggering pump and blower starts, avoiding simultaneous backwash and high-service peaks, and shifting discretionary loads off the peak window can cut the bill without cutting a single kilowatt-hour of consumption.

3. Procurement Under the Virginia Public Procurement Act

Virginia public bodies purchase under the Virginia Public Procurement Act (VPPA), Sect. 2.2-4300 et seq. of the Code of Virginia . Localities adopt their own policies within it, so exact dollar thresholds vary by locality - know your own.

The methods

Method Use

Small purchase procedures Below the locality's small purchase threshold; simplified, often requiring a documented number of informal quotes

Competitive sealed bidding (IFB) The default for goods and non-professional services ; award to the lowest responsive and responsible bidder

Competitive negotiation (RFP) For professional services (engineering, architecture, legal, accounting) and where factors other than price matter; award based on qualifications and negotiated terms

Sole source Only when there is only one source practicably available ; requires a written determination stating the basis, and public posting

Emergency purchase When an emergency exists; procure with such competition as is practicable under the circumstances, with a written determination and public posting

Cooperative procurement Purchasing from another public body's competitively awarded contract

Two rules that catch operators out:

"We have always bought this brand" is not a sole source. A sole source determination must show that no other product will practicably meet the need - not that the incumbent is familiar. Writing a specification around a single manufacturer's proprietary features has the same problem.

An emergency purchase must be a real emergency , documented at the time. A foreseeable failure that was deferred is not an emergency.

Ethics. The VPPA contains conflict-of-interest and gift provisions, and 18VAC160-30-330 independently prohibits an operator from conflicts of interest. Accepting anything of value from a chemical supplier or an equipment vendor whose products you specify or evaluate is a problem under both.

Writing a good specification

Describe performance, not a part number , wherever possible: capacity, head, efficiency at the duty point, materials of construction, applicable standards ( NSF/ANSI 61 and 372 for anything contacting potable water ), and warranty.

State the acceptance test. A pump specification with no witnessed performance test is a wish.

Specify chemical quality by standard - AWWA standards for treatment chemicals, with a required certificate of analysis and NSF/ANSI 60 certification.

Include delivery, unloading, and container requirements - this is where a specification protects the operator physically as well as financially.

  • 4. Inventory Control
  • What to stock, and why
  • Class Basis for stocking Examples
  • Consumables Usage rate and lead time Chemicals, lab reagents, filters, lubricants, PPE
  • Routine spares Usage rate Belts, seals, gaskets, bearings, common valves

Critical spares Consequence of failure , not usage rate The impeller for the only raw water pump, a spare PLC processor, a spare blower motor, the long-lead-time control valve

Insurance spares Extreme consequence plus extreme lead time A complete pump for a non-redundant service, a spare transformer

Critical spares are stocked precisely because their usage rate is near zero. A part used once a decade whose absence stops the plant for 16 weeks belongs on the shelf; a part used monthly whose absence stops nothing does not need a large stock.

  • Reorder arithmetic
  • Reorder point = (Average usage per day x Lead time in days) + Safety stock

A plant uses 480 lb/day of sodium hypochlorite equivalent, the supplier's lead time is 10 days, and the utility carries 5 days of safety stock:

Reorder point = (480 x 10) + (480 x 5) = 4,800 + 2,400 = 7,200 lb , which the operator converts to a tank level and marks on the gauge.

Chemical inventory has an expiry dimension that ordinary inventory does not. Sodium hypochlorite loses strength with time and temperature, so larger orders are not always cheaper - the discount can be smaller than the strength lost. Order smaller and more frequently, store cool and dark, rotate stock first in, first out , and verify strength on receipt.

Inventory discipline

Cycle counting - count a portion of the inventory continuously rather than shutting down for an annual count.

Minimum and maximum levels set for every stocked item, and reviewed annually against actual usage.

A single controlled storeroom with issue records. Parts scattered in five locations get bought three times.

Obsolete stock write-off - carrying spares for equipment removed a decade ago is a real cost in space and in confusion.

5. Capital Improvement Planning

A capital improvement plan (CIP) is a rolling multi-year list of projects with cost estimates, schedules, and funding sources. It is where asset management output becomes money.

How projects earn a place

Regulatory driver - a new standard, a consent order, a permit limit that current treatment cannot meet.

Condition and risk - assets at end of life ranked by criticality , meaning consequence of failure times likelihood of failure.

Capacity - growth, or a hydraulic bottleneck.

Efficiency - projects with a defensible payback, such as blower replacement, VFDs, or cogeneration.

Resilience - flood protection, redundancy, standby power, interconnections.

Funding sources in Virginia

Rates and a renewal and replacement reserve - the only sustainable base.

Revenue bonds - repaid from utility revenue; the standard for large projects.

The Virginia Drinking Water State Revolving Fund (DWSRF) , administered by VDH, and the Virginia Clean Water Revolving Loan Fund (VCWRLF) , administered by the Virginia Resources Authority with DEQ - subsidized loans, with principal forgiveness available to disadvantaged systems.

USDA Rural Development water and waste disposal loans and grants for small rural systems.

Virginia Community Development Block Grant funds.

Capital recovery / availability fees on new connections, so growth pays for growth.

Full cost pricing

Rates should recover:

  • Operations and maintenance ;
  • Debt service ;
  • A renewal and replacement reserve sized against the depreciation of the asset base; and

An operating reserve for cash flow and emergencies.

A utility that funds only the first two is consuming its asset base and shifting the cost to a future rate payer. The most common symptom is a distribution system with a break rate that rises every year while the replacement rate stays flat.

What the operator contributes to this conversation is the thing nobody else in the room has: the failure history, the condition data, the run hours, the chemical and energy trend, and the specific consequences of deferral. A budget request that says "the raw water pump is old" loses. One that says "this pump has failed twice in 18 months, it is non-redundant, its replacement lead time is 22 weeks, and its failure stops all production" wins.