13.4 Permits, Inspections, Class A & Class B Work, and Plan Review

Washington Journeyman Electrician 01 General Journey Level

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Exam Structure & Open-Book Code Navigation

1.1 Washington 01 Electrician Licensing Pathway & Exam Structure 1.2 National Electrical Code Architecture & Fast Lookup Strategies 1.3 Open-Book Exam Rules, Reference Preparation & Pacing

2 Chapter 2: Electrical Theory & Fundamental Math

2.1 Ohm's Law, Joule's Law & Circuit Analysis 2.2 AC Fundamentals, Reactance & Power Factor 2.3 Three-Phase Power Calculations: Wye & Delta Configurations

3 Chapter 3: General Installation Requirements & Conductor Sizing

3.1 Installation Requirements & Working Space Clearances 3.2 Conductor Sizing & Table 310.16 Ampacity 3.3 Temperature Correction Factors & Raceway Derating

4 Chapter 4: Wiring Methods, Raceways & Enclosure Calculations

4.1 Common Wiring Methods & Cable Assemblies 4.2 Conduit & Tubing Installation and Fill Calculations 4.3 Box Fill & Pull Box Sizing Calculations 4.4 Flexible Raceways, ENT, Wireways, Cable Trays, Specialty Cables & Plenum Rules

5 Chapter 5: Branch Circuits, Feeders & Overcurrent Protection

5.1 Branch Circuit Ratings, Receptacle Placement & Lighting 5.2 GFCI, AFCI & Special Protection Requirements 5.3 Overcurrent Protection & Feeder Tap Rules 5.4 Grounded Conductors, Feeders, Outside Circuits & Surge Protection (Articles 200, 215, 225, 280, 285) 5.5 Overcurrent Device Location, Fuses, Circuit Breakers & Transformer Secondary Conductors (Article 240)

6 Chapter 6: Grounding & Bonding (Article 250)

6.1 Grounding vs. Bonding: Core Principles & Definitions 6.2 Grounding Electrode Systems & GEC Sizing 6.3 Main Bonding Jumpers & Equipment Grounding Conductor Sizing

7 Chapter 7: Services, Feeders & Load Calculations

7.1 Electrical Services & Service Equipment (Article 230) 7.2 Dwelling Unit Load Calculations: Standard & Optional Methods 7.3 Commercial Load Calculations & Voltage Drop

8 Chapter 8: Equipment for General Use & Equipment Over 1000 Volts (Articles 400-490)

8.1 Flexible Cords, Fixture Wires, Switches, Receptacles & Panelboards (Articles 400-408) 8.2 Luminaires, Appliances, Space Heating & Other Equipment (Articles 410-427, 455-480) 8.3 Equipment Over 1000 Volts (Article 490 and Related Rules)

9 Chapter 9: Motors, HVAC Equipment, Generators & Transformers (Articles 430-450)

9.1 Motor Branch Circuit Conductor Sizing & Overloads 9.2 Motor Short-Circuit Protection & Disconnecting Means 9.3 Transformers, Generators & Hermetic HVAC Equipment

10 Chapter 10: Hazardous Locations & Special Occupancies (Articles 500-590)

10.1 Hazardous (Classified) Locations (Articles 500–516) 10.2 Health Care Facilities, Places of Assembly & Theaters (Articles 517-540) 10.3 Agricultural Buildings, Mobile Homes, RV Parks, Marinas & Temporary Installations (Articles 545-590)

11 Chapter 11: Special Equipment (Articles 600-695)

11.1 Signs, Cranes, Elevators, EV Charging, Welders, IT Rooms & Industrial Machinery (Articles 600-670) 11.2 Swimming Pools, Spas, Hot Tubs & Fountains (Article 680) 11.3 Solar Photovoltaic Systems, Fuel Cells, Wind & Fire Pumps (Articles 690-695)

12 Chapter 12: Emergency Systems, Special Conditions & Communications (Articles 700-830)

12.1 Emergency, Legally Required & Optional Standby Systems (Articles 700-702) 12.2 Interconnected Power Sources, Energy Storage, Power-Limited Circuits, Fire Alarm & Communications (Articles 705-830)

13 Chapter 13: Washington Electrical Laws & Administrative Code (RCW 19.28 & WAC 296-46B)

13.1 Certificates of Competency, Specialty Scopes & Renewal 13.2 Trainees, Supervision Ratios, Apprenticeship & Qualifying Experience 13.3 Electrical Contractors, Administrators, Bonds & Exemptions 13.4 Permits, Inspections, Class A & Class B Work, and Plan Review 13.5 Civil Penalties, Appeals, Exam Rules & Certificate Discipline 13.6 WAC 296-46B Amendments: Adoption, General Rules, Services, Grounding & Wiring (NEC Chapters 1-4) 13.7 WAC 296-46B Amendments: Special Occupancies, Special Equipment, Emergency Systems & Communications (NEC Chapters 5-8)

13.4 Permits, Inspections, Class A & Class B Work, and Plan Review

Key Takeaways Explain This Topic AI

A work permit, or its number, must be posted at the job site or on or next to the supplying service or feeder panel before electrical work begins, and stay posted until inspection is complete (WAC 296-46B-901(5)).

Inspection must be requested within three working days after an installation is complete, or one working day after any part of it is energized, whichever comes first (WAC 296-46B-901(9)).

Installations that do not comply must be corrected within 15 calendar days of L&I's notice (RCW 19.28.101(3); WAC 296-46B-901(15)).

Class B labels must be validated online and posted before work begins; an entity may use no more than two labels per week per job site, and the work must be finished within 15 days (WAC 296-46B-908).

Class B work is not allowed in classified (hazardous) locations, Article 517 or 680 areas, plan review projects, or fire alarm, nurse call, lighting control, industrial automation, or energy management systems (WAC 296-46B-908(11)).

Last updated: September 2026

Why this section matters

Permit and inspection questions are among the most practical items on the WA Codes section. The rules are in Part C of WAC 296-46B. Tab -900 (plan review), -901 (permits, inspections, corrections), and -908 (Class B).

When a permit is required (WAC 296-46B-901(7))

An electrical work permit is required to install, alter, or maintain all electrical systems or equipment, except:

travel trailers ;

Class A basic electrical work , which is like-in-kind replacement of items such as lamps; a single set of fuses; a single battery smaller than 150 amp-hours; contactors, relays, timers, starters, or circuit boards; one household appliance; circuit breakers; single-family residential luminaires and line-voltage smoke or CO alarms; up to five snap switches, dimmers, receptacles, thermostats, heating elements, or ballasts/drivers; and one motor of 10 hp or less. Class A also covers gate induction loops, heat cable repair, embedding listed heat mats, and disconnecting circuits so equipment can be removed;

certain exempt low-voltage systems : thermocouple circuits; residential garage door and built-in vacuum circuits; and underground sprinkler, landscape lighting, and pet-fence antennas powered by listed Class 2 supplies, with conditions.

Telecommunications: a permit is required for projects of more than 10 outlets , for all backbone work, and for work that penetrates fire barriers or passes through hazardous locations. Telecommunications work inside individual dwelling units needs no permit (WAC 296-46B-901(8)).

Buying and posting the permit

Rule WAC 296-46B-901

No inspection, energizing, or service connection without a valid permit showing the facility type, scope, and location; the address visible from the road; and driving directions (1)

A permit covers one job site address (except annual permits and two-family dwellings) (2)

Each entity furnishes a permit for its own work; a new entity can take over the original permit only with the chief electrical inspector's written approval (3)

Post the permit at the job site, or post the permit number on or next to the service or feeder panel supplying the work, before beginning any electrical work and until inspection is complete (except Class B) (5)

Emergency like-in-kind repairs by an owner: the permit must be obtained no later than the next business day after work begins (5)(a)

  • Permits expire one year after purchase; the first $25 of each purchase is a nonrefundable application fee (11)
  • Inspections

Request timing: no later than three working days after the installation is complete, or one working day after any part is energized , whichever comes first (WAC 296-46B-901(9)(a)).

After-hours, weekend, or short temporary jobs (energized less than 48 hours): contact the inspection supervisor at least three working days ahead. Portal-to-portal fees apply.

No inspection until all fees are paid (WAC 296-46B-901(10)).

Access at inspection: wiring must be accessible for visual inspection. The only exception is not more than 8 feet of service-entrance conduit in the foundation of a one- or two-family dwelling or residential outbuilding (WAC 296-46B-010(4)).

Rough-in cover inspection: all required equipment grounding conductors in concealed cable or flexible conduit must be installed and made up (WAC 296-46B-010(5)). Framing, plumbing, and ducting must be complete in the area. Before an exterior wall is covered, either the building inspector has passed the shear-panel nailing, or wiring and boxes are at least 2-1/2 inches from the exterior face of the framing, or they are protected by 1/16-inch steel plates (WAC 296-46B-010(6)).

Open trenches: request the inspection in writing at least two working days ahead (WAC 296-46B-010(20)).

Covering or concealing work before inspection is a civil infraction: $250, then $1,000, then $2,000 (WAC 296-46B-915(9)).

Corrections

When an installation doesn't comply, the owner or operator is notified and must make the corrections within 15 days , or a longer reasonable time granted on request (RCW 19.28.101(3)). WAC 296-46B-901(15) says 15 calendar days and posts correction notices electronically with the permit's inspection results. Missing the deadline costs $250, then $1,000, then $2,000 (WAC 296-46B-915(10)).

Class B random-inspection labels (WAC 296-46B-908)

Class B labels let qualified entities do small jobs without a full permit. The work is inspected at random.

Who may use them: licensed electrical or telecommunications contractors, and health care, commercial, or industrial facilities using certified electrician employees with the chief electrical inspector's written permission.

Rules:

The label must be validated in L&I's online Class B system and the label or number posted before work begins , at the main service or feeder location or on the equipment.

Labels are sold in blocks and are nonrefundable and nontransferable.

A separate label is needed for each type of work item. No more than two labels per week per job site .

Work must be finished within 15 days of validation. In a one- or two-family residence, a label stays valid 120 days if the purchaser does all the work.

Inspections are random. If an inspection finds corrections, a progress inspection fee is charged.

Class B work includes (WAC 296-46B-908(10)):

  • Item Limits
  • Extension of one branch circuit 120 V, 20 A; no more than two outlets; no cover inspection needed
  • Like-in-kind replacement of a motor Larger than 10 hp (10 hp or smaller is Class A)

Like-in-kind furnace replacement Electric, gas, or oil furnace not over 240 V and 100 A on an existing branch circuit, with its Class 2 control wiring

Room heater, AC unit, heat pump, or refrigeration unit Not over 240 V and 40 A minimum circuit ampacity, on an existing branch circuit

  • GFCI/AFCI receptacle upgrades Up to 10 receptacles
  • Switches to dimmers or occupancy sensors Up to 10

Like-in-kind luminaires, paddle fans, switches, receptacles, and similar Up to 20; luminaires not over 277 V and 20 A

Low-voltage work Up to 20 devices or 5,000 square feet for thermostat, security, intercom, sound, or access control; not fire alarm, nurse call, lighting control, automation, or energy management

  • Single electric sign On an existing 120 V, 20 A branch circuit
  • EV output cable Like-in-kind replacement on fixed EVSE

Class B is never allowed in Class I, II, III, or Zone locations; in areas covered by NEC 517 or 680; on work that needs plan review; or on fire alarm, nurse call, lighting control, industrial automation or control, or energy management systems (WAC 296-46B-908(11)).

Electrical plan review (WAC 296-46B-900)

Required for new or altered electrical projects in educational, institutional, and health or personal care occupancies as defined in the WAC, with limited exceptions (low-voltage systems, lighting-only or HVAC retrofits with no load increase, small modifications at or below 400 A and 250 V, and similar).

Plans must be submitted and accepted before work begins. L&I gives a preliminary review within seven business days . No inspection proceeds on a rejected plan.

Plans for educational facilities, hospitals, and nursing homes must be prepared by or under a Washington-registered engineer and stamped.

Outside plan review, a nondwelling service or feeder larger than 400 A or over 600 V needs a signed one-line diagram on site before the first inspection can be approved (WAC 296-46B-215(2)).