Study guide

1.3 General Regulations: Prohibited Fittings, Pipe Protection, Nail Plates, Sleeves, & Trenching (UPC Chapter 3)

Washington Journeyman Plumber Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Administration, Licensing, & General Regulations

1.1 Washington Plumber Certification Law: RCW 18.106, WAC 296-400A, Trainees, & Supervision 1.2 Permits, Inspections, Tests, & Disinfection (UPC Chapter 1, 609, 712) 1.3 General Regulations: Prohibited Fittings, Pipe Protection, Nail Plates, Sleeves, & Trenching (UPC Chapter 3) 1.4 Hangers, Supports, Rod Sizes, Dissimilar Metals, & Expansion (UPC 313, Table 313.3)

2 Chapter 2: Plumbing Fixtures, Fittings, & Clearances

2.1 Fixture Setting, Clearances, Closet Flanges, & Water Closets (UPC 402, 411, 413; WA 402.5) 2.2 Showers, Shower Pans, Bathtubs, Lavatories, Bidets, & Scald Limits (UPC 407–410; WA 408) 2.3 Urinals, Floor Drains, Floor Sinks, Sinks, Dishwashers, Disposers, & Special Fixtures (UPC 412–421) 2.4 Minimum Fixture Counts in Washington: IBC Table 2902.1, Not UPC Table 422.1

3 Chapter 3: Water Heaters & Storage Tanks

3.1 Water Heater Permits, Sizing (WA Table 501.1), Bedroom and Bathroom Locations, & Safety Devices 3.2 Temperature and Pressure Relief Valves & Discharge Piping (UPC 504.6, 608; WA 608.3.1 and 608.5) 3.3 Water Heater Installation Details: Garages, Pans, Supports, Attic and Under-Floor Access, & Washington's Mechanical Code Deletions 3.4 Seismic Strapping, Thermal Expansion Tanks, Pressure Regulators, & Temperature Controls (WA 507.2, 608.2, 608.3)

4 Chapter 4: Water Supply and Distribution Systems

4.1 Water Piping Materials, Joints, Lead Limits, Under-Slab Rules, & Velocity (UPC 604, 605, 609, 610.12) 4.2 Water Supply Fixture Units & the Sizing Tables (UPC 610.3, 610.4, 610.8, 610.10) 4.3 Water Pressure Limits, Booster Pumps, Potable Water Tanks, & Water Hammer (UPC 607–609) 4.4 Water Valves, Shutoffs, Manifolds, & Hot Water Distribution (UPC 606, 609.11; WA 210.0 and 609.11)

5 Chapter 5: Backflow Prevention & Cross-Connection Control

5.1 Backflow Principles: Backsiphonage, Backpressure, & Degree of Hazard (UPC 602–603; WAC 246-290-490) 5.2 Backflow Assemblies and Devices: RP, DC, PVB, SVB, AVB, & Installation Rules (UPC 603.3, 603.4, Table 603.2) 5.3 Air Gaps, Critical Level, & Specific Backflow Applications (UPC Table 603.3.1, 603.5) 5.4 Backflow Testing, Certified Testers, & Washington's Cross-Connection Program (WA 603.4.2; WAC 246-290-490, 246-292)

6 Chapter 6: Sanitary Drainage Systems & Sizing

6.1 DWV Materials, Joints, & Changes in Direction (UPC 701, 704–706; WA 701.2) 6.2 Drainage Fixture Units, Trap Sizes, & Flow Conversions (UPC Table 702.1, 702.2, 702.3) 6.3 Sizing Drainage Piping with Table 703.2 (Vertical, Horizontal, Water Closet Limits, & WA Note 4) 6.4 Building Drains, Grade, Gravity Drainage, Backwater Valves, & Washington's Deletion of Building Sewer Rules

7 Chapter 7: Cleanouts, Sumps and Ejectors, Indirect Wastes, & Interceptors

7.1 Cleanouts: Location, Spacing, Size, and Clearance (UPC 707 as Amended by Washington) 7.2 Sumps, Sewage Ejectors, Grinder Pumps, & Macerating Systems (UPC 710) 7.3 Indirect Wastes, Air Gaps and Air Breaks, Receptors, Standpipes, & Condensate (UPC Chapter 8) 7.4 Interceptors and Separators: Grease, Sand, Oil, Laundry, & Bottling (UPC 1009–1017)

8 Chapter 8: Vents and Venting Fundamentals

8.1 Venting Fundamentals: Trap Seal Protection, Vent Sizing, the Half-Drain Rule, & Aggregate Venting (UPC 901–904) 8.2 Vent Grades and Connections, Vent Stacks, Relief and Yoke Vents, & Suds Relief (UPC 905, 907, 711) 8.3 Wet Venting and Circuit Venting (UPC 908, 911; WA 908.2.4 and 911.1) 8.4 Island Fixture Venting, Combination Waste and Vent Systems, & Engineered Vent Systems (UPC 909, 910, 912)

9 Chapter 9: Vent Terminations, Traps, & Priming

9.1 Vent Terminations: Roof Height, Clearances, Used Roofs, Outdoor Vents, & Frost Closure (UPC 906) 9.2 Traps, Trap Arms, Table 1002.2 Distances, & Prohibited Traps (UPC 1001–1004) 9.3 How Trap Seals Are Lost & How the Code Protects Them: Venting, Seal Depth, and Trap Seal Primers (UPC 901.3, 1005, 1007)

10 Chapter 10: Alternate Water, Rainwater Catchment, Definitions, & Referenced Standards

10.1 Alternate Water Sources: Reclaimed, Gray, and On-Site Treated Water (UPC Chapter 15 as Amended by Washington) 10.2 Nonpotable Rainwater Catchment Systems (UPC Chapter 16 as Amended by Washington) 10.3 Key UPC Definitions and Referenced Standards (UPC Chapters 2 and 17; WA Definition Amendments)

11 Chapter 11: Part 2 — Waste & Vent Isometric Drawings & Plan Analysis

11.1 Part 2 Explained: Reading the Waste and Vent Drawing 11.2 Part 2 Worked Example: Accumulating DFU and Sizing Every Drain Segment 11.3 Part 2 Worked Example: Sizing Individual, Branch, and Main Vents and Checking Aggregate Venting 11.4 Spotting Code Violations on Waste and Vent Drawings: A Checklist with Code Citations

12 Chapter 12: Part 3 — Water Supply Isometric Drawings & Pipe Sizing

12.1 Part 3 Explained: Reading the Water Sizing Drawing and Gathering the 610.7 Data 12.2 Part 3 Worked Example: Accumulating Water Supply Fixture Units, Cold and Hot 12.3 Part 3: Available Pressure, Elevation, Regulators, Device Losses, and the Length Column 12.4 Part 3 Worked Example: Sizing the Meter, Building Supply, and Every Branch with Table 610.4

13 Chapter 13: Washington Amendments Review, Plumbing Math, & Water Service Special Topics

13.1 Washington's Amendments to the 2015 UPC (WAC 51-56): A Consolidated Review 13.2 Plumbing Math for the Exam: Offsets, Rolling Offsets, Grade, Areas, Volumes, and Pressure 13.3 Water Service Details, Treatment Units, Softeners, & Residential Sprinklers (UPC 604, 609, 611, 612; WA Amendments)

14 Chapter 14: Comprehensive Exam Preparation & Test-Taking Strategy

14.1 The PSI Exam Day: Structure, Fees, Retakes, Rules, and Pacing 14.2 Using the Provided Tables Fast (702.1, 610.3, 610.4, 610.10) and Writing the Missing Ones from Memory 14.3 High-Yield Number Review, Classic Traps, and a Final Readiness Checklist

1.3 General Regulations: Prohibited Fittings, Pipe Protection, Nail Plates, Sleeves, & Trenching (UPC Chapter 3)

Key Takeaways Explain This Topic AI

UPC 312.9 requires 18-gauge steel nail plates where plastic or copper piping is within 1 inch of the framing face, extending 1-1/2 inches beyond the pipe.

UPC 310.1 prohibits double hub fittings, single or double tee branches, side inlet quarter bends, running threads, bands, and saddles as drainage fittings.

UPC 314.4 requires backfill in thin layers of clean earth to 12 inches above the pipe before machines complete the backfill.

Thermoplastic sewer pipe needs at least 4 inches of granular bedding and side compaction in 6-inch layers to 12 inches over the pipe (UPC 314.4.1).

Tests of 10 psi or less require gauges graduated in 0.10 psi or finer, and gauge range may not exceed twice the test pressure (UPC 318).

Last updated: September 2026

Why Chapter 3 Shows Up Everywhere

Chapter 3 of the UPC holds the "general regulations." These rules apply in every other chapter: approved materials and markings, prohibited fittings, pipe protection, hangers, trenching, and test gauges. Part 1 of the Washington exam draws on UPC Chapters 1 through 10, so expect short, direct questions here. Typical examples ask which fitting is prohibited, what gauge a nail plate must be, or how deep backfill must go.

Materials, Marking, and Workmanship

301.2 Minimum standards: Pipe, fittings, traps, fixtures, and devices must be listed or labeled by a listing agency and meet the referenced standards. Plastic pipe and fittings other than gas components must comply with NSF 14.

301.2.1 Marking: Each length of pipe and each fitting must carry the manufacturer's mark, plus the weight and quality where the standard requires it.

301.3 Alternates: Equivalent systems, methods, or devices may be approved by the AHJ with technical documentation. Washington's amendment adds that a disapproval must be explained in writing .

309 Workmanship: It is unlawful to hide cracks or holes with welding, solder, paint, wax, tar, or sealants (309.2). Burred ends must be reamed to full bore (309.3).

Prohibited Fittings and Practices (UPC 310)

Rule What is prohibited

310.1 Using a double hub fitting, single or double tee branch, single or double tapped tee branch, side inlet quarter bend, running thread, band, or saddle as a drainage fitting . Exception: a double hub sanitary tapped tee may be used on a vertical line as a fixture connection.

  • 310.2 Drilling and tapping drainage or vent piping to make a connection; threading cast-iron soil pipe
  • 310.3 Connecting a waste to a closet bend or water closet stub

310.4 Using a vent as a soil or waste pipe, or the reverse, except as allowed by 908–911. Single-stack systems with unvented branch lines are prohibited.

310.5 Any fitting or method that obstructs flow beyond normal friction. Enlarging a 3-inch closet bend to 4 inches is not an obstruction.

310.6 Dissimilar-metal connections in concealed locations; except for necessary valves, they must be exposed or accessible

315.2 Any joint with an enlargement, chamber, recess, ledge, or shoulder that obstructs the drain

Section 316.1 requires proper increasers or reducers between pipe sizes. A copper alloy or cast-iron cleanout body may not be used as a reducer or adapter from cast-iron drainage pipe to IPS pipe.

Independent Systems (UPC 311)

Each new building must have a drainage system separate and independent from any other building, with its own sewer connection where available. The exception: when one building stands behind another on an interior lot and no private sewer can reach the rear building, the front building's drain may be extended to it.

Protection of Piping (UPC 312)

312.2: Plumbing piping may not be directly embedded in concrete or masonry . Provide for expansion, contraction, and settlement.

312.3: Drainage piping made of materials not approved for use in a building may not be installed within 2 feet of the building or less than 1 foot below the ground surface.

312.6 Freezing (Washington amendment): Water, soil, or waste pipe outside a building, in attics or crawl spaces, or in exterior walls must be protected from freezing where necessary. Washington adds that all hot and cold water pipes outside the conditioned space must be insulated . The 2015-edition amendment set a minimum of R-3 .

312.7 (Washington amendment): Penetrations of fire-resistance-rated assemblies are protected as the building code requires. Washington does not adopt UPC Chapter 14, Firestop Protection.

312.9 Steel nail plates: Plastic, copper, or copper-alloy piping that passes through framing within 1 inch of the exposed framing face needs a steel nail plate at least No. 18 gauge (0.0478 inch) . The plate must extend at least 1-1/2 inches beyond the outside diameter of the pipe.

312.10 Sleeves: Piping through concrete or masonry walls and concrete floors needs sleeves, except where the opening is drilled or bored. The pipe may not carry building loads. The annular space in exterior walls must be sealed watertight.

312.11 Structural members: A member weakened by cutting or notching must be reinforced, repaired, or replaced as the building code requires . Boring and notching limits come from the building code, not the UPC.

312.12 Rodentproofing: Strainer openings on drain inlets may not exceed 1/2 inch . Pipe openings through walls and floors get metal collars . Tub waste openings into crawl spaces at or below the first floor get metal collars or screen with no opening over 1/2 inch.

312.13 and 312.14 Sunlight: ABS and PVC may not be exposed to direct sunlight unless protected with water-based synthetic latex paint. PVC may also be wrapped with tape at least 0.04 inch thick.

Trenching, Excavation, and Backfill (UPC 314)

314.1: A trench deeper than a footing and parallel to it must stay outside a 45-degree line from the bottom exterior edge of the footing.

314.2: Tunnels need 2 feet of clear height above the pipe and are limited to half the trench depth, with a maximum length of 8 feet . A drive pipe must be at least one size larger than the pipe being laid.

314.3: Excavations for building drainage inside the walls must be open trench and stay open until the piping is inspected, tested, and accepted.

314.4: Backfill in thin layers to 12 inches above the top of the pipe with clean earth free of stones, boulders, cinders, frozen earth, or debris. After that, machines may finish the backfill.

314.4.1 Thermoplastic sewer pipe: Make the trench 1.25 × OD + 12 inches or OD + 16 inches wide. Bed the pipe in at least 4 inches of granular fill . Compact the sides in 6-inch layers to at least 12 inches above the pipe, at 85% standard proctor density or better.

Section 313.5 also requires underground piping to be laid on a firm bed for its entire length .

Test Gauges (UPC 318)

  • Test pressure Gauge graduation required
  • 10 psi or less (for example, the 5 psi DWV air test) 0.10 psi or finer
  • Over 10 psi to 100 psi 1 psi or finer
  • Over 100 psi 2% of the test pressure or finer

The gauge's range may not exceed twice the test pressure (318.5).