Study guide
10.3 Key UPC Definitions and Referenced Standards (UPC Chapters 2 and 17; WA Definition Amendments)
Washington Journeyman Plumber Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Administration, Licensing, & General Regulations
1.1 Washington Plumber Certification Law: RCW 18.106, WAC 296-400A, Trainees, & Supervision 1.2 Permits, Inspections, Tests, & Disinfection (UPC Chapter 1, 609, 712) 1.3 General Regulations: Prohibited Fittings, Pipe Protection, Nail Plates, Sleeves, & Trenching (UPC Chapter 3) 1.4 Hangers, Supports, Rod Sizes, Dissimilar Metals, & Expansion (UPC 313, Table 313.3)
2 Chapter 2: Plumbing Fixtures, Fittings, & Clearances
2.1 Fixture Setting, Clearances, Closet Flanges, & Water Closets (UPC 402, 411, 413; WA 402.5) 2.2 Showers, Shower Pans, Bathtubs, Lavatories, Bidets, & Scald Limits (UPC 407–410; WA 408) 2.3 Urinals, Floor Drains, Floor Sinks, Sinks, Dishwashers, Disposers, & Special Fixtures (UPC 412–421) 2.4 Minimum Fixture Counts in Washington: IBC Table 2902.1, Not UPC Table 422.1
3 Chapter 3: Water Heaters & Storage Tanks
3.1 Water Heater Permits, Sizing (WA Table 501.1), Bedroom and Bathroom Locations, & Safety Devices 3.2 Temperature and Pressure Relief Valves & Discharge Piping (UPC 504.6, 608; WA 608.3.1 and 608.5) 3.3 Water Heater Installation Details: Garages, Pans, Supports, Attic and Under-Floor Access, & Washington's Mechanical Code Deletions 3.4 Seismic Strapping, Thermal Expansion Tanks, Pressure Regulators, & Temperature Controls (WA 507.2, 608.2, 608.3)
4 Chapter 4: Water Supply and Distribution Systems
4.1 Water Piping Materials, Joints, Lead Limits, Under-Slab Rules, & Velocity (UPC 604, 605, 609, 610.12) 4.2 Water Supply Fixture Units & the Sizing Tables (UPC 610.3, 610.4, 610.8, 610.10) 4.3 Water Pressure Limits, Booster Pumps, Potable Water Tanks, & Water Hammer (UPC 607–609) 4.4 Water Valves, Shutoffs, Manifolds, & Hot Water Distribution (UPC 606, 609.11; WA 210.0 and 609.11)
5 Chapter 5: Backflow Prevention & Cross-Connection Control
5.1 Backflow Principles: Backsiphonage, Backpressure, & Degree of Hazard (UPC 602–603; WAC 246-290-490) 5.2 Backflow Assemblies and Devices: RP, DC, PVB, SVB, AVB, & Installation Rules (UPC 603.3, 603.4, Table 603.2) 5.3 Air Gaps, Critical Level, & Specific Backflow Applications (UPC Table 603.3.1, 603.5) 5.4 Backflow Testing, Certified Testers, & Washington's Cross-Connection Program (WA 603.4.2; WAC 246-290-490, 246-292)
6 Chapter 6: Sanitary Drainage Systems & Sizing
6.1 DWV Materials, Joints, & Changes in Direction (UPC 701, 704–706; WA 701.2) 6.2 Drainage Fixture Units, Trap Sizes, & Flow Conversions (UPC Table 702.1, 702.2, 702.3) 6.3 Sizing Drainage Piping with Table 703.2 (Vertical, Horizontal, Water Closet Limits, & WA Note 4) 6.4 Building Drains, Grade, Gravity Drainage, Backwater Valves, & Washington's Deletion of Building Sewer Rules
7 Chapter 7: Cleanouts, Sumps and Ejectors, Indirect Wastes, & Interceptors
7.1 Cleanouts: Location, Spacing, Size, and Clearance (UPC 707 as Amended by Washington) 7.2 Sumps, Sewage Ejectors, Grinder Pumps, & Macerating Systems (UPC 710) 7.3 Indirect Wastes, Air Gaps and Air Breaks, Receptors, Standpipes, & Condensate (UPC Chapter 8) 7.4 Interceptors and Separators: Grease, Sand, Oil, Laundry, & Bottling (UPC 1009–1017)
8 Chapter 8: Vents and Venting Fundamentals
8.1 Venting Fundamentals: Trap Seal Protection, Vent Sizing, the Half-Drain Rule, & Aggregate Venting (UPC 901–904) 8.2 Vent Grades and Connections, Vent Stacks, Relief and Yoke Vents, & Suds Relief (UPC 905, 907, 711) 8.3 Wet Venting and Circuit Venting (UPC 908, 911; WA 908.2.4 and 911.1) 8.4 Island Fixture Venting, Combination Waste and Vent Systems, & Engineered Vent Systems (UPC 909, 910, 912)
9 Chapter 9: Vent Terminations, Traps, & Priming
9.1 Vent Terminations: Roof Height, Clearances, Used Roofs, Outdoor Vents, & Frost Closure (UPC 906) 9.2 Traps, Trap Arms, Table 1002.2 Distances, & Prohibited Traps (UPC 1001–1004) 9.3 How Trap Seals Are Lost & How the Code Protects Them: Venting, Seal Depth, and Trap Seal Primers (UPC 901.3, 1005, 1007)
10 Chapter 10: Alternate Water, Rainwater Catchment, Definitions, & Referenced Standards
10.1 Alternate Water Sources: Reclaimed, Gray, and On-Site Treated Water (UPC Chapter 15 as Amended by Washington) 10.2 Nonpotable Rainwater Catchment Systems (UPC Chapter 16 as Amended by Washington) 10.3 Key UPC Definitions and Referenced Standards (UPC Chapters 2 and 17; WA Definition Amendments)
11 Chapter 11: Part 2 — Waste & Vent Isometric Drawings & Plan Analysis
11.1 Part 2 Explained: Reading the Waste and Vent Drawing 11.2 Part 2 Worked Example: Accumulating DFU and Sizing Every Drain Segment 11.3 Part 2 Worked Example: Sizing Individual, Branch, and Main Vents and Checking Aggregate Venting 11.4 Spotting Code Violations on Waste and Vent Drawings: A Checklist with Code Citations
12 Chapter 12: Part 3 — Water Supply Isometric Drawings & Pipe Sizing
12.1 Part 3 Explained: Reading the Water Sizing Drawing and Gathering the 610.7 Data 12.2 Part 3 Worked Example: Accumulating Water Supply Fixture Units, Cold and Hot 12.3 Part 3: Available Pressure, Elevation, Regulators, Device Losses, and the Length Column 12.4 Part 3 Worked Example: Sizing the Meter, Building Supply, and Every Branch with Table 610.4
13 Chapter 13: Washington Amendments Review, Plumbing Math, & Water Service Special Topics
13.1 Washington's Amendments to the 2015 UPC (WAC 51-56): A Consolidated Review 13.2 Plumbing Math for the Exam: Offsets, Rolling Offsets, Grade, Areas, Volumes, and Pressure 13.3 Water Service Details, Treatment Units, Softeners, & Residential Sprinklers (UPC 604, 609, 611, 612; WA Amendments)
14 Chapter 14: Comprehensive Exam Preparation & Test-Taking Strategy
14.1 The PSI Exam Day: Structure, Fees, Retakes, Rules, and Pacing 14.2 Using the Provided Tables Fast (702.1, 610.3, 610.4, 610.10) and Writing the Missing Ones from Memory 14.3 High-Yield Number Review, Classic Traps, and a Final Readiness Checklist
10.3 Key UPC Definitions and Referenced Standards (UPC Chapters 2 and 17; WA Definition Amendments)
Key Takeaways Explain This Topic AI
The UPC defines a trap arm as the portion of a fixture drain between the trap and the vent, and the trap seal as the vertical distance between the crown weir and the top dip of the trap.
Developed length is measured along the centerline of the pipe and fittings (UPC Chapter 2).
A stack vent is the extension of a soil or waste stack above its highest horizontal drain; a vent stack is a separate vertical vent that circulates air to and from the drainage system.
Washington defines hot water as water at 100°F or more and includes water heaters and medical gas systems within the property lines in the plumbing system definition (WA 210.0, 218.0).
Standards in UPC Table 1701.1 are mandatory where required by code sections; for example ASSE 1013 covers RP assemblies and ASSE 1016 covers shower and tub-shower valves.
Last updated: September 2026
Why Definitions Matter
Code language is precise. "Building drain" and "building sewer" are different pipes. That difference matters in Washington, where building sewer rules are deleted (Section 6.4). Likewise, a "vent stack" and a "stack vent" are different pipes. Many Part 1 questions are answered by knowing the definition.
Drainage and Vent Definitions (UPC Chapter 2)
Term Definition in brief
Building drain The lowest drainage piping inside the building walls, carrying discharge to the building sewer, which begins 2 feet outside the wall
Building sewer Horizontal piping from the end of the building drain to a public or private sewer or other point of disposal
Drainage system All piping within public or private premises conveying sewage, storm water, or liquid wastes to a legal point of disposal; not the public sewer or treatment plant
- Fixture drain The drain from a fixture's trap to its junction with any other drain
- Trap arm The portion of a fixture drain between the trap and the vent
Trap A fitting or device that provides a liquid seal against the back passage of air, without materially affecting flow
Trap seal The vertical distance between the crown weir and the top dip of the trap
Crown weir (trap weir) The lowest point in the cross-section of the horizontal waterway at the exit of the trap
Horizontal branch A drain extending laterally from a stack or building drain, receiving one or more fixture drains
- Stack The vertical main of soil, waste, or vent piping extending through one or more stories
- Soil pipe Conveys water closet, urinal, clinical sink, or similar discharge
- Waste pipe Conveys only liquid waste, free of fecal matter
Branch interval A length of stack corresponding generally to a story height, but not less than 8 feet , within which one floor's branches connect
- Developed length Length measured along the centerline of pipe and fittings
- Grade The slope or fall of a pipe, usually expressed as a fraction of an inch or a percentage per foot
- Offset A combination of elbows or bends that moves one pipe section out of line but parallel to the other
- Stack vent The extension of a soil or waste stack above the highest horizontal drain connected to it
Vent stack A vertical vent pipe installed primarily to circulate air to and from any part of the drainage system
- Continuous vent A vertical vent that continues the drain it connects to
- Individual vent Vents one fixture trap, connecting above the fixture or terminating outdoors
- Relief vent Mainly provides air circulation between drainage and vent systems, or acts as an auxiliary vent
- Yoke vent Connects upward from a soil or waste stack to a vent stack to prevent pressure changes in the stacks
- Wet vent A vent that also serves as a drain
- Dry vent A vent that carries no sewage or waste
Combination waste and vent system Waste piping that horizontally wet vents sinks or floor drains through an oversized common waste and vent pipe
Water and Backflow Definitions
Term Definition in brief
Building supply Pipe carrying potable water from the meter or source to the building or point of use on the lot
- Fixture branch Water pipe between the fixture supply pipe and the water distribution pipe
- Fixture supply Water pipe connecting the fixture with the fixture branch
Air gap, water distribution Unobstructed vertical distance through free atmosphere from the lowest potable outlet to the flood-level rim
Air gap, drainage Same concept for a pipe or fixture conveying waste, measured to the receptor's flood-level rim
- Air break A physical separation, which may be a low inlet into the indirect waste receptor
- Flood-level rim The top edge of a receptor from which water overflows
Critical level The marked point on a backflow device that sets its minimum height above the flood-level rim. With no marking, the bottom of the device
- Roof washer A device diverting initial rainfall away from a cistern, also called a first-flush device
- Washington Definition Amendments (WAC 51-56-0200)
205.0 Certified backflow assembly tester: certified by the Department of Health under chapter 246-292 WAC to inspect, test, maintain, and repair assemblies, devices, and air gaps (maintenance and repair in compliance with chapter 18.106 RCW).
210.0 Hot water: water at 100°F or more . The unamended UPC uses 120°F.
211.0 Insanitary (2015 amendment): includes a trap that does not keep its seal, an opening without a trap, a fixture without enough water to stay clean, a defective fixture or pipe, an unvented trap, and any cross-connection that could let foreign matter into domestic water.
218.0 Plumbing system: includes potable water, building supply and distribution pipes, alternate and rainwater systems, fixtures and traps, drainage and vent piping, and building drains within the property lines , plus potable water treating equipment, medical gas and medical vacuum systems , and water heaters . No certification is required for installing a plumbing system within the property lines and outside a building .
225.0 Water/wastewater utility: a public or private entity, including a water purveyor as defined in chapter 246-290 WAC, that treats or delivers reclaimed or potable water.
Referenced Standards (UPC Chapter 17)
Section 1701.1: the standards in Table 1701.1 are for design, testing, and installation of materials and devices, and are mandatory where required by code sections . Standard numbers you should recognize:
- Standard Subject
- ASSE 1001 Atmospheric vacuum breakers
- ASSE 1002 Antisiphon fill valves (ballcocks)
- ASSE 1010 Water hammer arresters (also PDI-WH 201)
- ASSE 1011 Hose connection vacuum breakers
- ASSE 1013 Reduced pressure principle assemblies
- ASSE 1015 Double check valve assemblies
- ASSE 1016 Shower and tub-shower control valves
- ASSE 1018 and 1044 Trap seal primers
- ASSE 1020 and 1056 Pressure and spill-resistant vacuum breakers
- ASSE 1037 Flushometers
- ASSE 1047 and 1048 RP and DC detector fire assemblies
- ASSE 1060 Outdoor enclosures for backflow assemblies
- ASSE 1061 Push-fit fittings
- ASSE 1069 Gang shower mixing valves
- ASSE 1070 Temperature-limiting devices
- ASSE 1079 Dielectric unions
- ASME A112.1.2 Air gaps
- ASME A112.18.1 / CSA B125.1 Faucets and fixture fittings
- ASME A112.19.2 / CSA B45.1 Ceramic fixtures
- ASTM B88 Copper water tube
- ASTM B813 and B828 Soldering flux and soldering practice
- ASTM C564 Gaskets for cast-iron soil pipe
- CISPI 301 and 310 Hubless cast-iron pipe and couplings
- NSF 14 Plastic piping components
- NSF 61 Drinking water system components
- NSF 350 On-site treated nonpotable water systems