10.2 Nonpotable Rainwater Catchment Systems (UPC Chapter 16 as Amended by Washington)

Washington Journeyman Plumber Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Administration, Licensing, & General Regulations

1.1 Washington Plumber Certification Law: RCW 18.106, WAC 296-400A, Trainees, & Supervision 1.2 Permits, Inspections, Tests, & Disinfection (UPC Chapter 1, 609, 712) 1.3 General Regulations: Prohibited Fittings, Pipe Protection, Nail Plates, Sleeves, & Trenching (UPC Chapter 3) 1.4 Hangers, Supports, Rod Sizes, Dissimilar Metals, & Expansion (UPC 313, Table 313.3)

2 Chapter 2: Plumbing Fixtures, Fittings, & Clearances

2.1 Fixture Setting, Clearances, Closet Flanges, & Water Closets (UPC 402, 411, 413; WA 402.5) 2.2 Showers, Shower Pans, Bathtubs, Lavatories, Bidets, & Scald Limits (UPC 407–410; WA 408) 2.3 Urinals, Floor Drains, Floor Sinks, Sinks, Dishwashers, Disposers, & Special Fixtures (UPC 412–421) 2.4 Minimum Fixture Counts in Washington: IBC Table 2902.1, Not UPC Table 422.1

3 Chapter 3: Water Heaters & Storage Tanks

3.1 Water Heater Permits, Sizing (WA Table 501.1), Bedroom and Bathroom Locations, & Safety Devices 3.2 Temperature and Pressure Relief Valves & Discharge Piping (UPC 504.6, 608; WA 608.3.1 and 608.5) 3.3 Water Heater Installation Details: Garages, Pans, Supports, Attic and Under-Floor Access, & Washington's Mechanical Code Deletions 3.4 Seismic Strapping, Thermal Expansion Tanks, Pressure Regulators, & Temperature Controls (WA 507.2, 608.2, 608.3)

4 Chapter 4: Water Supply and Distribution Systems

4.1 Water Piping Materials, Joints, Lead Limits, Under-Slab Rules, & Velocity (UPC 604, 605, 609, 610.12) 4.2 Water Supply Fixture Units & the Sizing Tables (UPC 610.3, 610.4, 610.8, 610.10) 4.3 Water Pressure Limits, Booster Pumps, Potable Water Tanks, & Water Hammer (UPC 607–609) 4.4 Water Valves, Shutoffs, Manifolds, & Hot Water Distribution (UPC 606, 609.11; WA 210.0 and 609.11)

5 Chapter 5: Backflow Prevention & Cross-Connection Control

5.1 Backflow Principles: Backsiphonage, Backpressure, & Degree of Hazard (UPC 602–603; WAC 246-290-490) 5.2 Backflow Assemblies and Devices: RP, DC, PVB, SVB, AVB, & Installation Rules (UPC 603.3, 603.4, Table 603.2) 5.3 Air Gaps, Critical Level, & Specific Backflow Applications (UPC Table 603.3.1, 603.5) 5.4 Backflow Testing, Certified Testers, & Washington's Cross-Connection Program (WA 603.4.2; WAC 246-290-490, 246-292)

6 Chapter 6: Sanitary Drainage Systems & Sizing

6.1 DWV Materials, Joints, & Changes in Direction (UPC 701, 704–706; WA 701.2) 6.2 Drainage Fixture Units, Trap Sizes, & Flow Conversions (UPC Table 702.1, 702.2, 702.3) 6.3 Sizing Drainage Piping with Table 703.2 (Vertical, Horizontal, Water Closet Limits, & WA Note 4) 6.4 Building Drains, Grade, Gravity Drainage, Backwater Valves, & Washington's Deletion of Building Sewer Rules

7 Chapter 7: Cleanouts, Sumps and Ejectors, Indirect Wastes, & Interceptors

7.1 Cleanouts: Location, Spacing, Size, and Clearance (UPC 707 as Amended by Washington) 7.2 Sumps, Sewage Ejectors, Grinder Pumps, & Macerating Systems (UPC 710) 7.3 Indirect Wastes, Air Gaps and Air Breaks, Receptors, Standpipes, & Condensate (UPC Chapter 8) 7.4 Interceptors and Separators: Grease, Sand, Oil, Laundry, & Bottling (UPC 1009–1017)

8 Chapter 8: Vents and Venting Fundamentals

8.1 Venting Fundamentals: Trap Seal Protection, Vent Sizing, the Half-Drain Rule, & Aggregate Venting (UPC 901–904) 8.2 Vent Grades and Connections, Vent Stacks, Relief and Yoke Vents, & Suds Relief (UPC 905, 907, 711) 8.3 Wet Venting and Circuit Venting (UPC 908, 911; WA 908.2.4 and 911.1) 8.4 Island Fixture Venting, Combination Waste and Vent Systems, & Engineered Vent Systems (UPC 909, 910, 912)

9 Chapter 9: Vent Terminations, Traps, & Priming

9.1 Vent Terminations: Roof Height, Clearances, Used Roofs, Outdoor Vents, & Frost Closure (UPC 906) 9.2 Traps, Trap Arms, Table 1002.2 Distances, & Prohibited Traps (UPC 1001–1004) 9.3 How Trap Seals Are Lost & How the Code Protects Them: Venting, Seal Depth, and Trap Seal Primers (UPC 901.3, 1005, 1007)

10 Chapter 10: Alternate Water, Rainwater Catchment, Definitions, & Referenced Standards

10.1 Alternate Water Sources: Reclaimed, Gray, and On-Site Treated Water (UPC Chapter 15 as Amended by Washington) 10.2 Nonpotable Rainwater Catchment Systems (UPC Chapter 16 as Amended by Washington) 10.3 Key UPC Definitions and Referenced Standards (UPC Chapters 2 and 17; WA Definition Amendments)

11 Chapter 11: Part 2 — Waste & Vent Isometric Drawings & Plan Analysis

11.1 Part 2 Explained: Reading the Waste and Vent Drawing 11.2 Part 2 Worked Example: Accumulating DFU and Sizing Every Drain Segment 11.3 Part 2 Worked Example: Sizing Individual, Branch, and Main Vents and Checking Aggregate Venting 11.4 Spotting Code Violations on Waste and Vent Drawings: A Checklist with Code Citations

12 Chapter 12: Part 3 — Water Supply Isometric Drawings & Pipe Sizing

12.1 Part 3 Explained: Reading the Water Sizing Drawing and Gathering the 610.7 Data 12.2 Part 3 Worked Example: Accumulating Water Supply Fixture Units, Cold and Hot 12.3 Part 3: Available Pressure, Elevation, Regulators, Device Losses, and the Length Column 12.4 Part 3 Worked Example: Sizing the Meter, Building Supply, and Every Branch with Table 610.4

13 Chapter 13: Washington Amendments Review, Plumbing Math, & Water Service Special Topics

13.1 Washington's Amendments to the 2015 UPC (WAC 51-56): A Consolidated Review 13.2 Plumbing Math for the Exam: Offsets, Rolling Offsets, Grade, Areas, Volumes, and Pressure 13.3 Water Service Details, Treatment Units, Softeners, & Residential Sprinklers (UPC 604, 609, 611, 612; WA Amendments)

14 Chapter 14: Comprehensive Exam Preparation & Test-Taking Strategy

14.1 The PSI Exam Day: Structure, Fees, Retakes, Rules, and Pacing 14.2 Using the Provided Tables Fast (702.1, 610.3, 610.4, 610.10) and Writing the Missing Ones from Memory 14.3 High-Yield Number Review, Classic Traps, and a Final Readiness Checklist

10.2 Nonpotable Rainwater Catchment Systems (UPC Chapter 16 as Amended by Washington)

Key Takeaways Explain This Topic AI

Washington's 1602.1 requires AHJ approval of rainwater catchment systems supplying water closets, urinals, trap primers, irrigation, water features, and cooling towers, except exterior irrigation piping.

A rainwater system may have no direct connection to potable or reclaimed water; makeup water must enter through an air gap or reduced pressure principle backflow preventer (UPC 1602.4).

A permit is not required for an exterior rainwater system used for outdoor drip and subsurface irrigation with a maximum storage capacity of 360 gallons (UPC 1601.3).

Rainwater supplied to water closets, urinals, trap primers, and drip irrigation must pass a filter of 100 microns or finer (UPC 1602.9.11).

Pumps supplying water closets, urinals, and trap primers must deliver at least 15 psi residual at the most remote outlet (UPC 1602.9.6).

Last updated: September 2026

What Chapter 16 Covers

A nonpotable rainwater catchment system collects rain from roofs or other manmade aboveground surfaces, stores it, and supplies nonpotable uses. L&I lists Chapter 16 in the Part 1 content. Potable rainwater systems are in UPC Appendix K, which Washington does not adopt.

Washington 1602.1: Installation, construction, alteration, and repair of rainwater catchment systems that supply water closets, urinals, trap primers for floor drains and floor sinks, irrigation, industrial processes, water features, cooling tower makeup, and other uses must be approved by the AHJ . Exception: exterior irrigation piping.

Permits, Design, and Maintenance (UPC 1601)

Section Requirement

1601.3 Permit A permit is required. Exception: exterior systems for outdoor drip and subsurface irrigation storing no more than 360 gallons

1601.2 Design By a person registered or licensed for plumbing design, or who demonstrates competency. The design professional requirement is waived for irrigation systems of 360 gallons or less. Components must be listed

1601.5 Maintenance Inspection per Table 1601.5; the owner keeps the maintenance log and is responsible for maintenance

1601.9 No mercury-containing controls in contact with rainwater

1601.10 Separation Underground rainwater piping is separated from the building sewer per 609.2. It may share a trench with potable water at 12 inches vertical and horizontal separation where both materials are approved for use in buildings

1601.11 Abandonment (WA 1601.11.1) Disconnect, drain, plug, and cap. Washington adds that abandoned components may not be reused for potable water . Underground tanks are drained and filled or removed

  • 1601.12 Sizing Rainwater distribution piping is sized per Chapter 6
  • Connections and Makeup Water (UPC 1602.4)

No direct connection to a potable supply or an alternate water source system.

Potable or reclaimed makeup water is allowed only through an air gap or a reduced pressure principle backflow preventer .

Both systems must have the valves and air or vacuum relief needed for deactivation and draining during a cross-connection test (1602.9.2). An initial test is required before occupancy when any part of the system is inside a building (1602.5).

Washington 1602.11.2.3: If a cross-connection is found, follow the same shutdown, disconnect, retest, 50 ppm for 24 hours chlorination, and Washington-certified laboratory procedure as for reclaimed water (Section 10.1).

Collection Surfaces and Water Quality

1602.9.3: Rainwater is collected from roof surfaces or other manmade, aboveground collection surfaces . Runoff from parking areas or surfaces at or below grade is treated as on-site treated nonpotable water under 1504.

1602.9.3.2: Overflows and bleed-off from roof-mounted equipment may not discharge onto roof areas that collect rainwater.

1602.9.10: A debris excluder or other approved means keeps leaves, needles, and sediment out of the tank. A roof washer , or first-flush device, diverts the initial rainfall.

1602.9.11: A 100-micron or finer filter is required for rainwater supplied to water closets, urinals, trap primers, and drip irrigation .

Table 1602.9.4: Where the AHJ sets no quality standard, the table sets minimum treatment by use. Every use needs a debris excluder. Spray irrigation from storage of 360 gallons or more also needs disinfection , and where the table sets quality limits they are E. coli under 100 CFU per 100 mL and turbidity under 10 NTU . Treatment is not required for subsurface or drip irrigation, or for aboveground irrigation from storage of 360 gallons or less, beyond the debris and filter rules.

Storage Tanks (UPC 1602.9.5)

  • Item Requirement
  • Construction Solid, durable, watertight, and AHJ-approved
  • Aboveground Opaque or shielded from sunlight; accessible; on a foundation designed for the load

Belowground Designed for earth loads; covers support at least 300 lb per sq ft ; manholes at least 20 inches in diameter, set at least 4 inches above grade sloped away; ballasted or anchored against flotation

Drain and overflow A means to drain and clean. The overflow has no shutoff valve , is at least the aggregate area of the inflow pipes, and discharges per the storm drainage rules. It gets a backwater valve if connected to storm drainage

Openings Protected against insects, birds, and rodents. Access openings over 12 inches must be lockable or otherwise secured

Marking Permanently marked with its capacity and a nonpotable warning

Venting Where overflow or drain piping does not vent the tank, a vent of at least 1-1/2 inches , ending at least 6 inches above grade , turned down, with a 3/32-inch mesh screen

Pumps, Pressure, and Piping

1602.9.6: Pumps are listed . Pumps supplying water closets, urinals, and trap primers must deliver at least 15 psi residual at the highest and most remote outlet. If pressure inside the building exceeds 80 psi , install a regulator to reduce it to 80 psi or less.

1602.7: Distribution piping materials meet the potable water materials rules. Gutters, downspouts, and conveyance piping meet the drainage and storm materials rules.

1602.9.12: Gutters keep a minimum slope and are sized per 1103.3.

1602.9.9: Tanks and piping subject to freezing need approved freeze protection.

1602.8 and 601.3: Piping has a purple background marked "CAUTION: NONPOTABLE RAINWATER WATER, DO NOT DRINK." Outside hose bibbs are allowed and are marked "CAUTION: NONPOTABLE WATER, DO NOT DRINK" (1602.9.1).

Worked Scenario

An office building will flush water closets and urinals with roof rainwater stored in a 3,000-gallon basement tank.

Approval and permit: AHJ approval (WA 1602.1) and a permit (1601.3).

Makeup water: potable makeup through an air gap or RP (1602.4).

Treatment: a debris excluder and a 100-micron filter (1602.9.11), plus any additional treatment the AHJ or Table 1602.9.4 requires for flushing.

Pump: listed, delivering 15 psi residual at the top-floor fixtures, with a regulator if pressure exceeds 80 psi.

Tank: watertight, vented or relieved through the overflow, openings screened, and capacity marked. A belowground installation needs a secured manhole of at least 20 inches.

Identification: purple piping and labels, with signs where required.

Testing: a cross-connection test before occupancy, witnessed by the AHJ.