5.2 Backflow Assemblies and Devices: RP, DC, PVB, SVB, AVB, & Installation Rules (UPC 603.3, 603.4, Table 603.2)
Washington Journeyman Plumber Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Administration, Licensing, & General Regulations
1.1 Washington Plumber Certification Law: RCW 18.106, WAC 296-400A, Trainees, & Supervision 1.2 Permits, Inspections, Tests, & Disinfection (UPC Chapter 1, 609, 712) 1.3 General Regulations: Prohibited Fittings, Pipe Protection, Nail Plates, Sleeves, & Trenching (UPC Chapter 3) 1.4 Hangers, Supports, Rod Sizes, Dissimilar Metals, & Expansion (UPC 313, Table 313.3)
2 Chapter 2: Plumbing Fixtures, Fittings, & Clearances
2.1 Fixture Setting, Clearances, Closet Flanges, & Water Closets (UPC 402, 411, 413; WA 402.5) 2.2 Showers, Shower Pans, Bathtubs, Lavatories, Bidets, & Scald Limits (UPC 407–410; WA 408) 2.3 Urinals, Floor Drains, Floor Sinks, Sinks, Dishwashers, Disposers, & Special Fixtures (UPC 412–421) 2.4 Minimum Fixture Counts in Washington: IBC Table 2902.1, Not UPC Table 422.1
3 Chapter 3: Water Heaters & Storage Tanks
3.1 Water Heater Permits, Sizing (WA Table 501.1), Bedroom and Bathroom Locations, & Safety Devices 3.2 Temperature and Pressure Relief Valves & Discharge Piping (UPC 504.6, 608; WA 608.3.1 and 608.5) 3.3 Water Heater Installation Details: Garages, Pans, Supports, Attic and Under-Floor Access, & Washington's Mechanical Code Deletions 3.4 Seismic Strapping, Thermal Expansion Tanks, Pressure Regulators, & Temperature Controls (WA 507.2, 608.2, 608.3)
4 Chapter 4: Water Supply and Distribution Systems
4.1 Water Piping Materials, Joints, Lead Limits, Under-Slab Rules, & Velocity (UPC 604, 605, 609, 610.12) 4.2 Water Supply Fixture Units & the Sizing Tables (UPC 610.3, 610.4, 610.8, 610.10) 4.3 Water Pressure Limits, Booster Pumps, Potable Water Tanks, & Water Hammer (UPC 607–609) 4.4 Water Valves, Shutoffs, Manifolds, & Hot Water Distribution (UPC 606, 609.11; WA 210.0 and 609.11)
5 Chapter 5: Backflow Prevention & Cross-Connection Control
5.1 Backflow Principles: Backsiphonage, Backpressure, & Degree of Hazard (UPC 602–603; WAC 246-290-490) 5.2 Backflow Assemblies and Devices: RP, DC, PVB, SVB, AVB, & Installation Rules (UPC 603.3, 603.4, Table 603.2) 5.3 Air Gaps, Critical Level, & Specific Backflow Applications (UPC Table 603.3.1, 603.5) 5.4 Backflow Testing, Certified Testers, & Washington's Cross-Connection Program (WA 603.4.2; WAC 246-290-490, 246-292)
6 Chapter 6: Sanitary Drainage Systems & Sizing
6.1 DWV Materials, Joints, & Changes in Direction (UPC 701, 704–706; WA 701.2) 6.2 Drainage Fixture Units, Trap Sizes, & Flow Conversions (UPC Table 702.1, 702.2, 702.3) 6.3 Sizing Drainage Piping with Table 703.2 (Vertical, Horizontal, Water Closet Limits, & WA Note 4) 6.4 Building Drains, Grade, Gravity Drainage, Backwater Valves, & Washington's Deletion of Building Sewer Rules
7 Chapter 7: Cleanouts, Sumps and Ejectors, Indirect Wastes, & Interceptors
7.1 Cleanouts: Location, Spacing, Size, and Clearance (UPC 707 as Amended by Washington) 7.2 Sumps, Sewage Ejectors, Grinder Pumps, & Macerating Systems (UPC 710) 7.3 Indirect Wastes, Air Gaps and Air Breaks, Receptors, Standpipes, & Condensate (UPC Chapter 8) 7.4 Interceptors and Separators: Grease, Sand, Oil, Laundry, & Bottling (UPC 1009–1017)
8 Chapter 8: Vents and Venting Fundamentals
8.1 Venting Fundamentals: Trap Seal Protection, Vent Sizing, the Half-Drain Rule, & Aggregate Venting (UPC 901–904) 8.2 Vent Grades and Connections, Vent Stacks, Relief and Yoke Vents, & Suds Relief (UPC 905, 907, 711) 8.3 Wet Venting and Circuit Venting (UPC 908, 911; WA 908.2.4 and 911.1) 8.4 Island Fixture Venting, Combination Waste and Vent Systems, & Engineered Vent Systems (UPC 909, 910, 912)
9 Chapter 9: Vent Terminations, Traps, & Priming
9.1 Vent Terminations: Roof Height, Clearances, Used Roofs, Outdoor Vents, & Frost Closure (UPC 906) 9.2 Traps, Trap Arms, Table 1002.2 Distances, & Prohibited Traps (UPC 1001–1004) 9.3 How Trap Seals Are Lost & How the Code Protects Them: Venting, Seal Depth, and Trap Seal Primers (UPC 901.3, 1005, 1007)
10 Chapter 10: Alternate Water, Rainwater Catchment, Definitions, & Referenced Standards
10.1 Alternate Water Sources: Reclaimed, Gray, and On-Site Treated Water (UPC Chapter 15 as Amended by Washington) 10.2 Nonpotable Rainwater Catchment Systems (UPC Chapter 16 as Amended by Washington) 10.3 Key UPC Definitions and Referenced Standards (UPC Chapters 2 and 17; WA Definition Amendments)
11 Chapter 11: Part 2 — Waste & Vent Isometric Drawings & Plan Analysis
11.1 Part 2 Explained: Reading the Waste and Vent Drawing 11.2 Part 2 Worked Example: Accumulating DFU and Sizing Every Drain Segment 11.3 Part 2 Worked Example: Sizing Individual, Branch, and Main Vents and Checking Aggregate Venting 11.4 Spotting Code Violations on Waste and Vent Drawings: A Checklist with Code Citations
12 Chapter 12: Part 3 — Water Supply Isometric Drawings & Pipe Sizing
12.1 Part 3 Explained: Reading the Water Sizing Drawing and Gathering the 610.7 Data 12.2 Part 3 Worked Example: Accumulating Water Supply Fixture Units, Cold and Hot 12.3 Part 3: Available Pressure, Elevation, Regulators, Device Losses, and the Length Column 12.4 Part 3 Worked Example: Sizing the Meter, Building Supply, and Every Branch with Table 610.4
13 Chapter 13: Washington Amendments Review, Plumbing Math, & Water Service Special Topics
13.1 Washington's Amendments to the 2015 UPC (WAC 51-56): A Consolidated Review 13.2 Plumbing Math for the Exam: Offsets, Rolling Offsets, Grade, Areas, Volumes, and Pressure 13.3 Water Service Details, Treatment Units, Softeners, & Residential Sprinklers (UPC 604, 609, 611, 612; WA Amendments)
14 Chapter 14: Comprehensive Exam Preparation & Test-Taking Strategy
14.1 The PSI Exam Day: Structure, Fees, Retakes, Rules, and Pacing 14.2 Using the Provided Tables Fast (702.1, 610.3, 610.4, 610.10) and Writing the Missing Ones from Memory 14.3 High-Yield Number Review, Classic Traps, and a Final Readiness Checklist
5.2 Backflow Assemblies and Devices: RP, DC, PVB, SVB, AVB, & Installation Rules (UPC 603.3, 603.4, Table 603.2)
Key Takeaways Explain This Topic AI
A reduced pressure principle assembly (RP, ASSE 1013) protects against both backsiphonage and backpressure for both pollution and contamination hazards (UPC Table 603.2).
A double check valve assembly (DC, ASSE 1015) is limited to pollution (low hazard) but protects against both backsiphonage and backpressure (UPC Table 603.2).
A PVB (ASSE 1020) or SVB (ASSE 1056) must be installed upright at least 12 inches above all downstream piping and the flood-level rim (UPC Table 603.2).
An atmospheric vacuum breaker (ASSE 1001) must be upright, have no valve downstream, sit at least 6 inches above downstream piping, and not be under pressure more than 12 hours in any 24 (UPC Table 603.2).
Backflow assemblies need at least 12 inches of clearance below them, and a permanent platform where they are more than 5 feet above the floor (UPC 603.4.3).
Last updated: September 2026
Choosing a Device: Three Questions
What is the degree of hazard? Pollution (low) or contamination (high)?
What kind of backflow can occur? Backsiphonage only, or backpressure as well?
Will the device be under continuous pressure? AVBs may not be.
The Main Devices (UPC 603.3 and Table 603.2)
Device Standard Construction Pollution Contamination Installation (Table 603.2)
Air gap ASME A112.1.2 Unobstructed vertical separation Backsiphonage and backpressure Backsiphonage and backpressure Per Table 603.3.1
RP (reduced pressure principle) ASSE 1013 Two check valves, a differential relief valve, 4 test cocks, 2 shutoffs Both Both Horizontal unless listed; 12-inch bottom clearance; may discharge water
DC (double check valve) ASSE 1015 Two check valves, 4 test cocks, 2 shutoffs Both Not permitted Horizontal unless listed; 12-inch bottom clearance; does not discharge
PVB (pressure vacuum breaker) ASSE 1020 Loaded air inlet, loaded check, 2 test cocks, 2 shutoffs Backsiphonage only Backsiphonage only Upright; may have valves downstream ; at least 12 inches above downstream piping and flood rim; may discharge water
SVB (spill-resistant vacuum breaker) ASSE 1056 One check, air inlet vent, test cock, shutoffs Backsiphonage only Backsiphonage only Upright; at least 12 inches above downstream piping and flood rim
AVB (atmospheric vacuum breaker) ASSE 1001 Body, checking member, atmospheric port Backsiphonage only Backsiphonage only Upright; no valve downstream ; at least 6 inches above downstream piping and flood rim; not under pressure more than 12 hours in 24
Double check detector (fire) ASSE 1048 DC with a metered bypass DC Both Not permitted Fire systems under continuous pressure
Reduced pressure detector (fire) ASSE 1047 RP with a metered bypass RP Both Both Fire systems under continuous pressure
Other Table 603.2 devices, all backsiphonage-only and not for continuous pressure unless noted:
Antisiphon ballcock (ASSE 1002): critical level 1 inch above the overflow.
Hose connection vacuum breaker (ASSE 1011): no valve downstream.
Hose connection backflow preventer (ASSE 1052).
Freeze-resistant wall hydrants (ASSE 1019 and 1053).
Freeze-resistant sanitary yard hydrants (ASSE 1057).
How an RP Works
The first check creates a pressure drop, so the zone between the checks is always lower than supply pressure.
A differential relief valve senses supply pressure against zone pressure. If the difference shrinks, the valve opens and dumps the zone to atmosphere . That happens if the first check leaks, if backpressure pushes past the second check, or if supply pressure falls.
Water from the relief port shows that the assembly is protecting the system. It is a normal response to a pressure change, not a nuisance leak. Provide drainage sized to the manufacturer's discharge rate (603.4.8).
Because the relief port must stay open to air, 603.4.9 prohibits devices with atmospheric vents or ports in pits, underground, or submerged locations . They are also not allowed in areas with toxic, poisonous, or corrosive fumes. Washington's DOH rule (WAC 246-290-490) also requires installation so the assembly cannot become submerged by flooding.
Why AVBs Have the Tightest Limits
An AVB's float drops by gravity to open the air port. Continuous pressure can hold the float up against its seat until it sticks. A downstream valve would trap pressure on it. That is why an AVB must have no shutoff downstream and may not be under pressure for more than 12 hours in any 24-hour period . A PVB or SVB has a spring-loaded air inlet and check, so it tolerates continuous pressure and downstream valves.
A PVB may spill water when it is repressurized, so 603.3.5 allows it indoors only where provisions for spillage are provided . An SVB is designed to avoid that spill.
General Installation Requirements (UPC 603.4)
Section Rule
603.2 / WA 603.1 Devices must be approved by the AHJ. In Washington, assemblies protecting the public water system must be models on the Department of Health approved list
603.4.1 Multiple backflow valves at one location on a premises must each be permanently identified
603.4.3 Access and clearance per the manufacturer, but at least 12 inches between the lowest part of the assembly and the grade, floor, or platform. Installations more than 5 feet above floor or grade need a permanent platform that can support a tester
- 603.4.5 Devices on hot water above 110°F must be rated for that temperature
- 603.4.7 Protect from freezing, for example with an ASSE 1060 enclosure
- 603.4.8 Drain lines sized to the device's discharge rate
Table 603.2 note 2 Installation in a pit or vault requires prior AHJ approval; never for devices with atmospheric ports (603.4.9)
Quick Selection Examples
Application Minimum protection
Lawn irrigation, no pumps or chemicals (WA 603.5.6) AVB, PVB, SVB, or RP; DC only if the purveyor and the AHJ approve
- Irrigation with chemical injection (603.5.6.3) RP
- Boiler makeup (WA 603.5.10) Air gap or RP
- Carbonated beverage dispenser (WA 603.5.12) Listed RP
- Fire sprinkler, no chemicals (WA 603.5.14) DC, double check detector, RP, or RP detector
- Fire sprinkler with antifreeze or chemicals (603.5.14.2) RP or RP detector
- Pure water process system, such as dialysis (603.5.18) RP
Pool, spa, or hot tub with a submerged fill line or a direct connection to the circulation system (603.5.20) Air gap or RP