7.1 Cleanouts: Location, Spacing, Size, and Clearance (UPC 707 as Amended by Washington)

Washington Journeyman Plumber Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Administration, Licensing, & General Regulations

1.1 Washington Plumber Certification Law: RCW 18.106, WAC 296-400A, Trainees, & Supervision 1.2 Permits, Inspections, Tests, & Disinfection (UPC Chapter 1, 609, 712) 1.3 General Regulations: Prohibited Fittings, Pipe Protection, Nail Plates, Sleeves, & Trenching (UPC Chapter 3) 1.4 Hangers, Supports, Rod Sizes, Dissimilar Metals, & Expansion (UPC 313, Table 313.3)

2 Chapter 2: Plumbing Fixtures, Fittings, & Clearances

2.1 Fixture Setting, Clearances, Closet Flanges, & Water Closets (UPC 402, 411, 413; WA 402.5) 2.2 Showers, Shower Pans, Bathtubs, Lavatories, Bidets, & Scald Limits (UPC 407–410; WA 408) 2.3 Urinals, Floor Drains, Floor Sinks, Sinks, Dishwashers, Disposers, & Special Fixtures (UPC 412–421) 2.4 Minimum Fixture Counts in Washington: IBC Table 2902.1, Not UPC Table 422.1

3 Chapter 3: Water Heaters & Storage Tanks

3.1 Water Heater Permits, Sizing (WA Table 501.1), Bedroom and Bathroom Locations, & Safety Devices 3.2 Temperature and Pressure Relief Valves & Discharge Piping (UPC 504.6, 608; WA 608.3.1 and 608.5) 3.3 Water Heater Installation Details: Garages, Pans, Supports, Attic and Under-Floor Access, & Washington's Mechanical Code Deletions 3.4 Seismic Strapping, Thermal Expansion Tanks, Pressure Regulators, & Temperature Controls (WA 507.2, 608.2, 608.3)

4 Chapter 4: Water Supply and Distribution Systems

4.1 Water Piping Materials, Joints, Lead Limits, Under-Slab Rules, & Velocity (UPC 604, 605, 609, 610.12) 4.2 Water Supply Fixture Units & the Sizing Tables (UPC 610.3, 610.4, 610.8, 610.10) 4.3 Water Pressure Limits, Booster Pumps, Potable Water Tanks, & Water Hammer (UPC 607–609) 4.4 Water Valves, Shutoffs, Manifolds, & Hot Water Distribution (UPC 606, 609.11; WA 210.0 and 609.11)

5 Chapter 5: Backflow Prevention & Cross-Connection Control

5.1 Backflow Principles: Backsiphonage, Backpressure, & Degree of Hazard (UPC 602–603; WAC 246-290-490) 5.2 Backflow Assemblies and Devices: RP, DC, PVB, SVB, AVB, & Installation Rules (UPC 603.3, 603.4, Table 603.2) 5.3 Air Gaps, Critical Level, & Specific Backflow Applications (UPC Table 603.3.1, 603.5) 5.4 Backflow Testing, Certified Testers, & Washington's Cross-Connection Program (WA 603.4.2; WAC 246-290-490, 246-292)

6 Chapter 6: Sanitary Drainage Systems & Sizing

6.1 DWV Materials, Joints, & Changes in Direction (UPC 701, 704–706; WA 701.2) 6.2 Drainage Fixture Units, Trap Sizes, & Flow Conversions (UPC Table 702.1, 702.2, 702.3) 6.3 Sizing Drainage Piping with Table 703.2 (Vertical, Horizontal, Water Closet Limits, & WA Note 4) 6.4 Building Drains, Grade, Gravity Drainage, Backwater Valves, & Washington's Deletion of Building Sewer Rules

7 Chapter 7: Cleanouts, Sumps and Ejectors, Indirect Wastes, & Interceptors

7.1 Cleanouts: Location, Spacing, Size, and Clearance (UPC 707 as Amended by Washington) 7.2 Sumps, Sewage Ejectors, Grinder Pumps, & Macerating Systems (UPC 710) 7.3 Indirect Wastes, Air Gaps and Air Breaks, Receptors, Standpipes, & Condensate (UPC Chapter 8) 7.4 Interceptors and Separators: Grease, Sand, Oil, Laundry, & Bottling (UPC 1009–1017)

8 Chapter 8: Vents and Venting Fundamentals

8.1 Venting Fundamentals: Trap Seal Protection, Vent Sizing, the Half-Drain Rule, & Aggregate Venting (UPC 901–904) 8.2 Vent Grades and Connections, Vent Stacks, Relief and Yoke Vents, & Suds Relief (UPC 905, 907, 711) 8.3 Wet Venting and Circuit Venting (UPC 908, 911; WA 908.2.4 and 911.1) 8.4 Island Fixture Venting, Combination Waste and Vent Systems, & Engineered Vent Systems (UPC 909, 910, 912)

9 Chapter 9: Vent Terminations, Traps, & Priming

9.1 Vent Terminations: Roof Height, Clearances, Used Roofs, Outdoor Vents, & Frost Closure (UPC 906) 9.2 Traps, Trap Arms, Table 1002.2 Distances, & Prohibited Traps (UPC 1001–1004) 9.3 How Trap Seals Are Lost & How the Code Protects Them: Venting, Seal Depth, and Trap Seal Primers (UPC 901.3, 1005, 1007)

10 Chapter 10: Alternate Water, Rainwater Catchment, Definitions, & Referenced Standards

10.1 Alternate Water Sources: Reclaimed, Gray, and On-Site Treated Water (UPC Chapter 15 as Amended by Washington) 10.2 Nonpotable Rainwater Catchment Systems (UPC Chapter 16 as Amended by Washington) 10.3 Key UPC Definitions and Referenced Standards (UPC Chapters 2 and 17; WA Definition Amendments)

11 Chapter 11: Part 2 — Waste & Vent Isometric Drawings & Plan Analysis

11.1 Part 2 Explained: Reading the Waste and Vent Drawing 11.2 Part 2 Worked Example: Accumulating DFU and Sizing Every Drain Segment 11.3 Part 2 Worked Example: Sizing Individual, Branch, and Main Vents and Checking Aggregate Venting 11.4 Spotting Code Violations on Waste and Vent Drawings: A Checklist with Code Citations

12 Chapter 12: Part 3 — Water Supply Isometric Drawings & Pipe Sizing

12.1 Part 3 Explained: Reading the Water Sizing Drawing and Gathering the 610.7 Data 12.2 Part 3 Worked Example: Accumulating Water Supply Fixture Units, Cold and Hot 12.3 Part 3: Available Pressure, Elevation, Regulators, Device Losses, and the Length Column 12.4 Part 3 Worked Example: Sizing the Meter, Building Supply, and Every Branch with Table 610.4

13 Chapter 13: Washington Amendments Review, Plumbing Math, & Water Service Special Topics

13.1 Washington's Amendments to the 2015 UPC (WAC 51-56): A Consolidated Review 13.2 Plumbing Math for the Exam: Offsets, Rolling Offsets, Grade, Areas, Volumes, and Pressure 13.3 Water Service Details, Treatment Units, Softeners, & Residential Sprinklers (UPC 604, 609, 611, 612; WA Amendments)

14 Chapter 14: Comprehensive Exam Preparation & Test-Taking Strategy

14.1 The PSI Exam Day: Structure, Fees, Retakes, Rules, and Pacing 14.2 Using the Provided Tables Fast (702.1, 610.3, 610.4, 610.10) and Writing the Missing Ones from Memory 14.3 High-Yield Number Review, Classic Traps, and a Final Readiness Checklist

7.1 Cleanouts: Location, Spacing, Size, and Clearance (UPC 707 as Amended by Washington)

Key Takeaways Explain This Topic AI

A horizontal drain needs a cleanout at its upper terminal, one for each 100 feet of developed length, and one for each aggregate horizontal change of direction exceeding 135 degrees (WA 707.4).

A cleanout may be omitted on a horizontal drain less than 5 feet long unless it serves sinks or urinals (WA 707.4 exception 1).

Washington's 707.9 requires 12 inches of clearance in front of cleanouts on pipe 2 inches or smaller and 18 inches on pipe over 2 inches.

Under Washington's 707.9, an under-floor cleanout may be no more than 20 feet from an access door, trap door, or crawl hole.

UPC Table 707.1 requires a 1-1/2-inch cleanout for 1-1/2 and 2-inch pipe, 2-1/2-inch for 2-1/2 and 3-inch pipe, and 3-1/2-inch for 4-inch and larger pipe.

Last updated: September 2026

Why Cleanouts Appear on the Part 2 Drawing

L&I describes the Part 2 exercise as a building drawing showing "the illustrated piping for the vents, waste, and cleanouts ." Expect questions on where cleanouts are required, where they may be omitted, and what size they must be. Washington amends two cleanout sections, so know the Washington numbers.

Where Cleanouts Are Required (Washington 707.4)

Each horizontal drainage pipe shall be provided with a cleanout at its upper terminal , and each run of piping that is more than 100 feet in total developed length shall be provided with a cleanout for each 100 feet, or fraction thereof , in length of such piping. An additional cleanout shall be provided in a drainage line for each aggregate horizontal change of direction exceeding 135 degrees .

Exceptions:

A cleanout may be omitted on a horizontal drain less than 5 feet long , unless the line serves sinks or urinals .

A cleanout may be omitted on a horizontal drainage pipe installed on a slope of 72 degrees or less from vertical (a one-fifth bend).

Except for the building drain, its horizontal branches, and urinals , no cleanout is required on piping above the floor level of the lowest floor of the building.

An approved two-way cleanout fitting may replace an upper-terminal cleanout. It may be installed inside the building wall near the connection between the building drain and the building sewer, or outside the building at the lower end of the building drain and extended to grade.

The unamended 2015 UPC also requires a cleanout above the fixture connection fitting for every urinal. Washington's version of 707.4 does not include that sentence. Urinal drains are still singled out in exceptions 1 and 3.

Counting aggregate change of direction

Add the horizontal turns along a run. Two 90-degree turns = 180°, so one additional cleanout is required. A 45° plus a 90° turn = 135°, which does not exceed 135°, so no additional cleanout is needed for that pair. A third 45° turn (180° total) would require one.

Cleanout Construction and Installation

Section Rule

707.1 Cast-iron pipe cleanouts use a cast-iron or copper-alloy body and an approved plug. Other pipe uses the plugs in Table 707.1, a copper-alloy cap, or an approved ABS, PVC, or stainless plug. Plugs have raised square heads or countersunk slots

707.3 Cleanouts are watertight and gastight

707.5 Cleanouts open in the direction of flow or at right angles to it. Except for wye-branch and end-of-line cleanouts, they are installed vertically above the flow line

707.6 A cleanout extension is drainage piping, and each 90-degree extension comes off a wye-type fitting or equivalent

707.7 An interceptor's cleanout must be outside the interceptor

707.8 Cleanouts are above grade and readily accessible , unless under an approved cover plate that still gives the required clearances

  • 707.12 Countersunk plugs where raised heads would be a hazard
  • 707.13 A hubless blind plug used as a cleanout must leave the whole coupling and plug accessible
  • 707.14 Trap arm cleanouts follow 1002.3 (Section 9.2)
  • 710.1 Cleanouts on drains through a backwater valve are labeled "backwater valve downstream"
  • Clearance (Washington 707.9)
  • Item Washington 707.9 Unamended 2015 UPC
  • Front clearance, pipe 2 inches or smaller 12 inches 18 inches
  • Front clearance, pipe over 2 inches 18 inches 24 inches

Under-floor cleanouts Extend to or above the finished floor, or outside the building, where there is less than 18 inches of vertical clearance or 30 inches of horizontal clearance from the access Same

  • Maximum distance of an under-floor cleanout from an access door, trap door, or crawl hole 20 feet 5 feet
  • Cleanout Size (Table 707.1)
  • Pipe size Minimum cleanout size Threads per inch
  • 1-1/2 in 1-1/2 in 11-1/2
  • 2 in 1-1/2 in 11-1/2
  • 2-1/2 in 2-1/2 in 8
  • 3 in 2-1/2 in 8
  • 4 in and larger 3-1/2 in 8

Section 707.10 requires cleanout fittings to be not less in size than Table 707.1.

Worked Example

A one-story commercial building has a 4-inch building drain running 140 feet from its upper end to where it leaves the building. It makes one 90° and one 45° horizontal turn. A 3-inch branch 4 feet long serves a floor drain, and a 2-inch branch 4 feet long serves a mop sink.

Upper terminal of the building drain: cleanout required.

Length: 140 feet is more than 100 feet, so one more cleanout is required within the run. That is 100 feet, then a fraction of the next 100.

Turns: 90° + 45° = 135°, which does not exceed 135°, so no additional cleanout is needed.

3-inch floor drain branch, 4 feet: less than 5 feet and not serving sinks or urinals, so exception 1 allows omitting the cleanout.

2-inch mop sink branch, 4 feet: a mop basin is a sink. Exception 1 does not apply, so it needs a cleanout at its upper end.

Sizes: 3-1/2-inch cleanouts on the 4-inch drain, and a 1-1/2-inch cleanout on the 2-inch branch.

Clearance: 18 inches in front of the 4-inch drain cleanouts and 12 inches in front of the 2-inch cleanout (Washington 707.9).