Study guide

14.2 Using the Provided Tables Fast (702.1, 610.3, 610.4, 610.10) and Writing the Missing Ones from Memory

Washington Journeyman Plumber Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Administration, Licensing, & General Regulations

1.1 Washington Plumber Certification Law: RCW 18.106, WAC 296-400A, Trainees, & Supervision 1.2 Permits, Inspections, Tests, & Disinfection (UPC Chapter 1, 609, 712) 1.3 General Regulations: Prohibited Fittings, Pipe Protection, Nail Plates, Sleeves, & Trenching (UPC Chapter 3) 1.4 Hangers, Supports, Rod Sizes, Dissimilar Metals, & Expansion (UPC 313, Table 313.3)

2 Chapter 2: Plumbing Fixtures, Fittings, & Clearances

2.1 Fixture Setting, Clearances, Closet Flanges, & Water Closets (UPC 402, 411, 413; WA 402.5) 2.2 Showers, Shower Pans, Bathtubs, Lavatories, Bidets, & Scald Limits (UPC 407–410; WA 408) 2.3 Urinals, Floor Drains, Floor Sinks, Sinks, Dishwashers, Disposers, & Special Fixtures (UPC 412–421) 2.4 Minimum Fixture Counts in Washington: IBC Table 2902.1, Not UPC Table 422.1

3 Chapter 3: Water Heaters & Storage Tanks

3.1 Water Heater Permits, Sizing (WA Table 501.1), Bedroom and Bathroom Locations, & Safety Devices 3.2 Temperature and Pressure Relief Valves & Discharge Piping (UPC 504.6, 608; WA 608.3.1 and 608.5) 3.3 Water Heater Installation Details: Garages, Pans, Supports, Attic and Under-Floor Access, & Washington's Mechanical Code Deletions 3.4 Seismic Strapping, Thermal Expansion Tanks, Pressure Regulators, & Temperature Controls (WA 507.2, 608.2, 608.3)

4 Chapter 4: Water Supply and Distribution Systems

4.1 Water Piping Materials, Joints, Lead Limits, Under-Slab Rules, & Velocity (UPC 604, 605, 609, 610.12) 4.2 Water Supply Fixture Units & the Sizing Tables (UPC 610.3, 610.4, 610.8, 610.10) 4.3 Water Pressure Limits, Booster Pumps, Potable Water Tanks, & Water Hammer (UPC 607–609) 4.4 Water Valves, Shutoffs, Manifolds, & Hot Water Distribution (UPC 606, 609.11; WA 210.0 and 609.11)

5 Chapter 5: Backflow Prevention & Cross-Connection Control

5.1 Backflow Principles: Backsiphonage, Backpressure, & Degree of Hazard (UPC 602–603; WAC 246-290-490) 5.2 Backflow Assemblies and Devices: RP, DC, PVB, SVB, AVB, & Installation Rules (UPC 603.3, 603.4, Table 603.2) 5.3 Air Gaps, Critical Level, & Specific Backflow Applications (UPC Table 603.3.1, 603.5) 5.4 Backflow Testing, Certified Testers, & Washington's Cross-Connection Program (WA 603.4.2; WAC 246-290-490, 246-292)

6 Chapter 6: Sanitary Drainage Systems & Sizing

6.1 DWV Materials, Joints, & Changes in Direction (UPC 701, 704–706; WA 701.2) 6.2 Drainage Fixture Units, Trap Sizes, & Flow Conversions (UPC Table 702.1, 702.2, 702.3) 6.3 Sizing Drainage Piping with Table 703.2 (Vertical, Horizontal, Water Closet Limits, & WA Note 4) 6.4 Building Drains, Grade, Gravity Drainage, Backwater Valves, & Washington's Deletion of Building Sewer Rules

7 Chapter 7: Cleanouts, Sumps and Ejectors, Indirect Wastes, & Interceptors

7.1 Cleanouts: Location, Spacing, Size, and Clearance (UPC 707 as Amended by Washington) 7.2 Sumps, Sewage Ejectors, Grinder Pumps, & Macerating Systems (UPC 710) 7.3 Indirect Wastes, Air Gaps and Air Breaks, Receptors, Standpipes, & Condensate (UPC Chapter 8) 7.4 Interceptors and Separators: Grease, Sand, Oil, Laundry, & Bottling (UPC 1009–1017)

8 Chapter 8: Vents and Venting Fundamentals

8.1 Venting Fundamentals: Trap Seal Protection, Vent Sizing, the Half-Drain Rule, & Aggregate Venting (UPC 901–904) 8.2 Vent Grades and Connections, Vent Stacks, Relief and Yoke Vents, & Suds Relief (UPC 905, 907, 711) 8.3 Wet Venting and Circuit Venting (UPC 908, 911; WA 908.2.4 and 911.1) 8.4 Island Fixture Venting, Combination Waste and Vent Systems, & Engineered Vent Systems (UPC 909, 910, 912)

9 Chapter 9: Vent Terminations, Traps, & Priming

9.1 Vent Terminations: Roof Height, Clearances, Used Roofs, Outdoor Vents, & Frost Closure (UPC 906) 9.2 Traps, Trap Arms, Table 1002.2 Distances, & Prohibited Traps (UPC 1001–1004) 9.3 How Trap Seals Are Lost & How the Code Protects Them: Venting, Seal Depth, and Trap Seal Primers (UPC 901.3, 1005, 1007)

10 Chapter 10: Alternate Water, Rainwater Catchment, Definitions, & Referenced Standards

10.1 Alternate Water Sources: Reclaimed, Gray, and On-Site Treated Water (UPC Chapter 15 as Amended by Washington) 10.2 Nonpotable Rainwater Catchment Systems (UPC Chapter 16 as Amended by Washington) 10.3 Key UPC Definitions and Referenced Standards (UPC Chapters 2 and 17; WA Definition Amendments)

11 Chapter 11: Part 2 — Waste & Vent Isometric Drawings & Plan Analysis

11.1 Part 2 Explained: Reading the Waste and Vent Drawing 11.2 Part 2 Worked Example: Accumulating DFU and Sizing Every Drain Segment 11.3 Part 2 Worked Example: Sizing Individual, Branch, and Main Vents and Checking Aggregate Venting 11.4 Spotting Code Violations on Waste and Vent Drawings: A Checklist with Code Citations

12 Chapter 12: Part 3 — Water Supply Isometric Drawings & Pipe Sizing

12.1 Part 3 Explained: Reading the Water Sizing Drawing and Gathering the 610.7 Data 12.2 Part 3 Worked Example: Accumulating Water Supply Fixture Units, Cold and Hot 12.3 Part 3: Available Pressure, Elevation, Regulators, Device Losses, and the Length Column 12.4 Part 3 Worked Example: Sizing the Meter, Building Supply, and Every Branch with Table 610.4

13 Chapter 13: Washington Amendments Review, Plumbing Math, & Water Service Special Topics

13.1 Washington's Amendments to the 2015 UPC (WAC 51-56): A Consolidated Review 13.2 Plumbing Math for the Exam: Offsets, Rolling Offsets, Grade, Areas, Volumes, and Pressure 13.3 Water Service Details, Treatment Units, Softeners, & Residential Sprinklers (UPC 604, 609, 611, 612; WA Amendments)

14 Chapter 14: Comprehensive Exam Preparation & Test-Taking Strategy

14.1 The PSI Exam Day: Structure, Fees, Retakes, Rules, and Pacing 14.2 Using the Provided Tables Fast (702.1, 610.3, 610.4, 610.10) and Writing the Missing Ones from Memory 14.3 High-Yield Number Review, Classic Traps, and a Final Readiness Checklist

14.2 Using the Provided Tables Fast (702.1, 610.3, 610.4, 610.10) and Writing the Missing Ones from Memory

Key Takeaways Explain This Topic AI

UPC Table 702.1 lists each fixture's minimum trap and trap arm size and its DFU value in private, public, and assembly columns; its notes set 2-inch minimum drains and 6 DFU per washer in batteries of three or more.

UPC Table 610.3 lists minimum fixture branch sizes and WSFU in private, public, and assembly columns; flushometer valves defer to Table 610.10.

UPC Table 610.4 is read by pressure range, then length column, then down to the first fixture-unit value at least equal to the load, with meter and supply sizes in the two left columns.

UPC Table 610.10 values are cumulative by the number of flushometer valves on a section: 40, 70, 90, 105 for water closets and 20, 35, 45, 53 for urinals.

Table 703.2, Table 1002.2, and the vent area list are not provided and should be written from memory on scratch paper at the start.

Last updated: September 2026

Table 702.1: Drainage Fixture Unit Values

Layout: fixture name, then minimum size trap and trap arm , then DFU columns for private , public , and assembly . Sinks are grouped under a "Sinks" heading. Water closets are split by flush volume (1.6 gpf, or more) and type.

Lookup habits:

Decide the occupancy column before looking up any fixture, and stay in it.

Scan for the right variant . Urinals come in integral-trap 1.0 gpf, integral-trap over 1.0 gpf, and exposed-trap versions. Service sinks come with 2-inch and 3-inch traps and a flushing-rim version.

Dashes mean the fixture is not rated for that occupancy.

Read the notes. Note 2 gives a 2-inch minimum drain for kitchen and laundry sinks, dishwashers, some sinks, and urinals. Note 5: a battery of three or more clothes washers counts 6 DFU each for common piping. Note 1: indirect waste receptors are sized from Table 702.2(2).

Table 610.3: Water Supply Fixture Units

Layout: fixture, then minimum fixture branch pipe size , then WSFU for private , public , and assembly .

Lookup habits:

Flushometer water closets and urinals say "See Footnote 7" , meaning Table 610.10. Do not look for a number in 610.3.

Note 3: listed values are the load on the cold building supply. For separate hot and cold branches, take 3/4 of the listed value on each side.

Note 8: the second and later hose bibbs are 1.0 on shared piping, but each hose bibb branch is sized at 2.5 .

Note 5: continuous flows are added separately in gpm.

Minimum branch sizes are floors: 1 inch for flushometer water closets, 3/4 inch for flushometer urinals and 3/4-inch tub fillers, and 1/2 inch for most others.

Table 610.4: Water Pipe and Meter Sizes

Layout: three stacked groups, 30–45 psi , 46–60 psi , and over 60 psi . Each group has rows for combinations of meter and street service size and building supply and branch size. The length columns run 40 through 1,000 feet. The cells hold the maximum fixture units .

Lookup sequence (610.8):

Adjusted pressure: minimum pressure, minus device losses, minus 1/2 psi per foot to the highest outlet (or 80% of a regulator's setting).

Pick the group (pressure range).

Pick the length column equal to or longer than the developed length.

Read down that column to the first value at least equal to the load. Use a ruler edge or your pencil to keep your place, because the rows are dense.

Read the meter and supply sizes from the left of that row.

Traps: The rows are ordered by combination, so values do not rise steadily down the column. For example, the 1-inch meter with 2-inch supply row holds 85 in many columns, below the rows above it. Read in order and stop at the first adequate value. Building supply is never under 3/4 inch (note 2).

Table 610.10: Flushometer Fixture Units

  • Valves on the section Water closets Urinals
  • 1 40 20
  • 2 70 35
  • 3 90 45
  • 4 105 53
  • 5 or more 115 + 10 each over 5 58 + 5 each over 5

Habit: For each pipe section, count the valves downstream of it (the valves that section serves), look up the cumulative value, and add the other fixtures at their Table 610.3 values.

Tables You Must Carry in Your Head

At the start of each drawing portion, write this template on your scratch paper:

Table 703.2 (drainage):

  • Size 1-1/2 2 3 4
  • Vertical DFU 2 16 48 256
  • Horizontal DFU 1 8 35 216
  • Notes — No water closets 4 WC vertical, 3 WC horizontal 0.8 factor at 1/8 in per ft

Table 703.2 (vents): 1-1/4 = 1 DFU / 45 ft; 1-1/2 = 8 / 60; 2 = 24 / 120; 3 = 84 / 212; 4 = 256 / 300. Individual vent: at least 1-1/4 inches and at least half the drain; no more than one-third horizontal.

Table 1002.2 (trap arm to vent): 1-1/4 = 30 in; 1-1/2 = 42 in; 2 = 60 in; 3 = 72 in; 4 = 120 in; water closet 6 ft from the flange.

Areas: 1-1/4 = 1.23; 1-1/2 = 1.77; 2 = 3.14; 3 = 7.07; 4 = 12.57 square inches.

For Part 1 , add: Table 313.3 hanger spacing (Section 1.4), Table 603.3.1 air gaps (Section 5.3), Table 707.1 cleanouts and Washington's 707.9 clearances (Section 7.1), and Washington's Table 501.1 first hour ratings (Section 3.1).

Practice Drill

Time yourself for each:

From memory, write Table 703.2's drainage and vent rows. The target is under 2 minutes .

On a printed Table 702.1, look up 10 mixed fixtures in the public column. The target is under 90 seconds .

On Table 610.4, answer: 46–60 psi, 150 ft, 97 FU. The answer is a 1-1/2-inch meter and 1-1/2-inch supply (128). Then: over 60 psi, 200 ft, 60 FU. Reading down that column (4, 13, 30, 32, 39, 62), the first adequate row is the 1-inch meter with 1-1/4-inch supply (62) .

Table 610.10: what do 6 flushometer water closets carry? The answer is 115 + 10 = 125 .