12.1 Part 3 Explained: Reading the Water Sizing Drawing and Gathering the 610.7 Data
Washington Journeyman Plumber Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Administration, Licensing, & General Regulations
1.1 Washington Plumber Certification Law: RCW 18.106, WAC 296-400A, Trainees, & Supervision 1.2 Permits, Inspections, Tests, & Disinfection (UPC Chapter 1, 609, 712) 1.3 General Regulations: Prohibited Fittings, Pipe Protection, Nail Plates, Sleeves, & Trenching (UPC Chapter 3) 1.4 Hangers, Supports, Rod Sizes, Dissimilar Metals, & Expansion (UPC 313, Table 313.3)
2 Chapter 2: Plumbing Fixtures, Fittings, & Clearances
2.1 Fixture Setting, Clearances, Closet Flanges, & Water Closets (UPC 402, 411, 413; WA 402.5) 2.2 Showers, Shower Pans, Bathtubs, Lavatories, Bidets, & Scald Limits (UPC 407–410; WA 408) 2.3 Urinals, Floor Drains, Floor Sinks, Sinks, Dishwashers, Disposers, & Special Fixtures (UPC 412–421) 2.4 Minimum Fixture Counts in Washington: IBC Table 2902.1, Not UPC Table 422.1
3 Chapter 3: Water Heaters & Storage Tanks
3.1 Water Heater Permits, Sizing (WA Table 501.1), Bedroom and Bathroom Locations, & Safety Devices 3.2 Temperature and Pressure Relief Valves & Discharge Piping (UPC 504.6, 608; WA 608.3.1 and 608.5) 3.3 Water Heater Installation Details: Garages, Pans, Supports, Attic and Under-Floor Access, & Washington's Mechanical Code Deletions 3.4 Seismic Strapping, Thermal Expansion Tanks, Pressure Regulators, & Temperature Controls (WA 507.2, 608.2, 608.3)
4 Chapter 4: Water Supply and Distribution Systems
4.1 Water Piping Materials, Joints, Lead Limits, Under-Slab Rules, & Velocity (UPC 604, 605, 609, 610.12) 4.2 Water Supply Fixture Units & the Sizing Tables (UPC 610.3, 610.4, 610.8, 610.10) 4.3 Water Pressure Limits, Booster Pumps, Potable Water Tanks, & Water Hammer (UPC 607–609) 4.4 Water Valves, Shutoffs, Manifolds, & Hot Water Distribution (UPC 606, 609.11; WA 210.0 and 609.11)
5 Chapter 5: Backflow Prevention & Cross-Connection Control
5.1 Backflow Principles: Backsiphonage, Backpressure, & Degree of Hazard (UPC 602–603; WAC 246-290-490) 5.2 Backflow Assemblies and Devices: RP, DC, PVB, SVB, AVB, & Installation Rules (UPC 603.3, 603.4, Table 603.2) 5.3 Air Gaps, Critical Level, & Specific Backflow Applications (UPC Table 603.3.1, 603.5) 5.4 Backflow Testing, Certified Testers, & Washington's Cross-Connection Program (WA 603.4.2; WAC 246-290-490, 246-292)
6 Chapter 6: Sanitary Drainage Systems & Sizing
6.1 DWV Materials, Joints, & Changes in Direction (UPC 701, 704–706; WA 701.2) 6.2 Drainage Fixture Units, Trap Sizes, & Flow Conversions (UPC Table 702.1, 702.2, 702.3) 6.3 Sizing Drainage Piping with Table 703.2 (Vertical, Horizontal, Water Closet Limits, & WA Note 4) 6.4 Building Drains, Grade, Gravity Drainage, Backwater Valves, & Washington's Deletion of Building Sewer Rules
7 Chapter 7: Cleanouts, Sumps and Ejectors, Indirect Wastes, & Interceptors
7.1 Cleanouts: Location, Spacing, Size, and Clearance (UPC 707 as Amended by Washington) 7.2 Sumps, Sewage Ejectors, Grinder Pumps, & Macerating Systems (UPC 710) 7.3 Indirect Wastes, Air Gaps and Air Breaks, Receptors, Standpipes, & Condensate (UPC Chapter 8) 7.4 Interceptors and Separators: Grease, Sand, Oil, Laundry, & Bottling (UPC 1009–1017)
8 Chapter 8: Vents and Venting Fundamentals
8.1 Venting Fundamentals: Trap Seal Protection, Vent Sizing, the Half-Drain Rule, & Aggregate Venting (UPC 901–904) 8.2 Vent Grades and Connections, Vent Stacks, Relief and Yoke Vents, & Suds Relief (UPC 905, 907, 711) 8.3 Wet Venting and Circuit Venting (UPC 908, 911; WA 908.2.4 and 911.1) 8.4 Island Fixture Venting, Combination Waste and Vent Systems, & Engineered Vent Systems (UPC 909, 910, 912)
9 Chapter 9: Vent Terminations, Traps, & Priming
9.1 Vent Terminations: Roof Height, Clearances, Used Roofs, Outdoor Vents, & Frost Closure (UPC 906) 9.2 Traps, Trap Arms, Table 1002.2 Distances, & Prohibited Traps (UPC 1001–1004) 9.3 How Trap Seals Are Lost & How the Code Protects Them: Venting, Seal Depth, and Trap Seal Primers (UPC 901.3, 1005, 1007)
10 Chapter 10: Alternate Water, Rainwater Catchment, Definitions, & Referenced Standards
10.1 Alternate Water Sources: Reclaimed, Gray, and On-Site Treated Water (UPC Chapter 15 as Amended by Washington) 10.2 Nonpotable Rainwater Catchment Systems (UPC Chapter 16 as Amended by Washington) 10.3 Key UPC Definitions and Referenced Standards (UPC Chapters 2 and 17; WA Definition Amendments)
11 Chapter 11: Part 2 — Waste & Vent Isometric Drawings & Plan Analysis
11.1 Part 2 Explained: Reading the Waste and Vent Drawing 11.2 Part 2 Worked Example: Accumulating DFU and Sizing Every Drain Segment 11.3 Part 2 Worked Example: Sizing Individual, Branch, and Main Vents and Checking Aggregate Venting 11.4 Spotting Code Violations on Waste and Vent Drawings: A Checklist with Code Citations
12 Chapter 12: Part 3 — Water Supply Isometric Drawings & Pipe Sizing
12.1 Part 3 Explained: Reading the Water Sizing Drawing and Gathering the 610.7 Data 12.2 Part 3 Worked Example: Accumulating Water Supply Fixture Units, Cold and Hot 12.3 Part 3: Available Pressure, Elevation, Regulators, Device Losses, and the Length Column 12.4 Part 3 Worked Example: Sizing the Meter, Building Supply, and Every Branch with Table 610.4
13 Chapter 13: Washington Amendments Review, Plumbing Math, & Water Service Special Topics
13.1 Washington's Amendments to the 2015 UPC (WAC 51-56): A Consolidated Review 13.2 Plumbing Math for the Exam: Offsets, Rolling Offsets, Grade, Areas, Volumes, and Pressure 13.3 Water Service Details, Treatment Units, Softeners, & Residential Sprinklers (UPC 604, 609, 611, 612; WA Amendments)
14 Chapter 14: Comprehensive Exam Preparation & Test-Taking Strategy
14.1 The PSI Exam Day: Structure, Fees, Retakes, Rules, and Pacing 14.2 Using the Provided Tables Fast (702.1, 610.3, 610.4, 610.10) and Writing the Missing Ones from Memory 14.3 High-Yield Number Review, Classic Traps, and a Final Readiness Checklist
12.1 Part 3 Explained: Reading the Water Sizing Drawing and Gathering the 610.7 Data
Key Takeaways Explain This Topic AI
Part 3 of the Washington journey level exam has 25 items in 90 minutes, requires 70 percent, and is closed book (PSI candidate bulletin).
L&I states Part 3 asks for fixture units and pipe sizes for hot and cold distribution, using minimum sizing allowed by the UPC.
UPC 610.7 requires four inputs for Table 610.4 sizing: total fixture units, developed length from the meter to the most remote outlet, elevation difference to the highest outlet, and the minimum street pressure.
Where street pressure fluctuates during the day, the system is designed on the minimum pressure available (UPC 610.7).
No building supply pipe may be smaller than 3/4 inch (UPC 610.8).
Last updated: September 2026
What L&I and PSI Say About Part 3
- Fact Source
- 25 items , 90 minutes , 70% , closed book PSI Washington Plumbing Candidate Information Bulletin
- "A water pipe sizing exercise taken from Chapter 6 of the UPC and amendments" L&I
"A drawing of a building … showing elevated views of plumbing fixtures along with the illustrated piping for the hot and cold-water distribution system " L&I
- "You will provide the fixture units and pipe sizes . Use minimum sizing as allowed by the UPC" L&I
- Tables 610.3, 610.4, and 610.10 are provided (with 702.1 for Part 2) L&I
Washington's 610.4 amendment keeps the choice of sizing from Table 610.4 or by Appendix A (610.5). The exam exercise uses Table 610.4 , the table L&I provides.
What the Drawing Shows
Meter and street service , the building supply entering the building, the water heater , and the cold and hot mains and branches to each fixture.
Line types: typically cold water in one line style and hot in another. Check the legend.
Segment labels (letters or numbers) at each branch point. Questions ask for fixture units or minimum size at a named segment.
Notes giving the street pressure , the elevation of the highest fixture above the meter, the developed length , the occupancy type (private, public, or assembly), and whether water closets are flushometer or tank type.
The Four Facts Section 610.7 Requires
Total fixture units from Table 610.3, with flushometer valves from Table 610.10.
Developed length of supply pipe from the meter to the most remote outlet . Developed length is measured along the centerline of pipe and fittings and includes vertical rises.
Elevation difference between the meter or other source and the highest fixture or outlet .
Street main pressure . Where the pressure fluctuates during the day, design on the minimum pressure available .
Also watch for:
A pressure regulator: size from 80% of its reduced setting (608.2).
Devices with pressure loss: filters, softeners, backflow preventers, and tankless heaters. Section 610.2 requires their losses to be included in the pressure calculation.
Continuous demands such as irrigation or process equipment: add them separately in gpm (Table 610.3 note 5).
A Worksheet Before Any Lookup
Build one line per segment. Record which fixtures it serves, whether it is cold, hot, or both, its fixture units, and its size. Then fill in the one-time values: available pressure, pressure range, and length column.
- Item Value in the Section 12.2 through 12.4 example
- Minimum street pressure at the meter 62 psi
- Highest outlet above the meter 8 feet
- Developed length, meter to most remote outlet 140 feet
- Occupancy Public (office)
- Water closets and urinal Flushometer valves
- Water heater Storage type, serving lavatories and sinks
- The Example Building (Used Through Section 12.4)
A one-story office has:
- 2 flushometer water closets (1.6 gpf)
- 1 flushometer urinal (1.0 gpf)
- 2 lavatories (public)
- 1 service (mop) sink (public)
- 1 kitchen sink in a break room (domestic-type sink)
- 1 drinking fountain
- 1 hose bibb
- 1 storage water heater supplying hot water to the lavatories and sinks
The cold main runs from the meter to the water heater tee, then to the restroom, where it splits to the flushometer branch and the lavatory, sink, and fountain branch. The hot main leaves the water heater for the restroom lavatories, the mop sink, and the break-room sink.
How Part 3 Questions Are Usually Phrased
Expect the same handful of question forms, each tied to a segment label on the drawing:
- "How many water supply fixture units are carried by segment ___?" (Section 12.2)
- "What is the minimum size of segment ___?" (Section 12.4)
- "What size meter and building supply are required?" (Section 12.4)
- "Which pressure range and length column of Table 610.4 apply?" (Section 12.3)
- "What is the minimum size of the branch to the flushometer valve ?" (Tables 610.3 and 610.10)
Because every size depends on the same pressure range and length column, a mistake in the first lookup repeats in every later answer. Settle those two values first and write them at the top of your scratch paper.
Abbreviations and Symbols to Recognize
- Mark Meaning
- CW / HW Cold water / hot water
- WM or M Water meter
- WH Water heater
- FV or FLV Flushometer valve
- HB Hose bibb
- PRV Pressure-reducing valve (use 80% of its setting)
- BFP, RP, or DC Backflow preventer (its pressure loss counts under 610.2)
- Elevation marks Heights above the meter or finished floor, used for the 1/2 psi per foot adjustment
- Reading Traps to Avoid
Developed length is not straight-line distance. Add every horizontal run and vertical rise from the meter to the most remote outlet.
"Most remote" means farthest by developed length , which is not always the highest fixture. Elevation uses the highest outlet. The two can be different fixtures.
Use the minimum pressure if the drawing gives a range such as "55 to 70 psi."
Minimum building supply is 3/4 inch even if the table would allow 1/2 inch (610.8).