Study guide

8.2 Vent Grades and Connections, Vent Stacks, Relief and Yoke Vents, & Suds Relief (UPC 905, 907, 711)

Washington Journeyman Plumber Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Administration, Licensing, & General Regulations

1.1 Washington Plumber Certification Law: RCW 18.106, WAC 296-400A, Trainees, & Supervision 1.2 Permits, Inspections, Tests, & Disinfection (UPC Chapter 1, 609, 712) 1.3 General Regulations: Prohibited Fittings, Pipe Protection, Nail Plates, Sleeves, & Trenching (UPC Chapter 3) 1.4 Hangers, Supports, Rod Sizes, Dissimilar Metals, & Expansion (UPC 313, Table 313.3)

2 Chapter 2: Plumbing Fixtures, Fittings, & Clearances

2.1 Fixture Setting, Clearances, Closet Flanges, & Water Closets (UPC 402, 411, 413; WA 402.5) 2.2 Showers, Shower Pans, Bathtubs, Lavatories, Bidets, & Scald Limits (UPC 407–410; WA 408) 2.3 Urinals, Floor Drains, Floor Sinks, Sinks, Dishwashers, Disposers, & Special Fixtures (UPC 412–421) 2.4 Minimum Fixture Counts in Washington: IBC Table 2902.1, Not UPC Table 422.1

3 Chapter 3: Water Heaters & Storage Tanks

3.1 Water Heater Permits, Sizing (WA Table 501.1), Bedroom and Bathroom Locations, & Safety Devices 3.2 Temperature and Pressure Relief Valves & Discharge Piping (UPC 504.6, 608; WA 608.3.1 and 608.5) 3.3 Water Heater Installation Details: Garages, Pans, Supports, Attic and Under-Floor Access, & Washington's Mechanical Code Deletions 3.4 Seismic Strapping, Thermal Expansion Tanks, Pressure Regulators, & Temperature Controls (WA 507.2, 608.2, 608.3)

4 Chapter 4: Water Supply and Distribution Systems

4.1 Water Piping Materials, Joints, Lead Limits, Under-Slab Rules, & Velocity (UPC 604, 605, 609, 610.12) 4.2 Water Supply Fixture Units & the Sizing Tables (UPC 610.3, 610.4, 610.8, 610.10) 4.3 Water Pressure Limits, Booster Pumps, Potable Water Tanks, & Water Hammer (UPC 607–609) 4.4 Water Valves, Shutoffs, Manifolds, & Hot Water Distribution (UPC 606, 609.11; WA 210.0 and 609.11)

5 Chapter 5: Backflow Prevention & Cross-Connection Control

5.1 Backflow Principles: Backsiphonage, Backpressure, & Degree of Hazard (UPC 602–603; WAC 246-290-490) 5.2 Backflow Assemblies and Devices: RP, DC, PVB, SVB, AVB, & Installation Rules (UPC 603.3, 603.4, Table 603.2) 5.3 Air Gaps, Critical Level, & Specific Backflow Applications (UPC Table 603.3.1, 603.5) 5.4 Backflow Testing, Certified Testers, & Washington's Cross-Connection Program (WA 603.4.2; WAC 246-290-490, 246-292)

6 Chapter 6: Sanitary Drainage Systems & Sizing

6.1 DWV Materials, Joints, & Changes in Direction (UPC 701, 704–706; WA 701.2) 6.2 Drainage Fixture Units, Trap Sizes, & Flow Conversions (UPC Table 702.1, 702.2, 702.3) 6.3 Sizing Drainage Piping with Table 703.2 (Vertical, Horizontal, Water Closet Limits, & WA Note 4) 6.4 Building Drains, Grade, Gravity Drainage, Backwater Valves, & Washington's Deletion of Building Sewer Rules

7 Chapter 7: Cleanouts, Sumps and Ejectors, Indirect Wastes, & Interceptors

7.1 Cleanouts: Location, Spacing, Size, and Clearance (UPC 707 as Amended by Washington) 7.2 Sumps, Sewage Ejectors, Grinder Pumps, & Macerating Systems (UPC 710) 7.3 Indirect Wastes, Air Gaps and Air Breaks, Receptors, Standpipes, & Condensate (UPC Chapter 8) 7.4 Interceptors and Separators: Grease, Sand, Oil, Laundry, & Bottling (UPC 1009–1017)

8 Chapter 8: Vents and Venting Fundamentals

8.1 Venting Fundamentals: Trap Seal Protection, Vent Sizing, the Half-Drain Rule, & Aggregate Venting (UPC 901–904) 8.2 Vent Grades and Connections, Vent Stacks, Relief and Yoke Vents, & Suds Relief (UPC 905, 907, 711) 8.3 Wet Venting and Circuit Venting (UPC 908, 911; WA 908.2.4 and 911.1) 8.4 Island Fixture Venting, Combination Waste and Vent Systems, & Engineered Vent Systems (UPC 909, 910, 912)

9 Chapter 9: Vent Terminations, Traps, & Priming

9.1 Vent Terminations: Roof Height, Clearances, Used Roofs, Outdoor Vents, & Frost Closure (UPC 906) 9.2 Traps, Trap Arms, Table 1002.2 Distances, & Prohibited Traps (UPC 1001–1004) 9.3 How Trap Seals Are Lost & How the Code Protects Them: Venting, Seal Depth, and Trap Seal Primers (UPC 901.3, 1005, 1007)

10 Chapter 10: Alternate Water, Rainwater Catchment, Definitions, & Referenced Standards

10.1 Alternate Water Sources: Reclaimed, Gray, and On-Site Treated Water (UPC Chapter 15 as Amended by Washington) 10.2 Nonpotable Rainwater Catchment Systems (UPC Chapter 16 as Amended by Washington) 10.3 Key UPC Definitions and Referenced Standards (UPC Chapters 2 and 17; WA Definition Amendments)

11 Chapter 11: Part 2 — Waste & Vent Isometric Drawings & Plan Analysis

11.1 Part 2 Explained: Reading the Waste and Vent Drawing 11.2 Part 2 Worked Example: Accumulating DFU and Sizing Every Drain Segment 11.3 Part 2 Worked Example: Sizing Individual, Branch, and Main Vents and Checking Aggregate Venting 11.4 Spotting Code Violations on Waste and Vent Drawings: A Checklist with Code Citations

12 Chapter 12: Part 3 — Water Supply Isometric Drawings & Pipe Sizing

12.1 Part 3 Explained: Reading the Water Sizing Drawing and Gathering the 610.7 Data 12.2 Part 3 Worked Example: Accumulating Water Supply Fixture Units, Cold and Hot 12.3 Part 3: Available Pressure, Elevation, Regulators, Device Losses, and the Length Column 12.4 Part 3 Worked Example: Sizing the Meter, Building Supply, and Every Branch with Table 610.4

13 Chapter 13: Washington Amendments Review, Plumbing Math, & Water Service Special Topics

13.1 Washington's Amendments to the 2015 UPC (WAC 51-56): A Consolidated Review 13.2 Plumbing Math for the Exam: Offsets, Rolling Offsets, Grade, Areas, Volumes, and Pressure 13.3 Water Service Details, Treatment Units, Softeners, & Residential Sprinklers (UPC 604, 609, 611, 612; WA Amendments)

14 Chapter 14: Comprehensive Exam Preparation & Test-Taking Strategy

14.1 The PSI Exam Day: Structure, Fees, Retakes, Rules, and Pacing 14.2 Using the Provided Tables Fast (702.1, 610.3, 610.4, 610.10) and Writing the Missing Ones from Memory 14.3 High-Yield Number Review, Classic Traps, and a Final Readiness Checklist

8.2 Vent Grades and Connections, Vent Stacks, Relief and Yoke Vents, & Suds Relief (UPC 905, 907, 711)

Key Takeaways Explain This Topic AI

Where a vent connects to a horizontal drain, its invert must be taken off above the drain's centerline, downstream of the trap it serves (UPC 905.2).

Each vent must rise at least 6 inches above the flood-level rim of the fixture served before offsetting horizontally or joining another vent (UPC 905.3).

Except for water closets and similar fixtures, the vent opening may not be below the weir of the trap (UPC 905.5).

A drainage stack of 10 or more stories needs a parallel vent stack with a yoke vent at every fifth floor, connected at least 42 inches above the floor (UPC 907.1, 907.2).

No drain may connect within 8 feet of the base of a stack carrying suds-producing fixtures, and parallel vent stacks connect 8 feet above the stack's lowest point (UPC 711.1).

Last updated: September 2026

Vent Grades and Connections (UPC 905)

Section Rule Why

905.1 Grade Vents have no drops or sags. They are level, or graded to drip back by gravity to the drain they serve Condensation and rain drain back out of the vent

905.2 Horizontal drains Where a vent connects to a horizontal drain, take the vent's invert off above the drain's centerline , downstream of the trap served Waste does not flow into and clog the vent

905.3 Vent rise Unless structure prevents it, each vent rises vertically at least 6 inches above the flood-level rim of the fixture served before offsetting horizontally. Where vents converge, each rises 6 inches above its own fixture's rim before joining. Vent piping lower than that must use drainage fittings, material, and grade If a drain stops, the fixture overflows before waste can back into the horizontal vent

905.4 Roof termination Vents extend undiminished in size above the roof, or reconnect to a soil or waste vent of proper size Full air flow

905.5 Opening location Except for water closets and similar fixtures, the vent opening from a soil or waste pipe may not be below the trap weir A vent below the weir acts as a siphon (a "crown vent" effect)

905.6 Common vertical pipe Two fixtures may share a common vertical pipe when each wastes separately into an approved double fitting with inlets at the same level Back-to-back lavatories or sinks

Kinds of Vents in Practice

Individual vent: one trap, connecting to the vent system above the fixture. It is at least 1-1/4 inches and at least half the drain size (904.1).

Common vent: two fixtures on one vent through a double fitting (905.6).

Branch vent: collects individual vents and runs to a vent stack or stack vent. It is sized by total DFU and length (Table 703.2).

Stack vent: the extension of a soil or waste stack above its highest horizontal drain.

Vent stack: a separate vertical vent run alongside a drainage stack. It connects at or below the lowest fixture drain and extends undiminished to the roof or back to the stack vent above the highest fixture.

Relief vent: relieves pressure on a stack or horizontal branch. Examples include the relief vent required for circuit venting (911.4, Section 8.3) and the yoke vent below.

Vent Stacks and Yoke Vents for Tall Buildings (UPC 907)

907.1: Each drainage stack extending 10 or more stories needs a parallel vent stack . It extends undiminished from its upper terminal and connects to the drainage stack at or immediately below the lowest fixture drain .

The vent stack also connects to the drainage stack at each fifth floor, counting down from the uppermost fixture drain , through a yoke vent . The yoke vent may not be smaller than the drainage stack or the vent stack, whichever is smaller.

907.2: The yoke vent connects to the vent stack at least 42 inches above the floor . It connects to the drainage stack through a wye branch below the lowest drainage branch connection on that floor.

Why every fifth floor? Water falling down a tall stack reaches a terminal velocity and pushes an air column ahead of it. The yoke vent gives that air a path so it does not blow trap seals on lower floors.

Suds Relief (UPC 711.1)

Suds from washers, tubs, and sinks stack up at the base of a drainage stack where it turns horizontal. There they create positive pressure that can push suds out of lower fixtures.

No drainage connection may be made within 8 feet of a vertical-to-horizontal change of direction of a stack containing suds-producing fixtures . Those fixtures are bathtubs, laundries, washing machine standpipes, kitchen sinks, and dishwashers .

Where parallel vent stacks are required, they connect to the drainage stack 8 feet above its lowest point .

Exceptions: single-family residences, and stacks receiving discharge from fewer than three stories of fixtures.

Worked Example: Venting a Two-Story Commercial Restroom Stack

Each floor has 2 water closets, 2 lavatories, and 1 integral-trap urinal, all public. The stack carries 4 water closets and 24 DFU in total. That is within the 3-inch vertical limits (48 DFU, four water closets), so the stack may be 3 inches . The horizontal building drain below it carries four water closets, and note 4 allows only three on a 3-inch horizontal, so the building drain must be 4 inches .

Individual vents: Water closets on 3-inch fixture drains need at least 1-1/2-inch vents (half of 3 inches). Lavatories on 1-1/4-inch trap arms need at least 1-1/4 inches . Urinals on 2-inch trap arms need at least 1-1/4 inches , because half of 2 is 1, which is below the 1-1/4 floor.

Branch vent per floor: total DFU per floor is 2 × 4 + 2 × 1 + 2 = 12 DFU . A 1-1/2-inch vent allows only 8 DFU, so use 2 inches (24 DFU), assuming the developed length is under 120 feet.

Rise: each vent rises 6 inches above its fixture's flood-level rim before turning horizontal (905.3).

Stack vent: it carries 24 DFU , and Table 703.2 allows a 2-inch vent up to 24 DFU within 120 feet. It must extend undiminished through the roof (905.4).

Aggregate venting (904.1): the required building drain is 4 inches (12.57 square inches). If the stack vent is the only roof terminal, a 2-inch stack vent (3.14 square inches) fails, so upsize it to 4 inches , or add vents until the total area reaches at least 12.57 square inches.

Yoke vents: not required, because the stack is under 10 stories.