Study guide
4.1 Water Piping Materials, Joints, Lead Limits, Under-Slab Rules, & Velocity (UPC 604, 605, 609, 610.12)
Washington Journeyman Plumber Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Administration, Licensing, & General Regulations
1.1 Washington Plumber Certification Law: RCW 18.106, WAC 296-400A, Trainees, & Supervision 1.2 Permits, Inspections, Tests, & Disinfection (UPC Chapter 1, 609, 712) 1.3 General Regulations: Prohibited Fittings, Pipe Protection, Nail Plates, Sleeves, & Trenching (UPC Chapter 3) 1.4 Hangers, Supports, Rod Sizes, Dissimilar Metals, & Expansion (UPC 313, Table 313.3)
2 Chapter 2: Plumbing Fixtures, Fittings, & Clearances
2.1 Fixture Setting, Clearances, Closet Flanges, & Water Closets (UPC 402, 411, 413; WA 402.5) 2.2 Showers, Shower Pans, Bathtubs, Lavatories, Bidets, & Scald Limits (UPC 407–410; WA 408) 2.3 Urinals, Floor Drains, Floor Sinks, Sinks, Dishwashers, Disposers, & Special Fixtures (UPC 412–421) 2.4 Minimum Fixture Counts in Washington: IBC Table 2902.1, Not UPC Table 422.1
3 Chapter 3: Water Heaters & Storage Tanks
3.1 Water Heater Permits, Sizing (WA Table 501.1), Bedroom and Bathroom Locations, & Safety Devices 3.2 Temperature and Pressure Relief Valves & Discharge Piping (UPC 504.6, 608; WA 608.3.1 and 608.5) 3.3 Water Heater Installation Details: Garages, Pans, Supports, Attic and Under-Floor Access, & Washington's Mechanical Code Deletions 3.4 Seismic Strapping, Thermal Expansion Tanks, Pressure Regulators, & Temperature Controls (WA 507.2, 608.2, 608.3)
4 Chapter 4: Water Supply and Distribution Systems
4.1 Water Piping Materials, Joints, Lead Limits, Under-Slab Rules, & Velocity (UPC 604, 605, 609, 610.12) 4.2 Water Supply Fixture Units & the Sizing Tables (UPC 610.3, 610.4, 610.8, 610.10) 4.3 Water Pressure Limits, Booster Pumps, Potable Water Tanks, & Water Hammer (UPC 607–609) 4.4 Water Valves, Shutoffs, Manifolds, & Hot Water Distribution (UPC 606, 609.11; WA 210.0 and 609.11)
5 Chapter 5: Backflow Prevention & Cross-Connection Control
5.1 Backflow Principles: Backsiphonage, Backpressure, & Degree of Hazard (UPC 602–603; WAC 246-290-490) 5.2 Backflow Assemblies and Devices: RP, DC, PVB, SVB, AVB, & Installation Rules (UPC 603.3, 603.4, Table 603.2) 5.3 Air Gaps, Critical Level, & Specific Backflow Applications (UPC Table 603.3.1, 603.5) 5.4 Backflow Testing, Certified Testers, & Washington's Cross-Connection Program (WA 603.4.2; WAC 246-290-490, 246-292)
6 Chapter 6: Sanitary Drainage Systems & Sizing
6.1 DWV Materials, Joints, & Changes in Direction (UPC 701, 704–706; WA 701.2) 6.2 Drainage Fixture Units, Trap Sizes, & Flow Conversions (UPC Table 702.1, 702.2, 702.3) 6.3 Sizing Drainage Piping with Table 703.2 (Vertical, Horizontal, Water Closet Limits, & WA Note 4) 6.4 Building Drains, Grade, Gravity Drainage, Backwater Valves, & Washington's Deletion of Building Sewer Rules
7 Chapter 7: Cleanouts, Sumps and Ejectors, Indirect Wastes, & Interceptors
7.1 Cleanouts: Location, Spacing, Size, and Clearance (UPC 707 as Amended by Washington) 7.2 Sumps, Sewage Ejectors, Grinder Pumps, & Macerating Systems (UPC 710) 7.3 Indirect Wastes, Air Gaps and Air Breaks, Receptors, Standpipes, & Condensate (UPC Chapter 8) 7.4 Interceptors and Separators: Grease, Sand, Oil, Laundry, & Bottling (UPC 1009–1017)
8 Chapter 8: Vents and Venting Fundamentals
8.1 Venting Fundamentals: Trap Seal Protection, Vent Sizing, the Half-Drain Rule, & Aggregate Venting (UPC 901–904) 8.2 Vent Grades and Connections, Vent Stacks, Relief and Yoke Vents, & Suds Relief (UPC 905, 907, 711) 8.3 Wet Venting and Circuit Venting (UPC 908, 911; WA 908.2.4 and 911.1) 8.4 Island Fixture Venting, Combination Waste and Vent Systems, & Engineered Vent Systems (UPC 909, 910, 912)
9 Chapter 9: Vent Terminations, Traps, & Priming
9.1 Vent Terminations: Roof Height, Clearances, Used Roofs, Outdoor Vents, & Frost Closure (UPC 906) 9.2 Traps, Trap Arms, Table 1002.2 Distances, & Prohibited Traps (UPC 1001–1004) 9.3 How Trap Seals Are Lost & How the Code Protects Them: Venting, Seal Depth, and Trap Seal Primers (UPC 901.3, 1005, 1007)
10 Chapter 10: Alternate Water, Rainwater Catchment, Definitions, & Referenced Standards
10.1 Alternate Water Sources: Reclaimed, Gray, and On-Site Treated Water (UPC Chapter 15 as Amended by Washington) 10.2 Nonpotable Rainwater Catchment Systems (UPC Chapter 16 as Amended by Washington) 10.3 Key UPC Definitions and Referenced Standards (UPC Chapters 2 and 17; WA Definition Amendments)
11 Chapter 11: Part 2 — Waste & Vent Isometric Drawings & Plan Analysis
11.1 Part 2 Explained: Reading the Waste and Vent Drawing 11.2 Part 2 Worked Example: Accumulating DFU and Sizing Every Drain Segment 11.3 Part 2 Worked Example: Sizing Individual, Branch, and Main Vents and Checking Aggregate Venting 11.4 Spotting Code Violations on Waste and Vent Drawings: A Checklist with Code Citations
12 Chapter 12: Part 3 — Water Supply Isometric Drawings & Pipe Sizing
12.1 Part 3 Explained: Reading the Water Sizing Drawing and Gathering the 610.7 Data 12.2 Part 3 Worked Example: Accumulating Water Supply Fixture Units, Cold and Hot 12.3 Part 3: Available Pressure, Elevation, Regulators, Device Losses, and the Length Column 12.4 Part 3 Worked Example: Sizing the Meter, Building Supply, and Every Branch with Table 610.4
13 Chapter 13: Washington Amendments Review, Plumbing Math, & Water Service Special Topics
13.1 Washington's Amendments to the 2015 UPC (WAC 51-56): A Consolidated Review 13.2 Plumbing Math for the Exam: Offsets, Rolling Offsets, Grade, Areas, Volumes, and Pressure 13.3 Water Service Details, Treatment Units, Softeners, & Residential Sprinklers (UPC 604, 609, 611, 612; WA Amendments)
14 Chapter 14: Comprehensive Exam Preparation & Test-Taking Strategy
14.1 The PSI Exam Day: Structure, Fees, Retakes, Rules, and Pacing 14.2 Using the Provided Tables Fast (702.1, 610.3, 610.4, 610.10) and Writing the Missing Ones from Memory 14.3 High-Yield Number Review, Classic Traps, and a Final Readiness Checklist
4.1 Water Piping Materials, Joints, Lead Limits, Under-Slab Rules, & Velocity (UPC 604, 605, 609, 610.12)
Key Takeaways Explain This Topic AI
Wetted surfaces of pipes, fittings, and fixtures carrying drinking water may contain no more than a 0.25 percent weighted average of lead; solder and flux no more than 0.2 percent (UPC 604.2).
Copper water tube must weigh at least Type L; Type M is permitted aboveground in or on a building or underground outside of structures (UPC 604.3).
Under a slab within a building, copper tube is installed without joints where possible, and any joints are brazed with wrought copper fittings (UPC 609.3).
Velocities in copper and copper-alloy tube systems may not exceed 8 feet per second cold and 5 feet per second hot (UPC 610.12.1).
PEX, PEX-AL-PEX, PE-AL-PE, and PE-RT may not be installed within the first 18 inches of piping connected to a water heater (UPC 604.13).
Last updated: September 2026
Materials Standards (UPC 604)
604.1: Pipe, tube, fittings, solvent cements, thread sealants, solder, and flux used in systems supplying drinking water must meet NSF 61 . Copper-alloy fittings with more than 15% zinc used in plastic piping systems must resist dezincification (NSF 14). Materials in one system should be alike unless the AHJ approves otherwise.
604.2 Lead: Wetted surfaces of pipe, fittings, fixture fittings, and fixtures carrying drinking water may contain no more than a 0.25% weighted average of lead. Solder and flux may contain no more than 0.2% lead. Non-drinking-water applications may use up to 8% (604.2.1).
604.8: Piping previously used for anything other than potable water may not be reused.
604.6 and 604.7: Cast-iron fittings up to and including 2 inches, and malleable iron fittings, used with potable water piping must be galvanized .
Copper Tube Types (UPC 604.3 and 604.4)
- Type Stripe on hard-drawn tube Where the UPC allows it for water
- K Green Anywhere, including under slabs and underground
- L Blue The UPC minimum weight for water piping; anywhere
- M Red Only aboveground in or on a building, or underground outside of structures
- DWV Yellow Drainage and vent only; not water supply
Exam trap: Type M is not banned from all underground work. The UPC allows it underground outside structures. It may not be used under a slab within the building foundation, where the rules of 609.3 apply.
Joining Methods (UPC 605)
- Joint Key requirements
- Soldered (605.1.4) ASTM B828 sequence; cut square, ream, clean bright; ASTM B813 flux; solder meeting 604.2
- Brazed (605.1.1) Filler with a liquidus above 1,000°F ; joint surfaces cleaned bright
- Flared (605.1.2) Soft copper only; cut square, ream, and flare with a proper tool
Pressed (605.1.3.2) Elastomeric O-ring; tube fully inserted and marked at the fitting shoulder ; pressed with the manufacturer's tool
- Push fit (605.1.3.3) ASSE 1061 ; cut square, chamfer, ream, insert fully, and check against the insertion mark
- Threaded copper-alloy (605.1.5) ASME B1.20.1 threads; sealant on male threads only
CPVC solvent cement (605.2.2) Orange ASTM F493 cement with ASTM F656 primer; listed one-step yellow or red cement allowed for ASTM D2846 pipe 1/2 through 2 inches
PVC solvent cement (605.12.2) Purple ASTM F656 primer, ASTM D2564 cement; hold the joint 1 minute
Threaded plastic (605.2.3, 605.12.3) Only Schedule 80 or heavier may be threaded, and the pressure rating drops 50%
- Mechanically formed tees (605.1.3.1) Collar height at least 3 times the branch wall thickness; brazed
- Slip joints (605.14) Water piping: only on the exposed fixture supply
PEX joints follow the manufacturer's instructions with fittings marked on the tubing (605.9). PE heat-fusion joints use butt, socket, or electrofusion (605.6.1).
Connectors (UPC 604.5, 604.12, 604.13)
Flexible water connectors must be readily accessible . Those under continuous pressure must meet ASME A112.18.6/CSA B125.6.
Flexible corrugated copper, copper-alloy, or stainless connectors are limited to 30 inches for fixtures, 72 inches for washing machines, and 120 inches for dishwashers and ice makers.
Metallic water heater connectors may not exceed 24 inches . PEX, PEX-AL-PEX, PE-AL-PE, and PE-RT may not be installed within the first 18 inches of piping connected to a water heater.
Underground and Under-Slab Water Piping (UPC 609.1–609.3)
609.1: Building supply yard piping must be at least 12 inches below the average local frost depth , with at least 12 inches of cover below finish grade. Copper tube may be bent only with equipment that does not deform or reduce its cross-section.
609.2 Common trench: Water pipe may share a trench with a clay sewer, or a sewer of material not approved inside buildings, only if the bottom of the water pipe is at least 12 inches above the top of the sewer and the water pipe sits on a solid shelf at least 12 inches horizontally from the sewer. Water pipe crossing such a sewer must be at least 12 inches above it.
609.3 Under a slab within a building: Ferrous pipe needs a machine-applied protective coating; galvanizing alone is not adequate. Copper tube is installed without joints where possible . Where joints are allowed, they must be brazed , with wrought copper fittings. "Within a building" means within the fixed limits of the foundation.
Velocity Limits (UPC 610.12)
Section 610.1 requires water systems to be designed so the code's maximum velocities are not exceeded:
- System Maximum velocity
- Copper and copper-alloy tube and fittings, cold water (610.12.1) 8 ft/s
- Copper and copper-alloy tube and fittings, hot water (610.12.1) 5 ft/s
- Copper fittings used in tubing of other materials (610.12.2) 8 ft/s cold, 5 ft/s hot
High velocity erodes copper, especially at elbows and tees on the hot side, and it makes noise. Table 610.4 and Appendix A sizing are built to keep velocities within these limits.