Study guide

5.3 Main Bonding Jumpers & Supply-Side Bonding

Wisconsin Journeyman Electrician Study Guide Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Wisconsin Administrative Rules, Licensing & Electrical Safety

1.1 Wisconsin Journeyman Licensing, Eligibility & Scope 1.2 Current SPS 316 Adoption, Enforcement & Wisconsin Amendments 1.3 Supplemental Job Safety: Shock, Arc-Flash & Work Practices 1.4 Electrical Theory & Mathematical Fundamentals

2 Chapter 2: General Code Rules, Definitions & Enclosure Sizing

2.1 NEC Article 100 Definitions & Article 110 General Installation Requirements 2.2 Conductor Sizing, Ampacity Ratings & Temperature Limitations 2.3 Conductor Ampacity Correction & Adjustment Calculations 2.4 Outlet Box, Device Box & Conduit Body Sizing

3 Chapter 3: Branch Circuits, Feeders & Calculations

3.1 Branch Circuit Ratings, Multiwire Circuits & General Receptacle Outlets 3.2 Wisconsin GFCI & AFCI Protection: NEC 2017-to-2023 Transition 3.3 Dwelling Branch Circuits, Receptacle Spacing & Wisconsin Countertop Rules 3.4 Feeder Sizing, Overcurrent Protection & Voltage Drop

4 Chapter 4: Services & Dwelling Load Calculations

4.1 Dwelling Unit Load Calculations: Standard Method 4.2 Dwelling Unit Load Calculations: Optional Method 4.3 Service Conductors, Disconnects & Current SPS 316.230 Amendments

5 Chapter 5: Grounding and Bonding

5.1 Grounding & Bonding Principles, Systems & Definitions 5.2 Grounding Electrode Systems & GEC Sizing 5.3 Main Bonding Jumpers & Supply-Side Bonding 5.4 Equipment Grounding Conductors & Enclosure Bonding

6 Chapter 6: Wiring Methods, Raceways & Cable Assemblies

6.1 General Wiring Rules & Underground Installations 6.2 Cable Assemblies: NM, NMC, MC, and AC 6.3 Raceways, Conduit Bending & Support Requirements 6.4 Conduit Fill Calculations & Pull Box Sizing

7 Chapter 7: Equipment for General Use: Motors, Generators & Transformers

7.1 Motor Branch Circuit Sizing & Full-Load Currents 7.2 Motor Branch-Circuit Short-Circuit & Overload Protection 7.3 Transformers & Overcurrent Protection

8 Chapter 8: General Loads & Utilization Equipment

8.1 General & Non-Dwelling Load Calculations 8.2 Luminaires, Lighting Systems & Electric Signs 8.3 Appliances, Fixed Electric Space Heating & Water Heating 8.4 Air-Conditioning & Refrigeration Equipment

9 Chapter 9: Special Occupancies & Emergency Systems

9.1 Hazardous (Classified) Locations & Commercial Applications 9.2 Health Care Facilities & Essential Electrical Systems 9.3 Pools, Spas, Hot Tubs & Fountains 9.4 Emergency Systems, Standby Power & Generators

10 Chapter 10: Modern Energy & Low-Voltage Systems

10.1 EV Charging, Photovoltaics, Energy Storage & Interconnections 10.2 Fire Alarm, Signaling & Communications Systems

11 Chapter 11: Exam Logistics & Success

11.1 Exam Logistics, Authorized References & 2026 Code Transition 11.2 Code Navigation, Time Management & Formula Review

5.3 Main Bonding Jumpers & Supply-Side Bonding

Key Takeaways Explain This Topic AI

The Main Bonding Jumper (MBJ) connects the grounded service conductor (neutral) to the service disconnect enclosure (NEC 250.28), completing the circuit necessary for ground-fault current to return to the utility transformer.

Sizing of MBJs, System Bonding Jumpers (SBJs), and Supply-Side Bonding Jumpers (SSBJs) is governed by NEC Table 250.102(C)(1); when ungrounded phase conductors exceed 1,100 kcmil copper (or 1,750 kcmil aluminum), the jumper must have an area not less than 12.5% of the largest ungrounded phase conductor area.

Separately derived systems (transformers, generators) require a System Bonding Jumper (SBJ) under NEC 250.30 installed at the source or first system disconnect, but never at both locations.

Standard locknuts and bushings are strictly prohibited for bonding service raceways (NEC 250.92); service bonding requires threaded bosses, threadless fittings made up tight, bonding bushings with jumpers, or listed bonding wedges.

NEC 250.94 mandates an Intersystem Bonding Termination (IBT) located external to enclosures at the service equipment with a minimum of three terminal connection points for communications, network, and CATV bonding.

Last updated: September 2026

5.3 Main Bonding Jumpers & Supply-Side Bonding

Ahead of the main service overcurrent protective device, electrical conductors and metal enclosures exist in a uniquely hazardous environment: there is no branch-circuit or feeder circuit breaker to trip if an ungrounded phase wire faults to a metal conduit or cabinet. The only upstream protection is the electric utility company's primary distribution fuses, which are engineered to protect utility transformers—not building wiring.

Under line-to-case fault conditions on the supply side, tens of thousands of amperes can flow. If bonding connections are inadequate, the metal enclosure will arc violently, weld shut, or burst into flame. To prevent this, NEC Article 250 Part V and Part VIII mandate rigorous supply-side bonding protocols, including the Main Bonding Jumper (MBJ) , Supply-Side Bonding Jumpers (SSBJ) , and specialized service raceway bonding fittings.

1. The Main Bonding Jumper (MBJ) - NEC 250.28

The Main Bonding Jumper is the single most critical conductor in any electrical service: Utility Transformer Secondary (Grounded Neutral)

  • |
  • v (Service Neutral Conductor)
  • Service Disconnecting Means Enclosure
  • |

[MAIN BONDING JUMPER (MBJ)] <---- NEC 250.28 establishes the bridge!

  • |
  • v
  • Service Equipment Metal Enclosure & Equipment Grounding Bus (EGCs)

Purpose: Connects the equipment grounding conductors and the service-disconnect enclosure to the grounded service conductor (neutral). Without the MBJ, a phase-to-ground fault occurring on any branch circuit or feeder downstream could not return to the utility transformer winding to trip its circuit breaker.

Permitted Construction Types (NEC 250.28(A)): May be a wire, busbar, screw, or similar suitable conductor.

Green Screw Identification (NEC 250.28(B)): Where a main bonding jumper is a screw, the screw must be manufactured with a green finish that is clearly visible after installation, allowing electrical inspectors to verify that the bond is properly seated.

Location Mandate: Must be installed inside the service disconnecting means enclosure (NEC 250.24(B) & 250.28). It is strictly prohibited downstream in panelboards or subpanels.

2. Sizing MBJs & Supply-Side Jumpers (NEC Table 250.102(C)(1))

In prior code editions, supply-side jumpers were sized using Table 250.66. Today, the NEC isolates all supply-side bonding sizing into a dedicated table: NEC Table 250.102(C)(1) ( Grounded Conductor, Main Bonding Jumper, System Bonding Jumper, and Supply-Side Bonding Jumper for Alternating-Current Systems ).

Table 250.102(C)(1) Conductor Sizing

Size of Largest Ungrounded Service Conductor or Equivalent Parallel Area (Copper) Size of Largest Ungrounded Service Conductor (Aluminum or Copper-Clad Al) Size of Minimum MBJ, SBJ, or SSBJ (Copper) Size of Minimum MBJ, SBJ, or SSBJ (Aluminum / Cu-Clad Al)

  • 2 AWG or smaller 1/0 AWG or smaller 8 AWG 6 AWG
  • 1 AWG or 1/0 AWG 2/0 AWG or 3/0 AWG 6 AWG 4 AWG
  • 2/0 AWG or 3/0 AWG 4/0 AWG or 250 kcmil 4 AWG 2 AWG
  • Over 3/0 AWG through 350 kcmil Over 250 kcmil through 500 kcmil 2 AWG 1/0 AWG
  • Over 350 kcmil through 600 kcmil Over 500 kcmil through 900 kcmil 1/0 AWG 3/0 AWG
  • Over 600 kcmil through 1,100 kcmil Over 900 kcmil through 1,750 kcmil 2/0 AWG 4/0 AWG
  • Over 1,100 kcmil Over 1,750 kcmil See 12.5% Rule (Note 1) See 12.5% Rule (Note 1)
  • The 12.5% Rule for Large Conductors (Note 1 to Table 250.102(C)(1))

When the total area of the ungrounded phase conductors exceeds 1,100 kcmil copper (or 1,750 kcmil aluminum ), Table 250.102(C)(1) no longer provides a fixed wire size. Instead, you must apply the 12.5% Rule : Required Jumper Area (cmil) = Total Phase Area (kcmil) × 0.125 × 1 , 000 \text{Required Jumper Area (cmil)} = \text{Total Phase Area (kcmil)} \times 0.125 \times 1,000 Required Jumper Area (cmil) = Total Phase Area (kcmil) × 0.125 × 1 , 000

The bonding jumper must have a cross-sectional circular mil area not less than 12.5% of the cross-sectional area of the largest ungrounded phase conductor (or total sum of parallel phase conductors).

  • 3. Mathematical Calculations for Supply-Side Sizing
  • Worked Example 1: Standard 200A Commercial Service Disconnect

Given: A 200-ampere, 120/208V service is wired with 3/0 AWG copper ungrounded phase conductors. Find the minimum size copper Main Bonding Jumper.

Look up 3/0 AWG copper in Table 250.102(C)(1).

3/0 AWG falls into the row "2/0 AWG or 3/0 AWG Copper".

Minimum copper Main Bonding Jumper = 4 AWG copper = \mathbf{4\text{ AWG copper}} = 4 AWG copper .

Worked Example 2: 1,600-Ampere Service (12.5% Rule)

Given: A 1,600-ampere, 480Y/277V 3-phase switchboard is supplied by four parallel conduits , each containing one 600 kcmil copper conductor per phase. Determine the minimum size copper Main Bonding Jumper.

Step 1: Calculate Total Ungrounded Phase Area: Phase Area = 4 × 600 kcmil = 2 , 400 kcmil copper \text{Phase Area} = 4 \times 600\text{ kcmil} = 2,400\text{ kcmil copper} Phase Area = 4 × 600 kcmil = 2 , 400 kcmil copper

Step 2: Check 1,100 kcmil Threshold: 2 , 400 kcmil > 1 , 100 kcmil 2,400\text{ kcmil} > 1,100\text{ kcmil} 2 , 400 kcmil > 1 , 100 kcmil . Table 250.102(C)(1) requires application of the 12.5% rule.

Step 3: Calculate Required Circular Mil Area: Required Area = 2 , 400 kcmil × 0.125 = 300 kcmil \text{Required Area} = 2,400\text{ kcmil} \times 0.125 = 300\text{ kcmil} Required Area = 2 , 400 kcmil × 0.125 = 300 kcmil

Step 4: Select Standard Conductor: Referring to NEC Chapter 9, Table 8 ( Conductor Properties ), 300 kcmil is a standard commercial wire size.

Minimum copper Main Bonding Jumper = 300 kcmil copper = \mathbf{300\text{ kcmil copper}} = 300 kcmil copper .

Worked Example 3: Supply-Side Bonding Jumper in Parallel Raceways (NEC 250.102(C)(2))

Where service raceways are installed in parallel, a Supply-Side Bonding Jumper (SSBJ) must be installed to bond each individual raceway:

If an individual SSBJ is routed through each raceway , it is sized based on the size of the ungrounded service conductors in that specific raceway .

For Example 2 above: Each raceway contains one 600 kcmil conductor per phase. Looking at Table 250.102(C)(1) under "Over 350 through 600 kcmil", each individual raceway bonding jumper must be not less than 1/0 AWG copper .

4. System Bonding Jumper (SBJ) for Separately Derived Systems (NEC 250.30)

A separately derived system (SDS) is a premises wiring system whose power is derived from a generator, transformer, or converter winding and has no direct electrical connection (including a solidly connected neutral) to supply conductors originating in another system.

The most common SDS encountered on commercial jobsites is a 480V-to-208Y/120V dry-type step-down transformer .

Role of the SBJ (NEC 250.30(A)(1)): Functions exactly like an MBJ, connecting the derived neutral to the transformer enclosure and equipment grounding conductor.

Sizing: Sized per NEC Table 250.102(C)(1) based on the derived secondary phase conductors.

Location Rule (Crucial Exam Concept): The SBJ must be installed at only one point on the separately derived system:

At the source (inside the transformer enclosure); OR

At the first system disconnecting means or overcurrent device (e.g., secondary main breaker panel).

It must NEVER be installed at both locations. Installing an SBJ at both the transformer and the secondary panel creates parallel neutral return paths across the metallic conduit, producing continuous objectionable stray circulating currents.

5. Service Raceway & Enclosure Bonding (NEC 250.92)

Service raceways contain conductors that lack downstream overcurrent protection. Therefore, bonding connections on service equipment must withstand massive fault currents without loosening or burning. NEC 250.92 establishes strict requirements:

Prohibited Bonding Methods (NEC 250.92(B))

Standard locknuts and standard bushings are never acceptable as the sole means of bonding service raceways:

Caution

Standard Locknut Prohibition: A standard locknut (even a double locknut configuration) relies on a thin, stamped-steel thread contact that can arc and vaporize under a 20,000-ampere service ground fault. Standard locknuts are strictly prohibited for bonding service raceways!

Approved Service Bonding Methods (NEC 250.92(B)(1)-(4))

Service raceways and enclosures must be bonded by one of the following four approved methods:

Bonding to the Grounded Service Conductor: Connection to the grounded service conductor using an approved bonding jumper.

Threaded Connections: Threaded couplings or threaded bosses on enclosures made up wrench-tight.

Threadless Couplings/Connectors: Threadless couplings and connectors made up tight for metal conduits and tubing (such as compression EMT connectors listed for service use).

Grounding Bushings with Bonding Jumpers: Other listed devices, such as grounding bushings with bonding jumpers sized per Table 250.102(C)(1), or listed bonding-type wedges.

Knockout Rings and Concentric / Eccentric Knockouts (NEC 250.92(B))

Where service raceways enter an enclosure through concentric or eccentric knockouts that have not been tested and listed for grounding:

A bonding jumper with a grounding bushing must be installed around the punched rings.

The stamped concentric rings have high electrical resistance and cannot safely carry fault current without arcing.

6. Bonding Other Metal Piping Systems & Structural Steel (NEC 250.104)

NEC 250.104 governs the bonding of metallic systems inside buildings that could accidentally become energized:

Interior Metal Water Piping System (NEC 250.104(A))

Interior metal water piping must be bonded to the service equipment enclosure, the grounded service conductor, the grounding electrode conductor, or one of the grounding electrodes.

Sizing: Sized according to NEC Table 250.102(C)(1) based on the largest ungrounded service-entrance conductor.

Must be bonded regardless of whether the water pipe qualifies as a grounding electrode.

Other Metal Piping Systems (Gas Piping) (NEC 250.104(B))

Metal gas piping systems must be bonded. However, unlike water piping, gas piping is not required to be sized from Table 250.102(C)(1).

Under NEC 250.104(B), gas piping is considered bonded if it is connected to the equipment grounding conductor (EGC) of the circuit that is likely to energize the piping (for example, the branch-circuit EGC supplying a gas furnace, gas water heater, or gas range satisfies the bonding requirement!).

Structural Metal (NEC 250.104(C))

Exposed structural metal that is interconnected to form a metal building frame and is not intentionally grounded must be bonded to the service equipment enclosure.

Sized per Table 250.102(C)(1) .

7. Intersystem Bonding Termination (IBT) - NEC 250.94

Modern buildings contain multiple communication and media systems: telephone, cable television (CATV), broadband network internet, and satellite dish receivers. Each of these utilities has its own surge protector or ground block.

In older installations, utility technicians clamped ground wires to random hose bibs or metal siding, creating hazardous voltage differentials during lightning strikes. +-------------------------------------------------------------------------+

  • | INTERSYSTEM BONDING TERMINATION (IBT) |
  • | (NEC 250.94) |
  • | - Location: External to enclosures at service or meter equipment |
  • | - Capacity: Minimum of THREE (3) terminal connection points |
  • | - Connection: Minimum 6 AWG copper conductor to GEC or service ground |
  • | - Connects: Telephone, Cable TV, Satellite Dish, Broadband Network |
  • +-------------------------------------------------------------------------+

Mandate: An Intersystem Bonding Termination (IBT) must be provided external to enclosures at the service equipment or metering equipment.

Terminal Requirement: Must provide a minimum of three (3) terminating points .

Conductor Size: Must be connected to the grounding electrode system with a copper conductor not smaller than 6 AWG .

Accessibility: Must be readily accessible so that communications and cable technicians can land their bonding conductors without opening high-voltage electrical panels.

8. Common Exam Traps & Practical Review

Warning

Common Exam Traps on Section 5.3:

MBJ Sizing vs. GEC Sizing: Sizing an MBJ is governed by Table 250.102(C)(1) , NOT Table 250.66! While the tables have similar rows, Table 250.102(C)(1) incorporates the 12.5% rule for conductors over 1,100 kcmil copper, whereas Table 250.66 caps out at 3/0 AWG copper.

Double Locknuts on Service Raceways: An exam question might ask: "Can rigid metal conduit enclosing service conductors be bonded using double locknuts?" The answer is no . Standard locknuts are prohibited by NEC 250.92(B).

Separately Derived System SBJ Location: Remember: at the transformer OR at the first disconnect, but never both . Installing it at both is an immediate inspection failure.