Study guide

4.3 Service Conductors, Disconnects & Current SPS 316.230 Amendments

Wisconsin Journeyman Electrician Study Guide Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Wisconsin Administrative Rules, Licensing & Electrical Safety

1.1 Wisconsin Journeyman Licensing, Eligibility & Scope 1.2 Current SPS 316 Adoption, Enforcement & Wisconsin Amendments 1.3 Supplemental Job Safety: Shock, Arc-Flash & Work Practices 1.4 Electrical Theory & Mathematical Fundamentals

2 Chapter 2: General Code Rules, Definitions & Enclosure Sizing

2.1 NEC Article 100 Definitions & Article 110 General Installation Requirements 2.2 Conductor Sizing, Ampacity Ratings & Temperature Limitations 2.3 Conductor Ampacity Correction & Adjustment Calculations 2.4 Outlet Box, Device Box & Conduit Body Sizing

3 Chapter 3: Branch Circuits, Feeders & Calculations

3.1 Branch Circuit Ratings, Multiwire Circuits & General Receptacle Outlets 3.2 Wisconsin GFCI & AFCI Protection: NEC 2017-to-2023 Transition 3.3 Dwelling Branch Circuits, Receptacle Spacing & Wisconsin Countertop Rules 3.4 Feeder Sizing, Overcurrent Protection & Voltage Drop

4 Chapter 4: Services & Dwelling Load Calculations

4.1 Dwelling Unit Load Calculations: Standard Method 4.2 Dwelling Unit Load Calculations: Optional Method 4.3 Service Conductors, Disconnects & Current SPS 316.230 Amendments

5 Chapter 5: Grounding and Bonding

5.1 Grounding & Bonding Principles, Systems & Definitions 5.2 Grounding Electrode Systems & GEC Sizing 5.3 Main Bonding Jumpers & Supply-Side Bonding 5.4 Equipment Grounding Conductors & Enclosure Bonding

6 Chapter 6: Wiring Methods, Raceways & Cable Assemblies

6.1 General Wiring Rules & Underground Installations 6.2 Cable Assemblies: NM, NMC, MC, and AC 6.3 Raceways, Conduit Bending & Support Requirements 6.4 Conduit Fill Calculations & Pull Box Sizing

7 Chapter 7: Equipment for General Use: Motors, Generators & Transformers

7.1 Motor Branch Circuit Sizing & Full-Load Currents 7.2 Motor Branch-Circuit Short-Circuit & Overload Protection 7.3 Transformers & Overcurrent Protection

8 Chapter 8: General Loads & Utilization Equipment

8.1 General & Non-Dwelling Load Calculations 8.2 Luminaires, Lighting Systems & Electric Signs 8.3 Appliances, Fixed Electric Space Heating & Water Heating 8.4 Air-Conditioning & Refrigeration Equipment

9 Chapter 9: Special Occupancies & Emergency Systems

9.1 Hazardous (Classified) Locations & Commercial Applications 9.2 Health Care Facilities & Essential Electrical Systems 9.3 Pools, Spas, Hot Tubs & Fountains 9.4 Emergency Systems, Standby Power & Generators

10 Chapter 10: Modern Energy & Low-Voltage Systems

10.1 EV Charging, Photovoltaics, Energy Storage & Interconnections 10.2 Fire Alarm, Signaling & Communications Systems

11 Chapter 11: Exam Logistics & Success

11.1 Exam Logistics, Authorized References & 2026 Code Transition 11.2 Code Navigation, Time Management & Formula Review

4.3 Service Conductors, Disconnects & Current SPS 316.230 Amendments

Key Takeaways Explain This Topic AI

Service conductors must satisfy overhead or underground clearances, protection, ampacity, and point-of-entry requirements in the assigned NEC edition.

Current SPS 316.230 limits service raceways, cables, or conductors to 8 ft inside a building before the service disconnect or first disconnect of a permitted group.

When the service disconnect is outside, current Wisconsin law requires it to be within sight of and no more than 30 ft from the building or structure served.

Current SPS 316.230 states that NEC 230.85 emergency-disconnect requirements are not included in the Wisconsin chapter.

Older Wisconsin cold-sequence metering and local utility dimensions are not current statewide SPS 316.230 exam rules; coordinate utility service requirements separately.

Last updated: September 2026

4.3 Service Conductors, Disconnects & Current SPS 316.230 Amendments

A service question often combines three authorities: the NEC governs premises service conductors and equipment, SPS 316 changes selected Wisconsin requirements, and the serving utility publishes connection and metering specifications. Keep those sources separate. A utility specification does not become a statewide SPS rule merely because several utilities use a similar drawing.

Overhead clearances and openings

Use the assigned NEC tables and paragraphs for the exact conductor type, voltage to ground, and area below the conductors. Common exam values include clearances over pedestrian areas, residential property and driveways, and public streets or truck-traffic areas, but the correct row depends on all stated conditions.

Open service conductors and certain cables near building openings must maintain the clearance specified by Article 230. Determine whether the window opens, whether the conductor is above the upper level of the opening, and whether a building surface is readily accessible. Do not convert a conditional exception into a blanket “three feet from every window” rule.

For underground services, apply burial, protection, and service-lateral provisions from the assigned edition and coordinate the demarcation between utility-controlled and premises wiring.

Location of the service disconnect

The NEC requires the service disconnecting means at a readily accessible location outside or inside nearest the point of entrance of the service conductors. Wisconsin adds a measurable inside limit. Current SPS 316.230(3)(b) provides that raceways containing service conductors, service cables, or service-entrance cable not in a raceway may not extend more than 8 ft into the building before reaching the service disconnect or the first disconnect of a permitted group.

Measure entry at the outer surface of the building exterior, subject to the adopted NEC treatment for conductors considered outside the building. The eight-foot allowance is a maximum, not a default design target. The disconnect still must satisfy accessibility, grouping, identification, and service-equipment rules.

Outside service disconnects

Current SPS 316.230(3)(c) says that an outside service disconnect must be:

within sight of the building or structure served, and

not more than 30 ft from it.

Both conditions apply. “Within sight” does not erase the distance maximum, and a disconnect 20 ft away behind an opaque wall does not satisfy the sight condition.

Emergency disconnect omission

The 2023 NEC contains a dwelling emergency-disconnect rule in 230.85. Current SPS 316.230(4) expressly says that the requirements of NEC 230.85 are not included as part of the Wisconsin chapter. Therefore, do not select an answer asserting that SPS 316 universally mandates the national 230.85 dwelling emergency disconnect.

An outdoor disconnect may still be installed or required for another reason—the service design, utility equipment, local facts, or another adopted provision. The point is narrower: the omitted NEC paragraph is not itself a Wisconsin SPS 316 requirement.

Wisconsin makes a parallel omission for the NEC 225.41 emergency disconnect at outside branch-circuit and feeder supplies. Keep Article 225 and Article 230 scopes distinct.

Multiple service disconnects

The assigned NEC controls the permitted number, grouping, and construction of service disconnects. Modern editions restrict how multiple disconnects share enclosures or compartments. For a transition-year exam, read the version in the assigned book; do not answer a 2017 question only from a 2023 memory aid.

Each service disconnect must be suitable for use as service equipment where required, properly rated, and identified. Grounded-conductor bonding and the grounding electrode connection belong at the locations permitted by Article 250. A meter disconnect that is not service equipment is not automatically the point for the main bonding jumper.

Metering and utility coordination

The current SPS 316 final order repealed older portions of SPS 316.230, including text that supported obsolete statewide study notes. Do not claim that current SPS 316.230 imposes a universal cold-sequence rule above 300V to ground. Instead, contact the serving utility before installing service and metering equipment and follow its current service manual in addition to the electrical code.

Likewise, meter height, working space around a meter, separation from gas equipment, approved sockets, bypasses, and cut-in procedures may be utility- and installation-specific. They should not be presented as uniform statewide exam facts without a current statewide citation.

Service-question checklist

Identify overhead or underground supply and the ownership boundary.

Apply conductor ampacity, clearances, and physical protection from the assigned NEC.

Locate the service disconnect using the NEC plus Wisconsin's 8-ft inside maximum.

For an outdoor disconnect, test both “within sight” and “30 ft maximum.”

Check SPS 316 for an exclusion before applying 230.85.

Treat utility metering rules as separate coordination requirements.

That sequence produces a current Wisconsin answer without importing repealed state language.