8.3 Hangers, Supports & Protection of Piping (SPS 382.60)

Wisconsin Journeyman Plumber Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Licensing, Exam Rules & Code Administration

1.1 Wisconsin Plumbing Credentials, Scope & Supervision (Ch. 145, SPS 305) 1.2 The Journeyman Exam: Format, Fees, Retakes & Permitted References 1.3 Plan Review, Plan Approval & Product Approvals (SPS 382.20) 1.4 Testing, Inspection, Maintenance & Repairs (SPS 382.21, 382.22) 1.5 Code Structure, Key Definitions, Basic Principles & Referenced Standards

2 Chapter 2: Sanitary Drainage Systems (SPS 382.30)

2.1 Drainage Fixture Units (DFU) & Load Values 2.2 Horizontal Branch Drains, Pitch & Changes in Direction 2.3 Drain Stacks, Branch Intervals & Stack Offsets 2.4 Building Drains, Building Sewers & Private Interceptor Main Sewers

3 Chapter 3: Venting Systems & Cold-Climate Vent Terminals (SPS 382.31)

3.1 Vent Stacks, Relief Vents & Vent Sizing Tables 3.2 Common Vents, Wet Vents & Circuit Vents 3.3 Return Vents, Combination Drain & Vent Systems & Air Admittance Valves 3.4 Vent Terminals, Frost Closure & Prohibited Vent Uses

4 Chapter 4: Traps, Indirect Waste & Wastewater Treatment Devices

4.1 Fixture Traps, Trap Seals & Direct Fixture Connections 4.2 Trap-to-Vent Distances (Table 382.31-1) 4.3 Indirect & Local Waste Piping, Air Gaps & Receptors 4.4 Interceptors, Catch Basins & Chemical Waste Treatment (SPS 382.34)

5 Chapter 5: Water Supply Systems (SPS 382.40)

5.1 Water Supply Fixture Units (WSFU) & Demand 5.2 Sizing Water Distribution Piping: Pressure, Friction & Velocity 5.3 Control Valves, Thermal Expansion, Water Hammer & Pipe Identification 5.4 Water Heaters, Relief Valves, Hot Water Delivery & Temperature Control 5.5 Water Services, Private Water Mains, Disinfection & Storage Tanks

6 Chapter 6: Cross-Connection Control & Backflow Prevention (SPS 382.41)

6.1 Cross-Connection Fundamentals, Hazard Classes & Pressure Conditions 6.2 Backflow Devices & Assemblies: Table 382.41-1, Limits & Installation 6.3 Assembly Registration, DSPS Tags, Annual Testing & Tester Registration

7 Chapter 7: Plumbing Fixtures, Fittings & Appliances (SPS 384.20)

7.1 Fixture Construction, Clearances, Shower Size & Safing 7.2 Water-Conserving Fixtures, Faucets & Fixture Supply Connectors 7.3 Water Heaters, Water Treatment Devices & Other Plumbing Appliances

8 Chapter 8: Piping Materials, Joints & Supports (SPS 384.30, 384.40, 382.60)

8.1 Approved Piping Materials by Service & Lead-Free Rules 8.2 Joints, Connections & Transitions Between Materials (SPS 384.40) 8.3 Hangers, Supports & Protection of Piping (SPS 382.60)

9 Chapter 9: Private Onsite Wastewater Treatment Systems (SPS 383, 385 & Component Manuals)

9.1 POWTS Regulation, Sanitary Permits, Plan Review & Inspection 9.2 Soil & Site Evaluation and In Situ Soil Parameters (SPS 385, SPS 383.44) 9.3 Design Flow, Septic & Holding Tanks and Tank Construction 9.4 Dispersal Components & the DSPS Component Manuals 9.5 POWTS Setbacks, Management, Maintenance Reporting & Abandonment

10 Chapter 10: Cleanouts, Stormwater, Sumps & Multipurpose Piping

10.1 Cleanouts & Manholes (SPS 382.35) 10.2 Stormwater & Clearwater Systems (SPS 382.36) 10.3 Sanitary Sumps, Ejectors & Discharge Points (SPS 382.30 (10), 382.38) 10.4 Multipurpose Piping Systems & NFPA 13D Residential Sprinklers

11 Chapter 11: Special Plumbing Installations & Water Reuse

11.1 Health Care & Related Facilities (SPS 382.50) 11.2 Manufactured Homes, Campgrounds, RV Parks & Dump Stations 11.3 Water Reuse, Plumbing Treatment Standards & Stormwater Infiltration

8.3 Hangers, Supports & Protection of Piping (SPS 382.60)

Key Takeaways Explain This Topic AI

Drain piping is designed as if full of water, and hangers must be compatible with the pipe so they do not cause galvanic action or cut or abrade it.

Table 382.60 limits horizontal support spacing to 4 feet for PVC and ABS (5 feet for PVC vents), 5 feet for cast iron (10 feet with 10-foot lengths) and 2 feet 8 inches for PEX.

Copper tubing 1-1/4 inch and smaller is supported every 6 feet horizontally; 1-1/2 inch and larger every 10 feet; copper pipe and steel pipe every 12 feet.

Hubless pipe laid horizontally must be supported within 24 inches on each side of a joint unless the joint has an alignment retaining shield.

Hangers may not be attached with wood plugs, and shower valves and piping to the showerhead must be securely fastened to the structure.

Last updated: October 2026

Materials and strength (SPS 382.60 (1))

Hangers, anchors and supports must carry the piping and its contents . Drain piping is considered full of water for this purpose.

Underground piers for pipe support must be concrete, masonry, plastic or pressure-treated wood .

Hangers and straps must be of a compatible material that reduces galvanic action, and may not distort, cut or abrade the pipe. Bare steel strap on copper is the classic violation.

Installation (SPS 382.60 (2))

Hangers and anchors are attached securely to the building structure at intervals no greater than Table 382.60. PVC used for venting may be supported every 5 feet horizontally.

The connection of drain piping to a fixture or appliance counts as a point of support.

Hubless pipe installed horizontally must be supported within 24 inches on each side of a joint , unless the joint has an alignment retaining shield .

Hangers may not be attached with wood plugs .

Shower valves and the piping from the valve to the showerhead outlet must be securely attached to the structure.

Table 382.60 support spacing

  • Material Max horizontal spacing Max vertical spacing
  • ABS 4 ft 10 ft
  • Brass 10 ft 10 ft
  • Cast iron 5 ft (10 ft with 10-ft lengths) 15 ft
  • Copper or copper-alloy pipe 12 ft 10 ft
  • Copper tubing, 1-1/4 in. and smaller 6 ft 10 ft
  • Copper tubing, 1-1/2 in. and larger 10 ft 10 ft
  • CPVC, 1 in. and smaller 3 ft 5 ft (mid-story guide)
  • CPVC, 1-1/4 in. and larger 4 ft 6 ft (mid-story guide)
  • PEX 2-2/3 ft (2 ft 8 in.) 4 ft
  • Ductile iron 5 ft (10 ft with 10-ft lengths) 15 ft
  • Galvanized steel 12 ft 15 ft
  • Lead Continuous 4 ft
  • Polybutylene 2 ft 8 in. 4 ft
  • PE, PP, PVDF, flexible PVC 2 ft 4 ft
  • PVC 4 ft (5 ft for vents) 10 ft
  • Stainless steel 12 ft 15 ft

"Mid-story guide" (CPVC vertical) means a guide is also required midway between floors.

Worked examples

PVC drain. A 60-foot horizontal run of 3-inch PVC drain needs supports at no more than 4-foot intervals: 60 / 4 = 15 spaces, so about 16 supports counting both ends. Where the drain connects to a fixture, that connection counts as one support point. If the same pipe were a vent, 5-foot spacing would need about 13 supports.

Cast iron. No-hub cast iron in 10-foot lengths may be hung every 10 feet. But each horizontal no-hub joint without an alignment shield still needs a support within 24 inches on each side. In practice that means a hanger near every coupling.

PEX. A 40-foot horizontal PEX run needs supports no more than 2 feet 8 inches (32 inches) apart: 480 inches / 32 = 15 spaces, so about 16 supports. That is why PEX is often run in continuous channel or laid on joists. Continuous support satisfies the spacing limit.

Copper. In a 1-inch copper tube riser through a three-story building, Table 382.60 requires vertical support at least every 10 feet. Horizontally the same 1-inch tube needs support every 6 feet; a 2-inch tube, every 10 feet.

Related protection rules

Topic Rule Section

Framing penetrations Steel plate of at least No. 18 gauge where plastic or copper pipe is within 1 inch of the framing edge, extending 1-1/2 inches beyond the pipe SPS 384.30 (1) (e)

Freezing All water supply piping protected from freezing; exterior wall hose bibbs frost-proof and self-draining SPS 382.40 (8) (a)

Traps Rigidly supported, set level, protected from freezing and evaporation SPS 382.32 (4) (a)

Fire-resistive assemblies Penetrations protected per the commercial building code, chs. SPS 361 to 366 SPS 384.13

Wall-hung fixtures Carriers meet ASME A112.6.1M or A112.6.2; no load on the drain connection SPS 384.20 (4) (b) 2.

Water distribution support Distribution piping supported per SPS 382.60 SPS 382.40 (8) (d) 1.

  • Vacuum drainage systems Hangers per SPS 382.60 SPS 382.30 (14) (i)
  • Rough-in inspection checklist for supports

Before calling for a rough-in inspection, walk the job with the table in hand:

Measure the longest unsupported horizontal run of each material and compare it to Table 382.60. Remember the fixture connection counts as one support.

Check every horizontal no-hub coupling for a hanger within 24 inches on each side, or an alignment shield.

Confirm that hangers are fastened to structure (not to other piping, ductwork or wood plugs), and that straps match the pipe material.

Look at risers: vertical supports at the table spacing, and mid-story guides on CPVC.

Verify that shower valves and the piping to the showerhead are rigidly fastened, and that nail plates protect pipe within 1 inch of framing edges.

Exam traps

Answering "10 feet" for horizontal cast iron : the base value is 5 feet , rising to 10 only with 10-foot lengths.

Confusing copper pipe (12 ft) with copper tubing (6 or 10 ft).

Forgetting that drain piping counts as full of water when sizing hangers.

Loading diagram... Placing pipe supports