Study guide

3.4 Vent Terminals, Frost Closure & Prohibited Vent Uses

Wisconsin Journeyman Plumber Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Licensing, Exam Rules & Code Administration

1.1 Wisconsin Plumbing Credentials, Scope & Supervision (Ch. 145, SPS 305) 1.2 The Journeyman Exam: Format, Fees, Retakes & Permitted References 1.3 Plan Review, Plan Approval & Product Approvals (SPS 382.20) 1.4 Testing, Inspection, Maintenance & Repairs (SPS 382.21, 382.22) 1.5 Code Structure, Key Definitions, Basic Principles & Referenced Standards

2 Chapter 2: Sanitary Drainage Systems (SPS 382.30)

2.1 Drainage Fixture Units (DFU) & Load Values 2.2 Horizontal Branch Drains, Pitch & Changes in Direction 2.3 Drain Stacks, Branch Intervals & Stack Offsets 2.4 Building Drains, Building Sewers & Private Interceptor Main Sewers

3 Chapter 3: Venting Systems & Cold-Climate Vent Terminals (SPS 382.31)

3.1 Vent Stacks, Relief Vents & Vent Sizing Tables 3.2 Common Vents, Wet Vents & Circuit Vents 3.3 Return Vents, Combination Drain & Vent Systems & Air Admittance Valves 3.4 Vent Terminals, Frost Closure & Prohibited Vent Uses

4 Chapter 4: Traps, Indirect Waste & Wastewater Treatment Devices

4.1 Fixture Traps, Trap Seals & Direct Fixture Connections 4.2 Trap-to-Vent Distances (Table 382.31-1) 4.3 Indirect & Local Waste Piping, Air Gaps & Receptors 4.4 Interceptors, Catch Basins & Chemical Waste Treatment (SPS 382.34)

5 Chapter 5: Water Supply Systems (SPS 382.40)

5.1 Water Supply Fixture Units (WSFU) & Demand 5.2 Sizing Water Distribution Piping: Pressure, Friction & Velocity 5.3 Control Valves, Thermal Expansion, Water Hammer & Pipe Identification 5.4 Water Heaters, Relief Valves, Hot Water Delivery & Temperature Control 5.5 Water Services, Private Water Mains, Disinfection & Storage Tanks

6 Chapter 6: Cross-Connection Control & Backflow Prevention (SPS 382.41)

6.1 Cross-Connection Fundamentals, Hazard Classes & Pressure Conditions 6.2 Backflow Devices & Assemblies: Table 382.41-1, Limits & Installation 6.3 Assembly Registration, DSPS Tags, Annual Testing & Tester Registration

7 Chapter 7: Plumbing Fixtures, Fittings & Appliances (SPS 384.20)

7.1 Fixture Construction, Clearances, Shower Size & Safing 7.2 Water-Conserving Fixtures, Faucets & Fixture Supply Connectors 7.3 Water Heaters, Water Treatment Devices & Other Plumbing Appliances

8 Chapter 8: Piping Materials, Joints & Supports (SPS 384.30, 384.40, 382.60)

8.1 Approved Piping Materials by Service & Lead-Free Rules 8.2 Joints, Connections & Transitions Between Materials (SPS 384.40) 8.3 Hangers, Supports & Protection of Piping (SPS 382.60)

9 Chapter 9: Private Onsite Wastewater Treatment Systems (SPS 383, 385 & Component Manuals)

9.1 POWTS Regulation, Sanitary Permits, Plan Review & Inspection 9.2 Soil & Site Evaluation and In Situ Soil Parameters (SPS 385, SPS 383.44) 9.3 Design Flow, Septic & Holding Tanks and Tank Construction 9.4 Dispersal Components & the DSPS Component Manuals 9.5 POWTS Setbacks, Management, Maintenance Reporting & Abandonment

10 Chapter 10: Cleanouts, Stormwater, Sumps & Multipurpose Piping

10.1 Cleanouts & Manholes (SPS 382.35) 10.2 Stormwater & Clearwater Systems (SPS 382.36) 10.3 Sanitary Sumps, Ejectors & Discharge Points (SPS 382.30 (10), 382.38) 10.4 Multipurpose Piping Systems & NFPA 13D Residential Sprinklers

11 Chapter 11: Special Plumbing Installations & Water Reuse

11.1 Health Care & Related Facilities (SPS 382.50) 11.2 Manufactured Homes, Campgrounds, RV Parks & Dump Stations 11.3 Water Reuse, Plumbing Treatment Standards & Stormwater Infiltration

3.4 Vent Terminals, Frost Closure & Prohibited Vent Uses

Key Takeaways Explain This Topic AI

Vents through a roof must extend at least 8 inches above the roof, or at least 7 feet where the roof is used for any purpose other than weather protection.

Every vent terminal must be at least 2 inches in diameter to resist frost closure, and any increase in size must be made at least 6 inches inside the building.

Vent terminals must be at least 10 feet from an air intake, 5 feet from a power exhaust vent, and 10 feet horizontally from or 2 feet above doors, openable windows and roof scuttles.

Terminals must be at least 5 feet from or 2 inches above parapet walls and at least 5 feet below any overhang; wall terminals must be 10 feet from any lot line.

Drain and vent piping may not run on the outside of an exterior wall of a new building, and steam, boiler blowoff and chemical waste vents may not join the sanitary vent system.

Last updated: October 2026

Why Wisconsin is strict about vent terminals

Warm, moist air leaving a vent in a Wisconsin January condenses and freezes at the pipe opening. A small terminal can frost shut, and then every trap downstream loses its protection from the 1-inch pressure limit of SPS 382.31 (3). Wisconsin's terminal rules answer three questions: how high , how far from openings , and how big .

Height above the roof (SPS 382.31 (16) (a) and (b))

  • Roof Minimum extension
  • Roof used only for weather protection 8 inches above the roof
  • Roof used for any other purpose (deck, terrace, patio, equipment area) 7 feet above the roof

Earth-covered roof extending from grade 7 feet above grade with an approved vent cap; outside portion without joints except one fitting where it leaves the structure

Every roof penetration must be made watertight with an approved flashing . The code doesn't specify flashing material, so any approved product that makes the penetration watertight complies.

Clearances (SPS 382.31 (16) (d))

  • Nearby feature Required location of the vent terminal
  • Air intake At least 10 feet away
  • Power exhaust vent At least 5 feet away
  • Roof scuttle, door or openable window At least 10 feet horizontally, or at least 2 feet above
  • Parapet wall At least 5 feet away, or at least 2 inches above
  • Overhang At least 5 feet below

Worked example. A vent must penetrate a flat roof 6 feet from an openable penthouse window whose top is 5 feet above the roof. It is inside the 10-foot horizontal zone, so the terminal must rise at least 2 feet above the opening, to 7 feet above the roof. Moving the penetration 10 feet or more from the window also complies, as long as the terminal still clears the 8-inch minimum height.

Notice the parapet rule: a vent close to a parapet doesn't need to be 5 feet away if it extends 2 inches above the top of the parapet wall.

Wall terminals and exterior piping (SPS 382.31 (16) (e) and (f))

A vent must terminate at least 10 feet horizontally from any lot line .

A vent extended through a wall must terminate beyond the soffit , turn downward and be screened . It must also meet all the clearance rules in (d).

Drain or vent piping may not be placed on the outside of an exterior wall of any new building ; it must be inside the building.

Frost closure (SPS 382.31 (16) (g))

Important

"For protection against frost closure, each vent terminal shall be at least 2 inches in diameter. Where it is necessary to increase the diameter of the vent, the change in diameter shall be made at least 6 inches inside the building."

Two numbers to remember: 2 inches minimum terminal and an increaser located at least 6 inches inside the building . A 1-1/2 inch stack vent from a small addition, for example, must be increased to 2 inches before it leaves the building. The increaser must be at least 6 inches inside, so the larger pipe passes through the roof structure. The ch. SPS 382 Appendix has explanatory material on this rule. In the code text, the measurement is simply "inside the building."

Worked example. A house's only stack vent is 3 inches (the main-stack minimum). It already exceeds 2 inches, so no increaser is needed. A separate 1-1/4 inch individual vent that goes through the roof on its own must be increased to 2 inches, with the increaser at least 6 inches inside the building. Tying that vent into the 3-inch stack vent instead avoids the second roof penetration entirely.

Penetrations through grade (SPS 382.31 (16) (h))

A vent that penetrates grade, such as from an exterior sump, must terminate at least 12 inches above finished grade with a vent cap or return bend. Earth-covered roofs are the exception and use the 7-foot rule above.

Prohibited uses (SPS 382.31 (16) (c) and (18))

Vent terminals may not be used as flagpoles, antenna supports or similar purposes.

A vent system may serve only the plumbing system.

Boiler blowoff basin vents may not join a vent serving a sanitary, storm or chemical waste system.

Chemical waste vents may not join a sanitary or storm vent system.

Steam vents from sterilizers, degreasers, pressing machines and other equipment that discharges steam into the vent may not join sanitary, storm or chemical waste vents.

Exam strategy

Terminal questions usually give one measurement and ask whether it complies. Read the clearance table carefully. An air intake needs 10 feet with no "above" alternative. A window or door allows either 10 feet horizontally or 2 feet above. A power exhaust needs only 5 feet. And for frost closure the answer is always 2 inches and 6 inches inside the building. Wisconsin code does not use 3-inch frost-closure terminals or an "inside the thermal envelope" test.