10.1 OHS Act Section 24 Statutory Reporting Criteria and Timeframes
SACPCMP Construction Health & Safety Manager Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: South African Occupational Health and Safety Legislation
1.1 The OHS Act Framework, General Duties of Employers and Employees 1.2 Corporate Governance and Section 16 Liability & Delegations 1.3 Worker Representation: Health & Safety Representatives and Committees 1.4 Mandatary Agreements, Acts/Omissions & Criminal Liability
2 Chapter 2: Construction Regulations 2014 & Legal Appointments
2.1 Construction Work Permits, Notifications & Client Duties 2.2 Designer Duties and Principal Contractor Obligations 2.3 Statutory Construction Supervision Appointments 2.4 The CHS Manager vs CHS Officer vs CHS Agent & Professional Registration
3 Chapter 3: Risk Assessment Methodologies & The HIRA Process
3.1 Fundamental Risk Terminology: Hazards, Risks, Consequences & Tolerability 3.2 The Three Tiers of HIRA: Baseline, Issue-Based & Continuous Risk Assessments 3.3 Risk Rating Matrices: Quantitative, Semi-Quantitative & Qualitative Scoring 3.4 Task-Based Risk Assessments (TBRA) & Workforce Participation
4 Chapter 4: Risk Control Hierarchy & Safe Work Procedures
4.1 The Hierarchy of Controls in Construction Operations 4.2 Developing and Implementing Safe Work Procedures (SWPs) and SOPs 4.3 Daily Safety Task Instructions (DSTI) and Pre-Task Risk Reviews
5 Chapter 5: Specifications, Plans & The Health and Safety File
5.1 Client Health and Safety Specifications 5.2 The Principal Contractor Health & Safety Plan: Structure and Approval 5.3 Compiling and Maintaining the Consolidated Health & Safety File 5.4 Subcontractor Safety File Verification and Onboarding
6 Chapter 6: Specialized Safety Plans, Method Statements & Registers
6.1 Comprehensive Fall Protection Planning (CR 10 Requirements) 6.2 Contractor Method Statements and Risk Alignment 6.3 Statutory Registers, Checklists, and Inspection Logs
7 Chapter 7: Working at Heights & Temporary Works
7.1 Working at Heights: Fall Prevention, Fall Arrest & Rescue Systems 7.2 Scaffolding Standards, Competent Inspection & SANS 10085 (CR 16) 7.3 Temporary Works Management: Formwork, Falsework & Support Structures (CR 12)
8 Chapter 8: Excavations, Demolition & Heavy Plant Operations
8.1 Excavation Safety, Shoring, Battering & Underground Services (CR 13) 8.2 Demolition Work, Structural Assessment & Control Zones (CR 14) 8.3 Mobile Plant, Construction Vehicles & Cranes (CR 22, 23)
9 Chapter 9: Electrical Safety, Hazardous Chemicals & Confined Spaces
9.1 Temporary Electrical Installations, Distribution Boards & SANS 10142 (CR 24) 9.2 Hazardous Chemical Agents (HCA) & the Globally Harmonized System (GHS) 9.3 Confined Space Entry, Atmospheric Testing & Emergency Protocols (GSR 5)
10 Chapter 10: Incident Reporting, Statutory Notifications & Investigations
10.1 OHS Act Section 24 Statutory Reporting Criteria and Timeframes 10.2 Compensation for Occupational Injuries and Diseases Act (COIDA) Compliance 10.3 Incident Scene Preservation and Evidence Gathering Protocols 10.4 Root Cause Analysis Methodologies (5 Whys, Fishbone) & CAPA
11 Chapter 11: Safety Auditing, Worker Consultation & Site Training
11.1 Internal Audits, Client Oversight Audits & Scoring Protocols (CR 5(1)(o), CR 7(1)(c)) 11.2 Non-Conformance Reports (NCRs), Corrective Actions & Close-Out Mandatory Site Induction, Competency Verification & Training Programs (CR 7(5)–(7)) 11.4 Medical Surveillance, Certificate of Fitness & Hygiene Monitoring (CR 7(8))
12 Chapter 12: Health and Safety Management Systems, Performance & Culture
12.1 Health and Safety Management Systems & ISO 45001 12.2 Health and Safety Performance Measurement, Statistics & Trend Analysis 12.3 Leadership, People & Health and Safety Culture 12.4 Innovation & Technology in Construction Health and Safety
13 Chapter 13: Emergency Preparedness, Communication & Health and Safety Procurement
13.1 Emergency Preparedness, Fire Precautions & First Aid (CR 29, GSR 3) 13.2 Health and Safety Communication, Consultation, Meetings & Reporting 13.3 Health and Safety Procurement & Cost Management
14 Chapter 14: Physical Agents, Environmental Management & Specialised Site Controls
14.1 Noise, Physical Agents & Ergonomics on Construction Sites 14.2 Environmental Management on Construction Projects 14.3 Specialised Site Controls: Structures, Platforms, Hoists, Plant & Facilities (CR 11, 15, 17-21, 25-28, 30)
10.1 OHS Act Section 24 Statutory Reporting Criteria and Timeframes
Key Takeaways Explain This Topic AI
Section 24(1)(a) requires reporting where any person dies, becomes unconscious, loses a limb or part of a limb, or is likely to die, suffer a permanent defect or be unable to do their usual work for at least 14 days.
Section 24(1)(c) requires reporting, even without injury, where persons were endangered and a dangerous substance was spilled, a substance under pressure was released uncontrollably, machinery failed causing flying or falling objects, or machinery ran out of control.
General Administrative Regulation 8 requires a written report to the provincial director within 7 days on W.Cl.2 (or W.Cl.1 for disease), with immediate notification of deaths, unconsciousness, limb loss and injuries likely to cause death or a permanent defect.
GAR 9 requires an Annexure 1 record of reportable incidents and of any injury needing more than first aid, investigation within 7 days, committee review at its next meeting, and retention for 3 years.
Section 24(2) bars disturbing the scene of a death, likely death or limb loss without an inspector's consent, except to prevent a further incident, remove the injured or dead, or rescue persons.
Last updated: October 2026
1. The Statutory Framework
Section 24 of the Occupational Health and Safety Act requires certain incidents to be reported to an inspector. The General Administrative Regulations, 2013 (GAR) set out how:
GAR 8 covers reporting to the provincial director: the form, the deadline and the immediate notification of serious cases.
GAR 9 covers recording and investigating incidents internally, on Annexure 1 .
Keep the two apart: an incident can be recordable without being reportable. CR 5(3) adds that where a fatality or permanent disabling injury occurs on a construction site, the client must ensure that the contractor gives the provincial director a Section 24 report under GAR 8 and 9 that includes the measures the contractor intends to implement.
Section 24 applies to incidents occurring at work, arising out of or in connection with the activities of persons at work, or in connection with the use of plant or machinery, in which any person is affected: employees, contractors' workers, visitors and members of the public.
2. What Must Be Reported (Section 24(1))
Section 24(1)(a) – people harmed. Any person:
- dies ;
- becomes unconscious (for any length of time);
- suffers the loss of a limb or part of a limb (including part of a finger); or
is otherwise injured or becomes ill to such a degree that they are likely to die , likely to suffer a permanent physical defect , or likely to be unable for at least 14 days either to work or to continue with the activity for which they were employed or are usually employed.
The 14-day test is about the likely inability to do the person's usual work, judged at the time. Moving an injured artisan to "light duty" does not avoid reporting if they cannot do their normal work for 14 days or more.
Section 24(1)(b) – a major incident. An occurrence of catastrophic proportions resulting from the use of plant or machinery or from activities at a workplace (as defined in Section 1).
Section 24(1)(c) – dangerous events without injury. The health or safety of any person was endangered and:
- (i) a dangerous substance was spilled ;
- (ii) there was an uncontrolled release of a substance under pressure ;
(iii) machinery or any part of it fractured or failed , resulting in flying, falling or uncontrolled moving objects; or
(iv) machinery ran out of control .
Construction examples of (c): a crane hoist rope parting and the load falling; a hydraulic line bursting on an excavator; a strike on a gas main releasing gas under pressure; a dump truck running away after brake failure. A trench or scaffold collapse with no injury is not listed as such; record and investigate it under GAR 9, and report it if it also falls within (b) or (c) (for example, if machinery failed and people were endangered).
Section 24(3) excludes traffic accidents on public roads, incidents in private households reported to the police, and aviation accidents investigated under the aviation legislation.
3. How and When to Report (GAR 8)
Situation Action Deadline
Any Section 24 incident Written report to the provincial director on form W.Cl.2 (accident) or W.Cl.1 (disease) Within 7 days
Death, unconsciousness, loss of a limb or part of a limb, or injury or illness likely to cause death or a permanent physical defect Additional notification by telephone, fax or similar means Forthwith (immediately)
An injured person later dies Notify the provincial director Forthwith
Incident involving a person who is not an employee Notify the provincial director with the prescribed particulars (who, where, when, how and why, and witnesses) Forthwith
The same W.Cl.2 form is also used for the COIDA claim (Section 10.2), but the two reports go to different authorities: the provincial director of the Department of Employment and Labour for Section 24, and the Compensation Fund or licensed insurer for compensation. Reporting to one does not satisfy the other.
4. Recording and Investigation (GAR 9)
GAR 9(1): every employer or user must keep, in the form of Annexure 1 , a record of every incident that must be reported under Section 24, and of every other incident in which a person needed medical treatment other than first aid . The record is kept at the workplace for at least three years and is open to inspectors.
GAR 9(2): every recorded incident must be investigated within 7 days by the employer or a designated person (which may include a health and safety representative or committee member), and finalised as soon as reasonably practicable.
GAR 9(3): the findings are entered on Annexure 1 when the investigation is complete.
GAR 9(4): the health and safety committee must consider the records at its next meeting , and the employer must ensure that the necessary preventive actions are implemented and followed up.
Annexure 1 has three parts: recording of the incident (person, injury, expected disablement period), the investigation (investigator, description, suspected cause, recommendations), and the action taken by the employer.
5. Preserving the Scene (Section 24(2))
Section 24(2) provides that, in the event of an incident in which a person died , was injured to such an extent that they are likely to die , or suffered the loss of a limb or part of a limb , no person may disturb the site or remove any article or substance involved without the consent of an inspector . The only actions permitted without consent are those necessary:
- to prevent a further incident ;
- to remove the injured or dead ; or
to rescue persons from danger .
Section 24(2) does not apply to incidents with lesser injuries or to no-injury events under Section 24(1)(c), but preserving evidence is still good investigation practice. Disturbing a protected scene is an offence under Section 38(1) (fine up to R50 000 or imprisonment up to one year, or both), and deliberately destroying evidence can also amount to the common-law crime of defeating or obstructing the course of justice.
6. Practical Classification
Scenario Reportable? Basis Action
Worker falls 1.8 m; fractured forearm; booked off 28 days Yes 24(1)(a): likely unable to work for 14 days or more W.Cl.2 to provincial director within 7 days; Annexure 1; investigate within 7 days
Carpenter knocked unconscious for 45 seconds; discharged same day Yes 24(1)(a): unconsciousness Report within 7 days; Annexure 1
Tower crane rope parts; load falls into barricaded area; people nearby Yes 24(1)(c)(iii): machinery failure, falling object, persons endangered Report within 7 days; investigate
Excavator ruptures a gas main; gas escapes under pressure; site evacuated Yes 24(1)(c)(ii): uncontrolled release under pressure Report within 7 days; investigate
Labourer needs four sutures; back at full duty next day No Below 24(1)(a) thresholds Record on Annexure 1 (medical treatment beyond first aid); investigate within 7 days
Welder loses the tip of an index finger Yes 24(1)(a): loss of part of a limb Immediate notification; scene preserved under 24(2); written report within 7 days
Empty trench wall collapses during lunch; no one endangered Not under 24(1)(c) as such Not one of the listed events Record as a near miss, investigate, review the excavation risk assessment
Artisan with fractured ankle does 21 days of office work Yes 24(1)(a): unable to do usual work for 14 days or more Report within 7 days
7. The CHSM's Incident Protocol
Life safety: activate the emergency plan, get first aiders and emergency medical services to the casualty, and isolate secondary hazards (electricity, gas, unstable structures).
Scene control: cordon the scene; where Section 24(2) applies, allow only rescue, removal of the injured or dead, and actions to prevent a further incident.
Notifications: forthwith to the provincial director for deaths, unconsciousness, limb loss and injuries likely to cause death or permanent defect (GAR 8); also inform the client and its agent (CR 5(3)), senior management and the Section 16 appointees.
Evidence: secure registers, task instructions, plant records and medical certificates; separate witnesses.
Paperwork: W.Cl.2 to the provincial director within 7 days; Annexure 1 record; investigation started within 7 days; committee review at its next meeting (GAR 9).