13.1 Emergency Preparedness, Fire Precautions & First Aid (CR 29, GSR 3)
SACPCMP Construction Health & Safety Manager Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: South African Occupational Health and Safety Legislation
1.1 The OHS Act Framework, General Duties of Employers and Employees 1.2 Corporate Governance and Section 16 Liability & Delegations 1.3 Worker Representation: Health & Safety Representatives and Committees 1.4 Mandatary Agreements, Acts/Omissions & Criminal Liability
2 Chapter 2: Construction Regulations 2014 & Legal Appointments
2.1 Construction Work Permits, Notifications & Client Duties 2.2 Designer Duties and Principal Contractor Obligations 2.3 Statutory Construction Supervision Appointments 2.4 The CHS Manager vs CHS Officer vs CHS Agent & Professional Registration
3 Chapter 3: Risk Assessment Methodologies & The HIRA Process
3.1 Fundamental Risk Terminology: Hazards, Risks, Consequences & Tolerability 3.2 The Three Tiers of HIRA: Baseline, Issue-Based & Continuous Risk Assessments 3.3 Risk Rating Matrices: Quantitative, Semi-Quantitative & Qualitative Scoring 3.4 Task-Based Risk Assessments (TBRA) & Workforce Participation
4 Chapter 4: Risk Control Hierarchy & Safe Work Procedures
4.1 The Hierarchy of Controls in Construction Operations 4.2 Developing and Implementing Safe Work Procedures (SWPs) and SOPs 4.3 Daily Safety Task Instructions (DSTI) and Pre-Task Risk Reviews
5 Chapter 5: Specifications, Plans & The Health and Safety File
5.1 Client Health and Safety Specifications 5.2 The Principal Contractor Health & Safety Plan: Structure and Approval 5.3 Compiling and Maintaining the Consolidated Health & Safety File 5.4 Subcontractor Safety File Verification and Onboarding
6 Chapter 6: Specialized Safety Plans, Method Statements & Registers
6.1 Comprehensive Fall Protection Planning (CR 10 Requirements) 6.2 Contractor Method Statements and Risk Alignment 6.3 Statutory Registers, Checklists, and Inspection Logs
7 Chapter 7: Working at Heights & Temporary Works
7.1 Working at Heights: Fall Prevention, Fall Arrest & Rescue Systems 7.2 Scaffolding Standards, Competent Inspection & SANS 10085 (CR 16) 7.3 Temporary Works Management: Formwork, Falsework & Support Structures (CR 12)
8 Chapter 8: Excavations, Demolition & Heavy Plant Operations
8.1 Excavation Safety, Shoring, Battering & Underground Services (CR 13) 8.2 Demolition Work, Structural Assessment & Control Zones (CR 14) 8.3 Mobile Plant, Construction Vehicles & Cranes (CR 22, 23)
9 Chapter 9: Electrical Safety, Hazardous Chemicals & Confined Spaces
9.1 Temporary Electrical Installations, Distribution Boards & SANS 10142 (CR 24) 9.2 Hazardous Chemical Agents (HCA) & the Globally Harmonized System (GHS) 9.3 Confined Space Entry, Atmospheric Testing & Emergency Protocols (GSR 5)
10 Chapter 10: Incident Reporting, Statutory Notifications & Investigations
10.1 OHS Act Section 24 Statutory Reporting Criteria and Timeframes 10.2 Compensation for Occupational Injuries and Diseases Act (COIDA) Compliance 10.3 Incident Scene Preservation and Evidence Gathering Protocols 10.4 Root Cause Analysis Methodologies (5 Whys, Fishbone) & CAPA
11 Chapter 11: Safety Auditing, Worker Consultation & Site Training
11.1 Internal Audits, Client Oversight Audits & Scoring Protocols (CR 5(1)(o), CR 7(1)(c)) 11.2 Non-Conformance Reports (NCRs), Corrective Actions & Close-Out Mandatory Site Induction, Competency Verification & Training Programs (CR 7(5)–(7)) 11.4 Medical Surveillance, Certificate of Fitness & Hygiene Monitoring (CR 7(8))
12 Chapter 12: Health and Safety Management Systems, Performance & Culture
12.1 Health and Safety Management Systems & ISO 45001 12.2 Health and Safety Performance Measurement, Statistics & Trend Analysis 12.3 Leadership, People & Health and Safety Culture 12.4 Innovation & Technology in Construction Health and Safety
13 Chapter 13: Emergency Preparedness, Communication & Health and Safety Procurement
13.1 Emergency Preparedness, Fire Precautions & First Aid (CR 29, GSR 3) 13.2 Health and Safety Communication, Consultation, Meetings & Reporting 13.3 Health and Safety Procurement & Cost Management
14 Chapter 14: Physical Agents, Environmental Management & Specialised Site Controls
14.1 Noise, Physical Agents & Ergonomics on Construction Sites 14.2 Environmental Management on Construction Projects 14.3 Specialised Site Controls: Structures, Platforms, Hoists, Plant & Facilities (CR 11, 15, 17-21, 25-28, 30)
13.1 Emergency Preparedness, Fire Precautions & First Aid (CR 29, GSR 3)
Key Takeaways Explain This Topic AI
Construction Regulation 29 requires fire risk control, flammable storage, no smoking near combustibles, hot-work precautions, suitable extinguishers inspected by a competent person appointed in writing, trained workers, marked and clear escape routes, an evacuation plan and a fire siren.
General Safety Regulation 13J, added in 2025, covers outward-opening escape doors where practicable, clear exits, handrails, non-combustible fire-escape stairs, adequate egress widths and at least two means of egress where needed.
Under General Safety Regulation 3, a workplace with more than 5 employees needs a first aid box, and one with more than 10 needs at least one qualified first aider for every group of up to 50 employees.
Specific rescue duties apply to falls (CR 10(2)(e): rescue implemented immediately), rope access (CR 18(3)), confined spaces (GSR 5), work over water (CR 26: rescue provision and lifejackets) and silos (CR 20(7)).
An emergency plan is only effective if it is site-specific, communicated at induction, tested through drills, and reviewed after drills, incidents and changes in site layout.
Last updated: October 2026
1. Emergency Preparedness as a Core Knowledge Area
Emergency Preparedness Management is one of the SACPCMP core knowledge areas for construction health and safety registration. Construction sites change constantly: escape routes move as floors are built, flammable materials arrive in bulk, hot work is common, and many workers are new to the site. A CHSM must plan for fire, falls, collapse, entrapment, electrocution, chemical spills, flooding and medical emergencies, and must check that the plan works in practice.
2. Fire Precautions under Construction Regulation 29
Construction Regulation 29 requires a contractor to ensure that:
- (a) all appropriate measures are taken to avoid the risk of fire;
- (b) sufficient and suitable storage is provided for flammable liquids, solids and gases;
(c) smoking is prohibited, with prominent notices, in all places containing readily combustible or flammable materials;
(d) in confined spaces and other places where flammable gases, vapours or dust can cause danger, only suitably protected electrical installations and equipment (including portable lights) are used, there are no flames or similar ignition sources, no-smoking notices are displayed, oily rags and similar waste are removed without delay, and adequate ventilation is provided;
- (e) combustible materials do not accumulate on the site;
- (f) welding, flame cutting and other hot work are done only after appropriate precautions to reduce fire risk;
(g) suitable and sufficient fire-extinguishing equipment is placed at strategic locations, or as recommended by the fire chief or local authority, and kept in good working order;
(h) that equipment is inspected by a competent person appointed in writing , in the manner the manufacturer indicates;
- (i) a sufficient number of workers are trained in the use of fire-extinguishing equipment ;
- (j) where appropriate, suitable visual signs clearly indicate the escape routes;
- (k) the means of escape is kept clear at all times;
(l) there is an effective evacuation plan providing for all persons to be evacuated speedily without panic, all persons to be accounted for, and plant and processes to be shut down; and
(m) a siren is installed and sounded in the event of a fire.
CR 25 adds rules for flammable liquids on site: effective ventilation, no smoking with notices at entrances, fire-fighting equipment around the store, only one day's quantity taken out of the store, closed containers, bonding and earthing when decanting, and no storage of rags or paper with flammable liquids.
3. Means of Egress: General Safety Regulation 13J (2025)
The 2025 amendment to the General Safety Regulations (GN R. 5954 of 6 March 2025) added regulation 13J, "Fire precaution and means of egress" , which takes over the fire and egress rules previously found in the Environmental Regulations for Workplaces. To speed up evacuation, the employer must ensure that:
emergency escape doors open outwards as far as practicable;
doors of rooms, passages and staircases used as exits are kept clear and can be opened easily and rapidly from inside, including the outer escape exit;
staircases have substantial handrails;
staircases intended as fire escapes are made of non-combustible material, kept clear and do not end in an enclosed area;
escape staircases, passages and exits are wide enough and gentle enough for the number of people who will use them; and
having regard to the size, construction, location, number of people and activities, the workplace has at least two means of egress as far apart as practicable.
Regulation 13J(2) also requires an adequate supply of suitable fire-fighting equipment at strategic locations, or as recommended by the local authority's fire chief, maintained in good working order. On a building under construction, the CHSM checks these rules floor by floor as the structure rises, because temporary stairs and hoists often become the only escape routes.
4. First Aid: General Safety Regulation 3
GSR 3 requires the employer to:
take all reasonable steps to ensure that persons injured at work receive prompt first aid;
provide a first aid box where more than 5 employees are employed, containing at least the items listed in the annexure to the regulations;
where more than 10 employees are employed, ensure that for every group of up to 50 employees at least one person with a valid first aid certificate from an organisation approved by the chief inspector is readily available during normal working hours (the ratio is one per 100 in shops and offices); and
provide eye-wash and emergency shower facilities where there is a risk of corrosive or harmful substances splashing the eyes or body.
On a large site, the CHSM plans first aiders per work area and shift, not only per total headcount, so that help is close to every work face.
5. Specific Rescue Duties
Several regulations require rescue arrangements before work starts:
Falls from height : the fall protection plan must include a rescue plan with the procedure, personnel and equipment needed so that rescue is implemented immediately after a fall (CR 10(2)(e)).
Rope access : adequate measures must allow rescue to start immediately in the event of a fall (CR 18(3)).
Suspended platforms : workers must be trained in emergency procedures and equipment malfunction (CR 17(12)).
Confined spaces : GSR 5 requires testing, ventilation, isolation and, where the atmosphere may be dangerous, breathing apparatus, a harness and rope, and an attendant trained in resuscitation. Silos at bulk mixing plants are confined spaces (CR 20(7)).
Water : where work is over or near water, provision must be made to prevent falls into water and to rescue persons in danger of drowning, and lifejackets must be worn where there is a drowning risk (CR 26).
Excavations : collapse rescue must not send untrained people into an unsupported trench; plan for shoring, vacuum excavation and fire and rescue services.
6. Building the Site Emergency Plan
A site emergency plan, usually part of the principal contractor's health and safety plan, should cover:
Scenarios from the risk assessment: fire, fall, collapse, electrocution, gas release, flooding, severe weather, medical emergency and security incidents.
Roles : emergency co-ordinator, fire team, first aiders, wardens per area, and who calls the emergency services.
Alarm and communication : the CR 29(m) siren, distinct signals, radio channels and emergency numbers displayed at the gate.
Escape routes and assembly points : marked, kept clear and updated as the site changes, with roll-call arrangements to account for everyone, including visitors.
Shut-down : who isolates electricity, gas, cranes and hoists.
Access for emergency services : gate control, routes for fire engines and ambulances, and site plans available at the gate.
Equipment : extinguishers, first aid boxes, stretchers, rescue kits, spill kits and eye-wash stations, with inspection records.
Liaison : the local fire service, hospital and neighbours, especially for high-rise or high-risk work.
7. Testing and Review
Plans must be tested. Drills show whether the siren is heard on every floor, whether wardens know their areas and whether the roll call accounts for everyone. Fall-rescue drills show whether the rescue kit actually reaches a suspended worker within minutes. After every drill, incident or significant site change, the CHSM reviews the plan, updates induction content and records the lessons.