2.2 Designer Duties and Principal Contractor Obligations

SACPCMP Construction Health & Safety Manager Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: South African Occupational Health and Safety Legislation

1.1 The OHS Act Framework, General Duties of Employers and Employees 1.2 Corporate Governance and Section 16 Liability & Delegations 1.3 Worker Representation: Health & Safety Representatives and Committees 1.4 Mandatary Agreements, Acts/Omissions & Criminal Liability

2 Chapter 2: Construction Regulations 2014 & Legal Appointments

2.1 Construction Work Permits, Notifications & Client Duties 2.2 Designer Duties and Principal Contractor Obligations 2.3 Statutory Construction Supervision Appointments 2.4 The CHS Manager vs CHS Officer vs CHS Agent & Professional Registration

3 Chapter 3: Risk Assessment Methodologies & The HIRA Process

3.1 Fundamental Risk Terminology: Hazards, Risks, Consequences & Tolerability 3.2 The Three Tiers of HIRA: Baseline, Issue-Based & Continuous Risk Assessments 3.3 Risk Rating Matrices: Quantitative, Semi-Quantitative & Qualitative Scoring 3.4 Task-Based Risk Assessments (TBRA) & Workforce Participation

4 Chapter 4: Risk Control Hierarchy & Safe Work Procedures

4.1 The Hierarchy of Controls in Construction Operations 4.2 Developing and Implementing Safe Work Procedures (SWPs) and SOPs 4.3 Daily Safety Task Instructions (DSTI) and Pre-Task Risk Reviews

5 Chapter 5: Specifications, Plans & The Health and Safety File

5.1 Client Health and Safety Specifications 5.2 The Principal Contractor Health & Safety Plan: Structure and Approval 5.3 Compiling and Maintaining the Consolidated Health & Safety File 5.4 Subcontractor Safety File Verification and Onboarding

6 Chapter 6: Specialized Safety Plans, Method Statements & Registers

6.1 Comprehensive Fall Protection Planning (CR 10 Requirements) 6.2 Contractor Method Statements and Risk Alignment 6.3 Statutory Registers, Checklists, and Inspection Logs

7 Chapter 7: Working at Heights & Temporary Works

7.1 Working at Heights: Fall Prevention, Fall Arrest & Rescue Systems 7.2 Scaffolding Standards, Competent Inspection & SANS 10085 (CR 16) 7.3 Temporary Works Management: Formwork, Falsework & Support Structures (CR 12)

8 Chapter 8: Excavations, Demolition & Heavy Plant Operations

8.1 Excavation Safety, Shoring, Battering & Underground Services (CR 13) 8.2 Demolition Work, Structural Assessment & Control Zones (CR 14) 8.3 Mobile Plant, Construction Vehicles & Cranes (CR 22, 23)

9 Chapter 9: Electrical Safety, Hazardous Chemicals & Confined Spaces

9.1 Temporary Electrical Installations, Distribution Boards & SANS 10142 (CR 24) 9.2 Hazardous Chemical Agents (HCA) & the Globally Harmonized System (GHS) 9.3 Confined Space Entry, Atmospheric Testing & Emergency Protocols (GSR 5)

10 Chapter 10: Incident Reporting, Statutory Notifications & Investigations

10.1 OHS Act Section 24 Statutory Reporting Criteria and Timeframes 10.2 Compensation for Occupational Injuries and Diseases Act (COIDA) Compliance 10.3 Incident Scene Preservation and Evidence Gathering Protocols 10.4 Root Cause Analysis Methodologies (5 Whys, Fishbone) & CAPA

11 Chapter 11: Safety Auditing, Worker Consultation & Site Training

11.1 Internal Audits, Client Oversight Audits & Scoring Protocols (CR 5(1)(o), CR 7(1)(c)) 11.2 Non-Conformance Reports (NCRs), Corrective Actions & Close-Out Mandatory Site Induction, Competency Verification & Training Programs (CR 7(5)–(7)) 11.4 Medical Surveillance, Certificate of Fitness & Hygiene Monitoring (CR 7(8))

12 Chapter 12: Health and Safety Management Systems, Performance & Culture

12.1 Health and Safety Management Systems & ISO 45001 12.2 Health and Safety Performance Measurement, Statistics & Trend Analysis 12.3 Leadership, People & Health and Safety Culture 12.4 Innovation & Technology in Construction Health and Safety

13 Chapter 13: Emergency Preparedness, Communication & Health and Safety Procurement

13.1 Emergency Preparedness, Fire Precautions & First Aid (CR 29, GSR 3) 13.2 Health and Safety Communication, Consultation, Meetings & Reporting 13.3 Health and Safety Procurement & Cost Management

14 Chapter 14: Physical Agents, Environmental Management & Specialised Site Controls

14.1 Noise, Physical Agents & Ergonomics on Construction Sites 14.2 Environmental Management on Construction Projects 14.3 Specialised Site Controls: Structures, Platforms, Hoists, Plant & Facilities (CR 11, 15, 17-21, 25-28, 30)

2.2 Designer Duties and Principal Contractor Obligations

Key Takeaways Explain This Topic AI

CR 6(1)(c) requires the designer to give the client, before tender, a report covering health and safety information that affects pricing, geotechnical aspects and the design loads.

Designers carry out construction-stage inspections, stop non-conforming work and issue completion certificates only when mandated by the client; otherwise the client's agent does so (CR 6(1)(g)–(i)).

CR 7(1)(c) requires the principal contractor to vet, appoint in writing, audit at least every 30 days, and stop any contractor whose work is unsafe or departs from the plan.

A contractor that appoints another contractor takes on the principal contractor's CR 7(1)(b)–(g) duties for that contractor (CR 7(3)).

CR 7(5) bars anyone from entering a site without hazard-specific induction, CR 7(6) covers visitors, and CR 7(8) requires an Annexure 3 medical certificate issued by an occupational health practitioner.

Last updated: October 2026

  • 2.2 Designer Duties and Principal Contractor Obligations
  • Who Counts as a "Designer" (CR 1)

Under Construction Regulation 1, a designer is (a) a competent person who prepares a design, checks and approves a design, arranges for someone under their control to prepare a design, or designs temporary work and its components; (b) an architect or engineer contributing to, or having overall responsibility for, a design; (c) a building services engineer designing details for fixed plant; (d) a surveyor specifying articles or drawing up specifications; (e) a contractor carrying out design work as part of a design-and-build project; or (f) an interior designer, shop-fitter or landscape architect. The definition therefore reaches far beyond the structural engineer, including the temporary works designers who design falsework, formwork, shoring or scaffolds.

Construction Regulation 6 recognises that many construction-phase fatalities and serious injuries originate on the drawing board. Decisions about building geometry, materials, foundation depths and façade maintenance fix much of a project's hazard profile before a contractor arrives.

Duties of the Designer of a Structure (CR 6(1))

The designer of a structure must:

(a) ensure that the safety standards incorporated into the Regulations under Section 44 of the Act are complied with in the design;

(b) take into consideration the client's health and safety specification;

(c) before the contract goes to tender, make available in a report to the client all relevant health and safety information about the design that may affect the pricing of the work, the geotechnical-science aspects where appropriate, and the loading the structure is designed to withstand (the 2017 guideline note confirms that designs must be accompanied by this report);

(d) inform the client in writing of any known or anticipated dangers relating to the construction work, and make available the information needed to execute the work safely, including when the design is later altered;

(e) refrain from including anything in the design that necessitates dangerous procedures or hazardous materials that could be avoided by modifying the design or substituting materials;

(f) take into account hazards relating to subsequent maintenance of the structure and make provision in the design for that work to be performed with minimal risk;

(g) when mandated by the client , carry out inspections at appropriate stages to verify that the structure is being built in accordance with the design (if the designer is not mandated, the client's appointed agent is responsible for those inspections);

(h) when so mandated, stop any contractor executing work that is not in accordance with the design's health and safety aspects (otherwise the client's appointed agent must do so);

(i) when so mandated, include the health and safety aspects in the final inspection of the completed structure under the National Building Regulations, declare the structure safe for use, and issue a completion certificate to the client with a copy to the contractor (the published text letters this paragraph "(j)", so you will see two paragraphs lettered (j)); and

(j) during design, take cognisance of ergonomic design principles to minimise ergonomic hazards in all phases of the structure's life cycle.

A typical exam application of paragraph (e): rather than designing a low parapet that forces roof maintenance workers onto fall-arrest equipment, the designer specifies a permanent parapet or guardrail of adequate height, eliminating the hazard at design stage.

Duties of the Temporary Works Designer (CR 6(2))

The designer of temporary works must ensure that all temporary works are adequately designed to support all anticipated vertical and lateral loads; that the designs are prepared with close reference to the structural design drawings issued by the contractor, consulting the contractor where uncertain; that all drawings and calculations are kept at the temporary works designer's office and made available to an inspector on request; and that the loads caused by the temporary works and any imposed loads are clearly indicated in the design.

Duties of the Principal Contractor (CR 7(1))

The principal contractor (PC) holds primary operational responsibility on site. It must:

(a) provide and demonstrate to the client a suitable, sufficiently documented and coherent site-specific health and safety plan based on the client's specification, applied from commencement for the duration of the work and reviewed and updated as work progresses ;

(b) open and keep on site a health and safety file containing all documentation required by the Act and Regulations, available on request to an inspector, the client, the client's agent or a contractor;

(c) on appointing any other contractor:

  • (i) give contractors tendering for its work the relevant sections of the client's specification;
  • (ii) ensure potential contractors have made sufficient provision for health and safety measures;
  • (iii) appoint no contractor unless reasonably satisfied that it has the necessary competencies and resources;

(iv) ensure, before work starts, that every contractor is registered and in good standing with the Compensation Fund or a licensed compensation insurer;

  • (v) appoint each contractor in writing for its part of the project;
  • (vi) take reasonable steps to ensure each contractor's plan is implemented and maintained;

(vii) ensure periodic site audits and document verification at agreed intervals, but at least once every 30 days ;

(viii) stop any contractor whose work is not in accordance with the specification and plan or threatens the health and safety of persons;

  • (ix) make sufficient information and resources available when design or construction changes; and
  • (x) discuss and negotiate each contractor's plan and then finally approve it for implementation;

(d) make its own plan and the contractors' plans available on request to an employee, inspector, contractor, the client or the client's agent;

(e) hand over a consolidated health and safety file to the client on completion, including a record of all drawings, designs, materials used and similar information about the completed structure;

(f) keep in the file an updated list of all contractors on site accountable to it, the agreements between the parties and the type of work being done; and

(g) ensure all its employees have a valid medical certificate of fitness in the form of Annexure 3.

Duties of Every Contractor (CR 7(2)–(8))

Before performing any construction work, a contractor must provide and demonstrate to the PC a suitable health and safety plan based on the relevant sections of the client's specification; open and keep its own health and safety file on site; be reasonably satisfied that any contractor it appoints is competent and resourced; co-operate with the PC; and promptly give the PC any information that might affect health and safety or justify reviewing the plan (CR 7(2)). Where a contractor appoints another contractor, the PC duties in CR 7(1)(b) to (g) apply to it as if it were the PC (CR 7(3)). The PC must take reasonable steps to ensure co-operation between all the contractors it appoints (CR 7(4)).

Induction and Medical Certificates

CR 7(5): no contractor may allow any employee or other person to enter a site unless that person has undergone health and safety induction training on the hazards prevalent on the site at the time of entry.

CR 7(6): all visitors must undergo induction on the prevalent hazards and have the necessary personal protective equipment.

CR 7(7): induction records must be kept on site and made available to an inspector, the client, the client's agent or the PC.

CR 7(8): every contractor must ensure all its employees have a valid medical certificate of fitness specific to the work, issued by an occupational health practitioner in the form of Annexure 3 . Under Section 1 of the Act, that term covers an occupational medicine practitioner or a person with an occupational health qualification recognised by the medical or nursing council, such as an occupational health nurse. The regulation sets no fixed validity period; follow the expiry date on the certificate.

Designer vs Principal Contractor Statutory Matrix

  • Aspect Designer (CR 6) Principal Contractor (CR 7)
  • Core mandate Design for safe construction, maintenance and use Execute the work safely and manage contractors

Key deliverables Pre-tender report to client (pricing information, geotechnical aspects, design loads); written hazard information Site-specific H&S plan; H&S file; consolidated file at handover

Timing Design stage; inspections only when mandated by the client From site possession to handover

Contractor control May stop non-conforming work only when mandated (otherwise the client's agent does) Appoints, approves plans, audits at least every 30 days, stops unsafe work

Worker protection Avoidable dangerous procedures and materials designed out; ergonomic principles Induction (CR 7(5)–(7)); Annexure 3 medical certificates (CR 7(8))