Study guide

2.4 The CHS Manager vs CHS Officer vs CHS Agent & Professional Registration

SACPCMP Construction Health & Safety Manager Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: South African Occupational Health and Safety Legislation

1.1 The OHS Act Framework, General Duties of Employers and Employees 1.2 Corporate Governance and Section 16 Liability & Delegations 1.3 Worker Representation: Health & Safety Representatives and Committees 1.4 Mandatary Agreements, Acts/Omissions & Criminal Liability

2 Chapter 2: Construction Regulations 2014 & Legal Appointments

2.1 Construction Work Permits, Notifications & Client Duties 2.2 Designer Duties and Principal Contractor Obligations 2.3 Statutory Construction Supervision Appointments 2.4 The CHS Manager vs CHS Officer vs CHS Agent & Professional Registration

3 Chapter 3: Risk Assessment Methodologies & The HIRA Process

3.1 Fundamental Risk Terminology: Hazards, Risks, Consequences & Tolerability 3.2 The Three Tiers of HIRA: Baseline, Issue-Based & Continuous Risk Assessments 3.3 Risk Rating Matrices: Quantitative, Semi-Quantitative & Qualitative Scoring 3.4 Task-Based Risk Assessments (TBRA) & Workforce Participation

4 Chapter 4: Risk Control Hierarchy & Safe Work Procedures

4.1 The Hierarchy of Controls in Construction Operations 4.2 Developing and Implementing Safe Work Procedures (SWPs) and SOPs 4.3 Daily Safety Task Instructions (DSTI) and Pre-Task Risk Reviews

5 Chapter 5: Specifications, Plans & The Health and Safety File

5.1 Client Health and Safety Specifications 5.2 The Principal Contractor Health & Safety Plan: Structure and Approval 5.3 Compiling and Maintaining the Consolidated Health & Safety File 5.4 Subcontractor Safety File Verification and Onboarding

6 Chapter 6: Specialized Safety Plans, Method Statements & Registers

6.1 Comprehensive Fall Protection Planning (CR 10 Requirements) 6.2 Contractor Method Statements and Risk Alignment 6.3 Statutory Registers, Checklists, and Inspection Logs

7 Chapter 7: Working at Heights & Temporary Works

7.1 Working at Heights: Fall Prevention, Fall Arrest & Rescue Systems 7.2 Scaffolding Standards, Competent Inspection & SANS 10085 (CR 16) 7.3 Temporary Works Management: Formwork, Falsework & Support Structures (CR 12)

8 Chapter 8: Excavations, Demolition & Heavy Plant Operations

8.1 Excavation Safety, Shoring, Battering & Underground Services (CR 13) 8.2 Demolition Work, Structural Assessment & Control Zones (CR 14) 8.3 Mobile Plant, Construction Vehicles & Cranes (CR 22, 23)

9 Chapter 9: Electrical Safety, Hazardous Chemicals & Confined Spaces

9.1 Temporary Electrical Installations, Distribution Boards & SANS 10142 (CR 24) 9.2 Hazardous Chemical Agents (HCA) & the Globally Harmonized System (GHS) 9.3 Confined Space Entry, Atmospheric Testing & Emergency Protocols (GSR 5)

10 Chapter 10: Incident Reporting, Statutory Notifications & Investigations

10.1 OHS Act Section 24 Statutory Reporting Criteria and Timeframes 10.2 Compensation for Occupational Injuries and Diseases Act (COIDA) Compliance 10.3 Incident Scene Preservation and Evidence Gathering Protocols 10.4 Root Cause Analysis Methodologies (5 Whys, Fishbone) & CAPA

11 Chapter 11: Safety Auditing, Worker Consultation & Site Training

11.1 Internal Audits, Client Oversight Audits & Scoring Protocols (CR 5(1)(o), CR 7(1)(c)) 11.2 Non-Conformance Reports (NCRs), Corrective Actions & Close-Out Mandatory Site Induction, Competency Verification & Training Programs (CR 7(5)–(7)) 11.4 Medical Surveillance, Certificate of Fitness & Hygiene Monitoring (CR 7(8))

12 Chapter 12: Health and Safety Management Systems, Performance & Culture

12.1 Health and Safety Management Systems & ISO 45001 12.2 Health and Safety Performance Measurement, Statistics & Trend Analysis 12.3 Leadership, People & Health and Safety Culture 12.4 Innovation & Technology in Construction Health and Safety

13 Chapter 13: Emergency Preparedness, Communication & Health and Safety Procurement

13.1 Emergency Preparedness, Fire Precautions & First Aid (CR 29, GSR 3) 13.2 Health and Safety Communication, Consultation, Meetings & Reporting 13.3 Health and Safety Procurement & Cost Management

14 Chapter 14: Physical Agents, Environmental Management & Specialised Site Controls

14.1 Noise, Physical Agents & Ergonomics on Construction Sites 14.2 Environmental Management on Construction Projects 14.3 Specialised Site Controls: Structures, Platforms, Hoists, Plant & Facilities (CR 11, 15, 17-21, 25-28, 30)

2.4 The CHS Manager vs CHS Officer vs CHS Agent & Professional Registration

Key Takeaways Explain This Topic AI

Section 18(2) of the Project and Construction Management Professions Act bars practising in a registration category without being registered in it; contravention is an offence under Section 41(1).

GN 1181 of 2019 describes a CHSM as a competent person appointed by an employer to manage the planning and implementation of construction health and safety systems, with services in project stages 4 to 6.

CR 8(5) requires a contractor, after consulting the client, to appoint a full- or part-time construction health and safety officer, with no fixed headcount trigger; CR 8(6) requires SACPCMP registration.

Under the SACPCMP Rules for Registration effective 1 August 2025, CHSM applicants need an NQF 6 (240-credit) qualification or RPL plus at least five years' relevant experience.

SACPCMP examinations are online and proctored with a 60% pass mark; 35–59% allows a rewrite within six months, while 0–34% archives the application.

Last updated: October 2026

  • 2.4 The CHS Manager vs CHS Officer vs CHS Agent & Professional Registration
  • Legislative Framework for Professional Registration

Construction health and safety practitioners are registered under the Project and Construction Management Professions Act, 2000 (Act 48 of 2000) by the South African Council for the Project and Construction Management Professions (SACPCMP) . Section 18 of that Act lets the Council prescribe "specified categories" in addition to the professional and candidate categories. Section 18(2) provides that a person may not practise in a category unless registered in it, and contravention is an offence under Section 41(1). Section 26 provides for the identification of work reserved for each category.

The Construction Regulations then make registration a legal precondition for the two roles they name:

Client's agent: must be registered with a statutory body approved by the Chief Inspector (CR 5(7)(b)).

Construction health and safety officer: a contractor may not appoint one unless reasonably satisfied that the person is registered with such a body and has the necessary competencies and resources (CR 8(6)).

The Three SACPCMP Construction Health and Safety Categories

The Rules for Registration list the specified categories Professional Construction Health and Safety Agent (PrCHSA) , Construction Health and Safety Manager (CHSM) and Construction Health and Safety Officer (CHSO) , each with a matching candidate category (Can CHSA, Can CHSM, Can CHSO). Their "level descriptors" come from the scope of work gazetted by the Council for the Built Environment ( Government Notice 1181 of 20 September 2019 ):

Category Level descriptor (GN 1181 of 2019) Typical position

PrCHSA A competent person who acts as a representative for a client in managing health and safety on a construction project Client's agent under CR 5(5)–(7), from project initiation to close-out

CHSM A competent person appointed by an employer to manage the planning and implementation of construction health and safety systems Contractor's (or, on suitable projects, client's) health and safety manager

CHSO A person appointed by an employer to assist site management with planning, implementing and managing construction health and safety systems Site officer appointed under CR 8(5)

The SAQA record for the CHSM designation adds that a CHSM must show detailed knowledge of construction health and safety requirements at managerial and operational levels, the ability to design, compile and implement or manage the health and safety requirements for a project, and the ability to mentor, coach and guide CHSOs.

The CHSM's Gazetted Scope of Services

GN 1181 lists CHSM services from project stage 4 onwards (the CHSM has no stage 1–3 services; those belong to the client's agent):

Stage 4 – Tender documentation and procurement: attend tender clarification meetings; review the documentation programme; finalise the baseline risk assessment; identify precautions and develop health and safety plans from the specification; agree the format of the health and safety file; help with health and safety cost estimates and budgets; manage the health and safety documents issued to tendering contractors; facilitate evaluation of contractors' competencies and resources; and facilitate health and safety contract documentation.

Stage 5 – Construction: attend site handover; facilitate the site-specific plan; ensure documents reach the authorities; manage assessment and approval of other contractors' plans; run health and safety meetings; ensure hazards are identified through coordinated inspections; manage communication structures; evaluate emergency response plans; monitor and report performance through compliance audits; evaluate contractor compliance; manage incident reporting and investigation; manage non-compliance and corrective and preventive action; review the management system; use trend analysis; manage changes to plans; and present technical reports to decision-makers.

Stage 6 – Close-out: review and approve contractors' consolidated files; manage site safety during the defects liability period ; and prepare the consolidated project health and safety file for the client.

The 2017 guideline note to CR 5 also allows a client to appoint a CHSA or a CHSM , depending on the scope and risk profile of the work, to represent it on health and safety matters.

The Construction Health and Safety Officer Appointment (CR 8(5)–(6))

A contractor must, after consulting the client and having considered the size of the project, the degree of danger and the accumulation of hazards or risks, appoint a full-time or part-time construction health and safety officer in writing. Where it is unclear whether an officer is needed, the inspector's decision is decisive. The regulation sets no headcount threshold: a small but high-risk job may justify a full-time officer, while a larger low-risk one may not. Many client specifications add their own ratios.

Becoming Registered as a CHSM

Under the SACPCMP Rules for Registration (version 3, effective 1 August 2025):

Qualification and experience: an NQF level 6 qualification of 240 credits on the Council's recognition list (or an RPL certificate), plus at least five years of relevant practical experience. Candidate CHSMs (Can CHSM) need the qualification but no experience, and log their experience in a mentored logbook.

Application: apply on the online construction health and safety portal (myCHS), watch the mandatory application video, and submit certified documents, a CV and an eligibility assessment report : a 3 000-word report on successes and challenges across ten knowledge areas (planning, implementation and management; procurement; cost; hazard identification; risk; accident or incident investigation; legislation and regulations; health, hygiene and environment; communication; emergency preparedness).

Eligibility assessment: two assessors must both recommend progression; if they disagree, a third assessor decides.

Competency assessment: a professional interview or examination . Examinations are online and virtually proctored ; points and time are set in advance for each paper, and the Council does not publish a standard question count. The pass mark is 60% . A candidate scoring 35–59% may rewrite within six months after paying the re-examination fee; 0–34% means the application is archived and a fresh application is needed.

Code of Conduct, CPD and Discipline

Registered persons must comply with the Council's Code of Conduct : putting the health and safety of workers and the public first, working only within their competence, avoiding conflicts of interest, and refusing to sign off unsafe plans or falsified records under commercial pressure. To keep registration they must comply with the SACPCMP CPD Policy and pay the annual fee ; failure leads to deregistration. The SAQA record for the designation summarises the CPD framework (Board Notice 75 of 2012) as a five-year cycle of 52 points: Category A (core and non-core knowledge) 60%, Category B (mentorship and development) 20% and Category C (ongoing practice) 20%. Check the current policy before relying on point values. Complaints of improper conduct are investigated under the Act and may lead to a disciplinary hearing, with sanctions up to removal from the register.

SACPCMP Categories Comparison Matrix

Attribute PrCHSA CHSM CHSO

Statutory hook CR 5(5)–(7) client's agent Employer's H&S manager; may represent client per 2017 guideline note CR 8(5)–(6) contractor's officer

Project stages (GN 1181) Stages 1 to 6 Stages 4 to 6 Construction stage

Key functions Specification, design-risk review, plan approval, client audits, stop-work Plans, contractor evaluation, audits, incident management, trend analysis, close-out file Site inspections, registers, induction, minor investigations, support to supervisors

Typical employer Client or consultancy Principal contractor, contractor or client Contractor