1 Chapter 1: South African Occupational Health and Safety Act (OHS Act 85 of 1993)
1.1 Scope, Purpose, and General Employer Duties (Sections 8, 9, 10) 1.2 Employee Duties, Rights, and Health & Safety Representation (Sections 14, 17, 18, 19, 20) 1.3 Corporate Governance, Accountability, and Mandatary Agreements (Sections 16, 37, 44)
2 Chapter 2: Construction Regulations 2014: Governance & Key Roles
2.1 Scope, Construction Work Permits, and Notifications (Regulations 1, 3, 4, Annexure 2) 2.2 Statutory Duties of Clients, Designers, and Principal Contractors (Regulations 5, 6, 7) 2.3 Site Supervision and Management Appointments (Regulation 8: CR 8(1), 8(2), 8(5), 8(7), 8(8))
3 Chapter 3: Compensation, Liability, and Administrative Regulations
3.1 Compensation for Occupational Injuries and Diseases Act (COIDA 130 of 1993) & Civil Liability 3.2 General Administrative Regulations (GAR) 2003: Reporting & Investigating Provisions 3.3 SACPCMP Statutory Mandate, Registration Rules, and Code of Conduct
4 Chapter 4: Risk Assessment Methodologies & Types
4.1 The Three Tiers of Construction Risk Assessment: Baseline, Issue-Based, and Continuous (CR 9) 4.2 Qualitative and Semi-Quantitative Risk Scoring (Probability, Severity, Matrix Evaluation) 4.3 Hierarchy of Risk Controls: From Elimination to Personal Protective Equipment
5 Chapter 5: Safe Work Procedures, Method Statements & Dynamic Risk
5.1 Developing Safe Work Procedures (SWPs) from Risk Assessments 5.2 Safe Work Method Statements (SWMS) and Task Execution 5.3 Daily Safe Task Instructions (DSTI), Toolbox Talks, and Dynamic Site Risk Management
6 Chapter 6: Health and Safety File & Planning Documentation
6.1 Client Health and Safety Specifications vs. Principal Contractor Health and Safety Plan 6.2 Structure, Contents, and Maintenance of the Site Health and Safety File (CR 7(1)(b), 7(2)(b) & 7(1)(e)) 6.3 Contractor Vetting, Approval, and Monthly Compliance Auditing (CR 5(1)(o) & CR 7)
7 Chapter 7: Statutory Registers, Checklists & Legal Appointments
7.1 Equipment and Plant Registers: Scaffolding, Ladders, and Portable Electrical Tools 7.2 Medical, Occupational Hygiene, and PPE Registers 7.3 Compiling, Signing, and Enforcing Legal Letters of Appointment on Site
8 Chapter 8: High-Risk Works: Working at Heights & Scaffolding
8.1 Fall Protection Plans, Fall Prevention, and Fall Arrest Systems (CR 10) 8.2 Scaffolding Erection, Tagging, and SANS 10085 Standards (CR 16) 8.3 Suspended Platforms, Boatswain's Chairs, and Rope Access (CR 17 & CR 18)
9 Chapter 9: Groundworks, Temporary Works & Heavy Operations
9.1 Excavations, Shoring, and Ground Stability Safeguards (CR 13) 9.2 Temporary Works, Formwork, and Support Work Safety (CR 12) 9.3 Cranes, Material Hoists, and Mobile Plant Operations (CR 19, CR 22, CR 23, DMR 18)
10 Chapter 10: Site Infrastructure, Fire, Electrical & Occupational Health
10.1 Temporary Electrical Installations and Portable Electrical Tools (CR 24 & SANS 10142) 10.2 Fire Precautions, Flammable Store Management, and Housekeeping (CR 25, 27, 28, 29) 10.3 Occupational Health Hazards: Noise Zones, Hazardous Chemical Agents, and Facilities (CR 30)
11 Chapter 11: Incident Notification, Reporting & Statutory Investigations
11.1 Section 24 Reportable Incidents vs. Minor Work Injuries: Thresholds and Windows 11.2 Incident Scene Management, Evidence Preservation, and Witness Interviewing 11.3 Incident Investigation Methodologies (GAR 9, 5 Whys, Root Cause Analysis) and CAPA
12 Chapter 12: Emergency Preparedness, First Aid & Safety Culture
12.1 Site Emergency Preparedness Plans, Evacuation Drills, and Alarms (CR 29) 12.2 First Aid Requirements, Box Standards, and Emergency Medical Services (GSR 3) 12.3 Mandatory Site Induction, Worker Participation, and Refusal of Dangerous Work
13 Chapter 13: Health and Safety Management Systems and Governance
13.1 Health and Safety Management Systems: ISO 45001 and the Plan-Do-Check-Act Cycle 13.2 Health and Safety Policy, Organising, and the Section 16(2) Chain of Accountability 13.3 Documented Information, Internal Audit, and Management Review
14 Chapter 14: Health and Safety Performance, Auditing and Reviews
14.1 Measuring Health and Safety Performance: Leading Indicators, DIFR and LTIFR 14.2 Inspections, Audits and Legal Compliance Auditing 14.3 Non-conformance, Corrective Action and Continual Improvement
15 Chapter 15: Health and Safety Procurement, Cost and Contractor Management
15.1 Health and Safety in Procurement and Tendering 15.2 Health and Safety Cost Management: Pricing, Budgeting and the Cost of Failure 15.3 Contractor Management Through the Project Life Cycle
16 Chapter 16: Communication, Safety Culture and Technology
16.1 Health and Safety Communication Management and Reporting to Decision Makers 16.2 People, Safety Culture and Worker Participation 16.3 Innovation and Technology in Construction Health and Safety
17 Chapter 17: Occupational Hygiene, Medical Surveillance, Environment and Ergonomics
17.1 Hazardous Chemical Agents, Asbestos and Lead on Construction Sites 17.2 Medical Surveillance and the Annexure 3 Certificate of Fitness 17.3 Environmental Management on Construction Sites 17.4 Ergonomics, Manual Handling and Physical Agents
18 Chapter 18: Enforcement, Standards and Remaining High-Risk Construction Works
18.1 Enforcement: Inspector Powers, Notices, Inquiries and Penalties 18.2 Incorporated Standards, SANS and Personal Protective Equipment Selection 18.3 Demolition Work and Structural Stability 18.4 Tunnelling, Water Environments, Bulk Mixing Plant, Material Hoists and Explosive Actuated Devices 18.5 Hazard Identification Techniques and Permit-to-Work Systems
18.2 Incorporated Standards, SANS and Personal Protective Equipment Selection
Key Takeaways Explain This Topic AI
Section 44 lets the Minister incorporate a health and safety standard by reference, and section 44(3) deems an incorporated standard to be a regulation two months after incorporation.
CR 16(2), CR 17(2)(a) and CR 18(2)(a) all incorporate standards under section 44, which is why the SANS 10085-1 scaffold inspection regime is enforceable law although it appears nowhere in the text of CR 16.
Section 44(4) makes incorporation dynamic: the duty follows later amendments or substitutions of the standard unless the incorporating notice says otherwise.
Section 23 makes PPE an employer cost without exception, and sections 38(1)(n) and 38(1)(o) make tampering with or failing to use provided safety equipment offences.
PPE selection fails on compatibility more often than absence: fall clearance calculations, respirator face-fit testing, helmet retention in fall risk positions and over-attenuating hearing protection are the recurring traps.
Last updated: September 2026
18.2 Incorporated Standards, SANS and Personal Protective Equipment Selection
Note
SACPCMP Blueprint Context : "Health and Safety Standards" is item 8 of the Construction Health and Safety core knowledge list in Annexure B and a separate heading in the Annexure G candidate logbook. The mechanism by which a voluntary South African National Standard becomes enforceable law — section 44 of the OHS Act — is one of the most commonly misunderstood pieces of the framework.
1. How a Standard Becomes Law: Section 44
Section 44(1) — the Minister may by notice in the Gazette incorporate in the regulations any health and safety standard or part of it, without stating the text , by mere reference to its number, title and year of issue. Section 44(2) — no standard may be incorporated except after consultation with the Advisory Council. Section 44(3) — an incorporated standard is, for the purposes of the Act and in so far as it is not repugnant to a regulation made under section 43, deemed to be a regulation , but not before the expiry of two months from the date of incorporation. Section 44(4) — where the standard is later amended or substituted by the competent authority, the incorporating notice is deemed to refer to the amended or substituted standard, unless it says otherwise. Section 44(5) — the chief inspector keeps a register of particulars of every publication in which an incorporated standard is published.
Three consequences a CHSO must be able to state:
An incorporated standard has the force of a regulation. Breaching it is not a breach of good practice; it is a statutory contravention.
The incorporation is dynamic. Section 44(4) means the duty follows the current edition of the standard unless the notice states otherwise — so a contractor working to a superseded edition is not automatically compliant.
Not every SANS standard is incorporated. The critical professional discipline is knowing which are, and describing the rest accurately as good practice rather than law.
2. Where the Construction Regulations Point to Incorporated Standards
The Construction Regulations 2014 use section 44 by cross-reference rather than by naming standards:
Provision What it incorporates
CR 16(2) A contractor using access scaffolding must ensure that the scaffolding, when in use, complies with the safety standards incorporated for this purpose into these Regulations under section 44 of the Act — in practice SANS 10085-1 , The design, erection, use and inspection of access scaffolding
CR 17(2)(a) The design, stability and construction of a suspended platform must comply with the safety standards incorporated under section 44
CR 18(2)(a) The design, selection and use of rope access equipment and anchors must comply with the safety standards incorporated under section 44
This is why the seven-day scaffold inspection interval is legally binding even though it appears nowhere in the text of Construction Regulation 16: CR 16(2) incorporates the standard, and section 44(3) deems the standard to be a regulation.
Other regulations point to standards directly. CR 24 requires compliance with the Electrical Installation Regulations, 2009 and the Electrical Machinery Regulations, 1988; the wiring code applied under the Electrical Installation Regulations is SANS 10142-1 . CR 22 requires compliance with the Driven Machinery Regulations. CR 25 and CR 29 operate alongside the Environmental Regulations for Workplaces, 1987, and CR 30(1) alongside the Facilities Regulations, 2004.
3. Standards a Construction Health and Safety Officer Encounters
- Standard Subject
- SANS 10085-1 Design, erection, use and inspection of access scaffolding
- SANS 10142-1 Wiring of premises: low-voltage installations
- SANS 10400 series Application of the National Building Regulations, including Part T (fire protection)
- SANS 1186 series Symbolic safety signs
- SANS 1475 / SANS 10105 series Portable fire extinguishers: manufacture, servicing and use
- SANS 10089 series Petroleum products: storage and handling of flammable liquids
- SANS 10083 / SABS 083 Measurement and assessment of occupational noise for hearing conservation
- SANS 50795 / EN 795 Anchor devices for personal fall protection
- SANS 10333 series Personal protective equipment: selection, use and maintenance
Important
Cite a standard correctly or not at all. In an examination answer, "SANS 10085-1, incorporated by CR 16(2) under section 44 of the Act" is correct. "Construction Regulation 16 requires a seven-day scaffold inspection" is not, because that interval is in the standard rather than the regulation. Precision here distinguishes a registered professional from a technician.
4. Personal Protective Equipment: Where It Sits and Who Pays
PPE is the last level of the hierarchy of controls, and South African law treats it accordingly.
Section 8(2)(d) requires the employer to establish the hazards and the precautionary measures. CR 10(4)(d) goes further for work at height, prohibiting reliance on fall arrest equipment where it is reasonably practicable to use fall prevention equipment. The professional discipline is that PPE is specified after the higher controls have been exhausted and documented, not instead of them.
Section 23 prohibits an employer from levying or permitting any levy on an employee in respect of anything the employer must provide or do in the interest of the employee's health and safety. PPE is therefore an employer cost without exception, and section 38(4) requires a court convicting an employer under section 23 to determine the amount deducted and deal with it as an underpayment.
Section 14(c) requires employees to carry out lawful orders and obey health and safety rules, and section 38(1)(o) makes it an offence for a person to fail to use safety equipment provided at a workplace, while section 38(1)(n) makes it an offence to tamper with or misuse safety equipment. Enforcement therefore runs in both directions: the employer must provide, and the employee must use.
5. Selecting PPE Properly
Selection is a technical decision, not a catalogue choice. For each hazard the CHSO should be able to state the hazard, the required performance, the standard, and the fit or compatibility constraint.
Hazard Selection driver Compatibility trap
Head impact and falling objects Industrial safety helmet with retention system; replace after any impact and per the manufacturer's life Chin strap essential where a fall risk exists — an unsecured helmet leaves the head at the moment of a fall
Falls from height Full body harness with the correct attachment point; energy-absorbing lanyard sized to available clearance; anchor rated and certified Fall clearance calculation : lanyard length plus deceleration distance plus the worker's height below the attachment plus a safety margin must be less than the available fall distance, or the worker strikes the ground with the system fully deployed
Respirable dust and fume Filter class matched to the agent; assigned protection factor matched to the exposure Face-fit testing for each wearer and each model; a facial seal is impossible over beard growth at the seal line
Noise at or above the 85 dBA rating limit Attenuation matched to the exposure, not the highest available Over-attenuation isolates the worker from reversing alarms and verbal warnings
Eye and face Impact grade for grinding; shade number for welding; chemical splash goggles rather than spectacles for liquids Prescription spectacles under a face shield; fogging drives non-compliance more than any other factor
Hands Cut level for handling steel and glass; chemical permeation data for the specific substance Cut-resistant gloves that cannot grip wet steel will be removed
Feet Toe protection, midsole penetration resistance, slip resistance, electrical properties where relevant Ankle support on uneven civils ground
Skin and cement Barrier and cover for alkaline wet cement Cement dermatitis and burns are usually a clothing and washing-facility problem before they are a glove problem
Warning
The most common PPE failure on South African sites is not absence but incompatibility. A worker issued a respirator that cannot seal, a helmet without a chin strap in a fall risk position, gloves that prevent grip, or hearing protection that masks a reversing alarm will defeat the control. Issue records prove issue; the CHSO's field verification proves use, fit and compatibility — and that verification is the control that matters.