13.3 Documented Information, Internal Audit, and Management Review

SACPCMP Construction Health & Safety Officer CHSO

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: South African Occupational Health and Safety Act (OHS Act 85 of 1993)

1.1 Scope, Purpose, and General Employer Duties (Sections 8, 9, 10) 1.2 Employee Duties, Rights, and Health & Safety Representation (Sections 14, 17, 18, 19, 20) 1.3 Corporate Governance, Accountability, and Mandatary Agreements (Sections 16, 37, 44)

2 Chapter 2: Construction Regulations 2014: Governance & Key Roles

2.1 Scope, Construction Work Permits, and Notifications (Regulations 1, 3, 4, Annexure 2) 2.2 Statutory Duties of Clients, Designers, and Principal Contractors (Regulations 5, 6, 7) 2.3 Site Supervision and Management Appointments (Regulation 8: CR 8(1), 8(2), 8(5), 8(7), 8(8))

3 Chapter 3: Compensation, Liability, and Administrative Regulations

3.1 Compensation for Occupational Injuries and Diseases Act (COIDA 130 of 1993) & Civil Liability 3.2 General Administrative Regulations (GAR) 2003: Reporting & Investigating Provisions 3.3 SACPCMP Statutory Mandate, Registration Rules, and Code of Conduct

4 Chapter 4: Risk Assessment Methodologies & Types

4.1 The Three Tiers of Construction Risk Assessment: Baseline, Issue-Based, and Continuous (CR 9) 4.2 Qualitative and Semi-Quantitative Risk Scoring (Probability, Severity, Matrix Evaluation) 4.3 Hierarchy of Risk Controls: From Elimination to Personal Protective Equipment

5 Chapter 5: Safe Work Procedures, Method Statements & Dynamic Risk

5.1 Developing Safe Work Procedures (SWPs) from Risk Assessments 5.2 Safe Work Method Statements (SWMS) and Task Execution 5.3 Daily Safe Task Instructions (DSTI), Toolbox Talks, and Dynamic Site Risk Management

6 Chapter 6: Health and Safety File & Planning Documentation

6.1 Client Health and Safety Specifications vs. Principal Contractor Health and Safety Plan 6.2 Structure, Contents, and Maintenance of the Site Health and Safety File (CR 7(1)(b), 7(2)(b) & 7(1)(e)) 6.3 Contractor Vetting, Approval, and Monthly Compliance Auditing (CR 5(1)(o) & CR 7)

7 Chapter 7: Statutory Registers, Checklists & Legal Appointments

7.1 Equipment and Plant Registers: Scaffolding, Ladders, and Portable Electrical Tools 7.2 Medical, Occupational Hygiene, and PPE Registers 7.3 Compiling, Signing, and Enforcing Legal Letters of Appointment on Site

8 Chapter 8: High-Risk Works: Working at Heights & Scaffolding

8.1 Fall Protection Plans, Fall Prevention, and Fall Arrest Systems (CR 10) 8.2 Scaffolding Erection, Tagging, and SANS 10085 Standards (CR 16) 8.3 Suspended Platforms, Boatswain's Chairs, and Rope Access (CR 17 & CR 18)

9 Chapter 9: Groundworks, Temporary Works & Heavy Operations

9.1 Excavations, Shoring, and Ground Stability Safeguards (CR 13) 9.2 Temporary Works, Formwork, and Support Work Safety (CR 12) 9.3 Cranes, Material Hoists, and Mobile Plant Operations (CR 19, CR 22, CR 23, DMR 18)

10 Chapter 10: Site Infrastructure, Fire, Electrical & Occupational Health

10.1 Temporary Electrical Installations and Portable Electrical Tools (CR 24 & SANS 10142) 10.2 Fire Precautions, Flammable Store Management, and Housekeeping (CR 25, 27, 28, 29) 10.3 Occupational Health Hazards: Noise Zones, Hazardous Chemical Agents, and Facilities (CR 30)

11 Chapter 11: Incident Notification, Reporting & Statutory Investigations

11.1 Section 24 Reportable Incidents vs. Minor Work Injuries: Thresholds and Windows 11.2 Incident Scene Management, Evidence Preservation, and Witness Interviewing 11.3 Incident Investigation Methodologies (GAR 9, 5 Whys, Root Cause Analysis) and CAPA

12 Chapter 12: Emergency Preparedness, First Aid & Safety Culture

12.1 Site Emergency Preparedness Plans, Evacuation Drills, and Alarms (CR 29) 12.2 First Aid Requirements, Box Standards, and Emergency Medical Services (GSR 3) 12.3 Mandatory Site Induction, Worker Participation, and Refusal of Dangerous Work

13 Chapter 13: Health and Safety Management Systems and Governance

13.1 Health and Safety Management Systems: ISO 45001 and the Plan-Do-Check-Act Cycle 13.2 Health and Safety Policy, Organising, and the Section 16(2) Chain of Accountability 13.3 Documented Information, Internal Audit, and Management Review

14 Chapter 14: Health and Safety Performance, Auditing and Reviews

14.1 Measuring Health and Safety Performance: Leading Indicators, DIFR and LTIFR 14.2 Inspections, Audits and Legal Compliance Auditing 14.3 Non-conformance, Corrective Action and Continual Improvement

15 Chapter 15: Health and Safety Procurement, Cost and Contractor Management

15.1 Health and Safety in Procurement and Tendering 15.2 Health and Safety Cost Management: Pricing, Budgeting and the Cost of Failure 15.3 Contractor Management Through the Project Life Cycle

16 Chapter 16: Communication, Safety Culture and Technology

16.1 Health and Safety Communication Management and Reporting to Decision Makers 16.2 People, Safety Culture and Worker Participation 16.3 Innovation and Technology in Construction Health and Safety

17 Chapter 17: Occupational Hygiene, Medical Surveillance, Environment and Ergonomics

17.1 Hazardous Chemical Agents, Asbestos and Lead on Construction Sites 17.2 Medical Surveillance and the Annexure 3 Certificate of Fitness 17.3 Environmental Management on Construction Sites 17.4 Ergonomics, Manual Handling and Physical Agents

18 Chapter 18: Enforcement, Standards and Remaining High-Risk Construction Works

18.1 Enforcement: Inspector Powers, Notices, Inquiries and Penalties 18.2 Incorporated Standards, SANS and Personal Protective Equipment Selection 18.3 Demolition Work and Structural Stability 18.4 Tunnelling, Water Environments, Bulk Mixing Plant, Material Hoists and Explosive Actuated Devices 18.5 Hazard Identification Techniques and Permit-to-Work Systems

13.3 Documented Information, Internal Audit, and Management Review

Key Takeaways Explain This Topic AI

The Construction Regulations 2014 make a specific list of documents compulsory, including the CR 7(1)(a) health and safety plan, the CR 7(1)(b) site file, CR 10(2) fall protection plan, and the CR 12(3)(f), CR 13(2)(h), CR 23(1)(k) and CR 24(d)-(e) inspection registers.

Retention periods differ by record type: at least three years for the GAR 9(1) Annexure 1 record and GAR 5(b) committee records, and at least ten years for the service history of leased lifting equipment under DMR 18(7)(c).

CR 5(1)(o) and CR 7(1)(c)(vii) both require audits and document verification at intervals not exceeding 30 days, and CR 5(1)(p) requires the client's audit report to reach the principal contractor within seven days.

An audit examines the system that produces safe conditions and requires independence from the activity audited, whereas an inspection examines the physical condition of plant, structures or work.

ISO 45001 clause 9.3 requires management review outputs to be decisions on suitability, improvement, change and resources - which under CR 7(1)(a) must feed back into a revised health and safety plan.

Last updated: September 2026

13.3 Documented Information, Internal Audit, and Management Review

Note

SACPCMP Blueprint Context : This section completes the management-system chapter by covering the Check and Act clauses of ISO 45001 (clauses 7.5, 9.2 and 9.3) and their South African statutory analogues. It connects directly to Annexure B item 4, "Health and Safety Performance (audit and reviews)", which Chapter 14 then develops in measurement detail.

1. Documented Information: What Must Exist, and Why

ISO 45001 clause 7.5 uses the term documented information to cover both what older standards called "documents" (things that specify how work is done) and "records" (evidence that it was done). On a South African construction site the statutory documentation load is heavy, and a CHSO must know which items are legally compulsory and which are system choices.

Document Statutory source Compulsory?

  • Baseline risk assessment CR 5(1)(a) (client), CR 9 Yes
  • Client health and safety specification CR 5(1)(b) Yes
  • Principal contractor's health and safety plan CR 7(1)(a) Yes
  • Health and safety file, on site CR 7(1)(b), CR 7(2)(b) Yes
  • Consolidated file handed to client on completion CR 7(1)(e) Yes
  • Register of contractors on site, agreements, type of work CR 7(1)(f) Yes
  • Medical certificates of fitness (Annexure 3) CR 7(1)(g), CR 7(8) Yes
  • Induction training records kept on site CR 7(7) Yes
  • Fall protection plan CR 10(1)(a), CR 10(2) Yes
  • Excavation inspection register CR 13(2)(h) Yes
  • Temporary works inspection register CR 12(3)(f) Yes
  • Temporary electrical installation register CR 24(d) Yes
  • Electrical machinery daily checklist register CR 24(e) Yes
  • Construction vehicle / mobile plant daily register, kept in the vehicle CR 23(1)(k) Yes
  • Annexure 1 incident record, kept at the workplace at least three years GAR 9(1) Yes
  • Health and safety committee records, kept at least three years GAR 5(b) read with s 20(2) Yes
  • Copy of the Act and relevant regulations available at the workplace (five or more employees) GAR 4 Yes
  • ISO 45001 procedure manual, KPI dashboard, audit schedule — System choice

Important

Retention is not uniform. GAR 9(1) requires the Annexure 1 record to be kept for at least three years . GAR 5(b) requires health and safety committee records under section 20(2) to be kept for at least three years . Occupational medical surveillance records under the Hazardous Chemical Agents Regulations and the Asbestos Abatement Regulations carry far longer retention — up to 40 years after the last exposure entry for certain agents — and are held confidentially by the occupational medicine practitioner, not in the site file. DMR 18(7)(c) requires the owner and lessor of leased lifting equipment to keep full service history records for at least 10 years . Do not average these into a single "three-year rule".

Document control on a construction site fails in predictable ways: superseded method statements left in the file next to the current one; a temporary works drawing without a revision number; an appointment letter for a person who left three months ago. The control that matters is not a fancy register — it is a single named person who removes superseded versions the day they are superseded.

2. The Internal Audit Programme

Clause 9.2 of ISO 45001 requires internal audits at planned intervals. South African law supplies its own audit obligations, and they are stricter in frequency than most management systems:

CR 5(1)(o) : the client must ensure that periodic health and safety audits and document verification are conducted at intervals mutually agreed between the principal contractor and any contractor, but at least once every 30 days .

CR 5(1)(p) : a copy of that audit report must be provided to the principal contractor within seven days after the audit.

CR 7(1)(c)(vii) : the principal contractor must ensure that periodic site audits and document verification are conducted at intervals mutually agreed with any contractor, but at least once every 30 days .

Three attributes separate an audit from an inspection, and examiners test the distinction:

Inspection Audit

Object The physical condition of plant, structures or work The system that is supposed to produce safe conditions

Question "Is this scaffold safe today?" "Does the process that inspects scaffolds work, and can you evidence it?"

Frequency Daily to weekly, driven by regulation and standard At planned intervals; on site at least every 30 days by law

  • Output Register entry, tag status Findings, non-conformances, corrective action requests
  • Who Appointed competent person for that plant A person independent of the activity being audited

Independence is the attribute most often compromised. A scaffold inspector cannot meaningfully audit the scaffold inspection process. On a small site independence may mean a colleague from another section or a group safety manager, but it must mean someone other than the person who performs the work .

3. Non-conformance and Corrective Action

Clause 10.2 of ISO 45001 requires an organisation to react to non-conformities and incidents, evaluate the need for action to eliminate the root cause so the non-conformity does not recur, and review the effectiveness of the action taken. The South African statutory mirror is GAR 9: the incident is recorded in Annexure 1 (GAR 9(1)), investigated within seven days (GAR 9(2)), the findings entered in Annexure 1 immediately after completion (GAR 9(3)), and the record examined by the health and safety committee at its next meeting with the necessary actions implemented and followed up to prevent recurrence (GAR 9(4)).

A workable corrective action record answers five questions, and a CHSO auditing another contractor's system should look for exactly these:

What failed — the condition or behaviour, stated factually.

Why it failed — the root cause, not the immediate act. "Worker did not clip on" is an immediate cause; "no anchor point within reach of the leading edge, and the fall protection plan was not revised when the slab layout changed" is a root cause.

What will change — the control, at the highest practicable level of the hierarchy.

Who owns it and by when — a named person and a date, not "management" and "ASAP".

How effectiveness was verified — a re-check, dated and signed, after the due date.

The fifth is the one South African sites most often omit, and its absence is why the same finding reappears in three consecutive monthly audits.

4. Management Review

Clause 9.3 requires top management to review the system at planned intervals. On a construction project the review is usually monthly or quarterly and must consider, at minimum: the status of actions from the previous review; changes in external and internal issues including legal requirements ; the extent to which objectives have been met; incident, non-conformity and corrective action trends; monitoring and measurement results; audit results; consultation and participation of workers; risks and opportunities; and the adequacy of resources.

The output is not minutes. The outputs required by clause 9.3 are decisions: on the continuing suitability, adequacy and effectiveness of the system; on opportunities for improvement; on any need for change; and — critically on construction projects — on resources . A management review that identifies inadequate supervision ratios and does not resolve to fund more supervisors has produced a record, not a review.

Under CR 7(1)(a) the review has a statutory consequence: where the review shows the health and safety plan no longer matches the work, the plan must be updated. That is the point at which a management system stops being documentation and starts being management.

Loading diagram... Management Review Inputs, Decisions and the CR 7(1)(a) Feedback Loop