AACE CCP

AACE Certified Cost Professional

Quick practiceEnglish
Exam overview

Practice session

A project reports percent complete = 30%, EV = $300K, PV = $350K, AC = $310K, BAC = $1,000K. Compute SPI and interpret schedule status.

Loading your practice session…