AACE CCP

AACE Certified Cost Professional

Project Cost ManagementEnglish
Exam overview

Practice session

A project shows the following at month 6: Planned Value (PV) = $200,000, Earned Value (EV) = $180,000, Actual Cost (AC) = $210,000. What is the Cost Performance Index (CPI)?

Loading your practice session…