NASCLA Contractor

Nascla Project ManagementEnglish
Exam overview

Practice session

In a CPM schedule, Activity A has 5 days duration and Activity B has 8 days duration. Activity B cannot start until Activity A is complete. Activity C can start when both A and B are complete. What is the earliest Activity C can start?

Loading your practice session…