Project coordinator Excel test
A project task list with owners, dates and status. Count by status, find overdue work, average planned duration and load by owner.
Browse all Excel tests by topic or by job.
Your test
Project plan as of May 31, 2026. Tasks sheet has owners, dates and status. Leadership wants schedule health, not a pretty Gantt.
| ATaskID | BTask | COwner | DStartDate | EDueDate | FStatus | |
|---|---|---|---|---|---|---|
| 2 | T-1 | Task 1 | Mei Patel | 2026-01-17 | 2026-02-23 | In progress |
| 3 | T-2 | Task 2 | Hannah Nakamura | 2026-06-18 | 2026-08-02 | In progress |
| 4 | T-3 | Task 3 | Kwame Walsh | 2026-07-19 | 2026-08-02 | Blocked |
| 5 | T-4 | Task 4 | Hannah Nakamura | 2026-08-18 | 2026-09-17 | Not started |
| 6 | T-5 | Task 5 | Kwame Walsh | 2026-08-21 | 2026-08-27 | Blocked |
| 7 | T-6 | Task 6 | Mei Patel | 2026-07-21 | 2026-08-30 | Blocked |
| 8 | T-7 | Task 7 | Mei Patel | 2026-07-11 | 2026-08-14 | In progress |
| 9 | T-8 | Task 8 | Kwame Walsh | 2026-05-05 | 2026-05-18 | Done |
| 10 | T-9 | Task 9 | Priya Grant | 2026-10-27 | 2026-11-23 | Not started |
| 11 | T-10 | Task 10 | Kwame Walsh | 2026-03-22 | 2026-04-10 | Not started |
| 12 | T-11 | Task 11 | Liam Patel | 2026-09-01 | 2026-10-12 | Done |
| 13 | T-12 | Task 12 | Priya Grant | 2026-08-18 | 2026-09-05 | Blocked |
| 14 | T-13 | Task 13 | Priya Grant | 2026-06-15 | 2026-06-24 | Done |
| 15 | T-14 | Task 14 | Kwame Walsh | 2026-06-08 | 2026-06-18 | Not started |
| 16 | T-15 | Task 15 | Kwame Walsh | 2026-04-16 | 2026-05-21 | Done |
| 17 | T-16 | Task 16 | Mei Patel | 2026-06-14 | 2026-06-23 | Done |
| 18 | T-17 | Task 17 | Kwame Walsh | 2026-10-11 | 2026-10-18 | Blocked |
| 19 | T-18 | Task 18 | Mei Patel | 2026-04-10 | 2026-04-23 | In progress |
| 20 | T-19 | Task 19 | Mei Patel | 2026-09-13 | 2026-10-19 | Not started |
| 21 | T-20 | Task 20 | Liam Patel | 2026-04-13 | 2026-05-03 | Not started |
| 22 | T-21 | Task 21 | Hannah Nakamura | 2026-03-11 | 2026-03-31 | Blocked |
| 23 | T-22 | Task 22 | Liam Patel | 2026-03-03 | 2026-04-09 | In progress |
| 24 | T-23 | Task 23 | Mei Patel | 2026-04-11 | 2026-04-27 | Blocked |
| 25 | T-24 | Task 24 | Liam Patel | 2026-03-23 | 2026-04-14 | Not started |
| 26 | T-25 | Task 25 | Mei Patel | 2026-07-16 | 2026-07-21 | Not started |
| 27 | T-26 | Task 26 | Priya Grant | 2026-01-16 | 2026-01-31 | In progress |
| 28 | T-27 | Task 27 | Kwame Walsh | 2026-06-03 | 2026-06-30 | Blocked |
| 29 | T-28 | Task 28 | Priya Grant | 2026-09-11 | 2026-09-18 | In progress |
| 30 | T-29 | Task 29 | Priya Grant | 2026-08-18 | 2026-08-29 | Blocked |
| 31 | T-30 | Task 30 | Kwame Walsh | 2026-01-26 | 2026-02-14 | Not started |
| 32 | T-31 | Task 31 | Liam Patel | 2026-04-27 | 2026-05-05 | Not started |
| 33 | T-32 | Task 32 | Mei Patel | 2026-03-13 | 2026-04-12 | Not started |
| 34 | T-33 | Task 33 | Liam Patel | 2026-09-18 | 2026-10-08 | Blocked |
| 35 | T-34 | Task 34 | Mei Patel | 2026-04-08 | 2026-04-26 | In progress |
| 36 | T-35 | Task 35 | Hannah Nakamura | 2026-04-06 | 2026-05-09 | Not started |
| 37 | T-36 | Task 36 | Hannah Nakamura | 2026-05-03 | 2026-06-16 | Not started |
| 38 | T-37 | Task 37 | Hannah Nakamura | 2026-07-21 | 2026-09-01 | Blocked |
| 39 | T-38 | Task 38 | Kwame Walsh | 2026-06-15 | 2026-07-30 | Not started |
| 40 | T-39 | Task 39 | Hannah Nakamura | 2026-09-05 | 2026-09-18 | Blocked |
| 41 | T-40 | Task 40 | Priya Grant | 2026-02-13 | 2026-03-14 | Blocked |
Copy each sheet into Excel or Google Sheets (click A1, paste) or download the CSV, then answer below. Use any method you like; only your answers are graded.
What this test covers
| # | The task | Skills it checks |
|---|---|---|
| 1 | How many tasks are Done? | COUNTIF |
| 2 | How many tasks are Blocked? | COUNTIF |
| 3 | How many tasks are overdue (DueDate before May 31, 2026 and Status is not Done)? | COUNTIFS, Dates |
| 4 | What is the average planned duration in days (DueDate − StartDate)? Round to 1 decimal place. | AVERAGE, Dates |
| 5 | How many open tasks (Status ≠ Done) does Priya Grant own? | COUNTIFS |
COUNTIF by status, overdue date logic, duration math and workload totals per owner.
How to get faster
- Overdue usually means Due < as-of and Status is not Done — confirm against the brief.
- Duration is end minus start (or Planned Days); don’t mix calendar and workday math unless asked.
- Owner load is a COUNTIF or pivot on Owner for open tasks.
Questions people ask
Is this a PMP or Jira test?
No. Spreadsheet practice for coordinators who track tasks in Excel or exports.
How long?
About 20 minutes.
Keep practicing
Excel assessment test
8 questions, about 25 minutes. Lookups, conditional sums, dates.
ExcelExcel interview test
6 interview-style questions on a shipments sheet.
ExcelAdministrative assistant Excel test
Dedupe clients, chase overdue invoices, total orders.
ExcelAccounts payable Excel test
Duplicate bills, PO mismatches, aging buckets.
ExcelExcel charts test
Column, line and pie: peak month, slice share, chart-type choices.
ExcelExcel regression test
SLOPE, INTERCEPT, RSQ, CORREL, FORECAST on noisy data.
ExcelBookkeeper Excel test
Bank reconciliation: uncleared items and amount mismatches.
ExcelSales coordinator Excel test
Pipeline coverage, win rate and Closed Won totals.