Project coordinator Excel test

A project task list with owners, dates and status. Count by status, find overdue work, average planned duration and load by owner.

Browse all Excel tests by topic or by job.

Your test

Project plan as of May 31, 2026. Tasks sheet has owners, dates and status. Leadership wants schedule health, not a pretty Gantt.

Test #3701 5 questions about 20 min 0:00
Tasks · 40 rows · header in row 1
ATaskIDBTaskCOwnerDStartDateEDueDateFStatus
2T-1Task 1Mei Patel2026-01-172026-02-23In progress
3T-2Task 2Hannah Nakamura2026-06-182026-08-02In progress
4T-3Task 3Kwame Walsh2026-07-192026-08-02Blocked
5T-4Task 4Hannah Nakamura2026-08-182026-09-17Not started
6T-5Task 5Kwame Walsh2026-08-212026-08-27Blocked
7T-6Task 6Mei Patel2026-07-212026-08-30Blocked
8T-7Task 7Mei Patel2026-07-112026-08-14In progress
9T-8Task 8Kwame Walsh2026-05-052026-05-18Done
10T-9Task 9Priya Grant2026-10-272026-11-23Not started
11T-10Task 10Kwame Walsh2026-03-222026-04-10Not started
12T-11Task 11Liam Patel2026-09-012026-10-12Done
13T-12Task 12Priya Grant2026-08-182026-09-05Blocked

Copy each sheet into Excel or Google Sheets (click A1, paste) or download the CSV, then answer below. Use any method you like; only your answers are graded.

  1. COUNTIF

  2. COUNTIF

  3. COUNTIFSDates

  4. AVERAGEDates

  5. COUNTIFS

What this test covers

#The taskSkills it checks
1How many tasks are Done?COUNTIF
2How many tasks are Blocked?COUNTIF
3How many tasks are overdue (DueDate before May 31, 2026 and Status is not Done)?COUNTIFS, Dates
4What is the average planned duration in days (DueDate − StartDate)? Round to 1 decimal place.AVERAGE, Dates
5How many open tasks (Status ≠ Done) does Priya Grant own?COUNTIFS

COUNTIF by status, overdue date logic, duration math and workload totals per owner.

How to get faster

  • Overdue usually means Due < as-of and Status is not Done — confirm against the brief.
  • Duration is end minus start (or Planned Days); don’t mix calendar and workday math unless asked.
  • Owner load is a COUNTIF or pivot on Owner for open tasks.

Questions people ask

Is this a PMP or Jira test?

No. Spreadsheet practice for coordinators who track tasks in Excel or exports.

How long?

About 20 minutes.

Keep practicing

Browse all tests by type, topic or job

Browse Excel-only tests by topic or by job